RDM CONCRETE & MASONRY, LLC VS. SURFSIDE CASUAL FURNITURE (L-2182-13, OCEAN COUNTY AND STATEWIDE)

CourtNew Jersey Superior Court Appellate Division
DecidedAugust 4, 2020
DocketA-1077-17T2
StatusUnpublished

This text of RDM CONCRETE & MASONRY, LLC VS. SURFSIDE CASUAL FURNITURE (L-2182-13, OCEAN COUNTY AND STATEWIDE) (RDM CONCRETE & MASONRY, LLC VS. SURFSIDE CASUAL FURNITURE (L-2182-13, OCEAN COUNTY AND STATEWIDE)) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
RDM CONCRETE & MASONRY, LLC VS. SURFSIDE CASUAL FURNITURE (L-2182-13, OCEAN COUNTY AND STATEWIDE), (N.J. Ct. App. 2020).

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION DOCKET NO. A-1077-17T2

RDM CONCRETE & MASONRY, LLC,

Plaintiff-Respondent,

v.

SURFSIDE CASUAL FURNITURE, ROBERT A. HIMMELSTEIN and STEPHANIE L. HIMMELSTEIN,

Defendants-Appellants. ________________________________

SURFSIDE CASUAL FURNITURE,

Third-Party Plaintiff,

MARK CIULLO and RYAN CIULLO,

Third-Party Defendants- Respondents. ________________________________

Fourth-Party Plaintiff, v.

SL MACINTYRE UNDERGROUND, LLC,

Fourth-Party Defendant. ________________________________

Fifth-Party Plaintiff,

SURFSIDE CASUAL FURNITURE, ROBERT A. HIMMELSTEIN and STEPHANIE L. HIMMELSTEIN,

Fifth-Party Defendant. ________________________________

Argued February 24, 2020 – Decided August 4, 2020

Before Judges Ostrer and Vernoia.

On appeal from the Superior Court of New Jersey, Law Division, Ocean County, Docket No. L-2182-13.

William D. Wright argued the cause for appellants (The Wright Law Firm; attorneys; William D. Wright and David T. Wright, on the briefs).

Paul John Endler, Jr. and Edward Francis Bezdecki argued the cause for respondent RDM Concrete & Masonry, LLC (Methfessel & Werbel, attorneys; Paul John Endler, Jr. and Steven Andrew Unterburger, on the brief).

A-1077-17T2 2 PER CURIAM

Defendant-counterclaimant Surfside Casual Furniture (defendant) appeals

from a final judgment following a jury trial finding it breached a contract by

failing to pay sums due for concrete work plaintiff RDM Concrete & Masonry,

LLC (plaintiff) performed during the construction of defendant's Manahawkin

furniture store. Defendant claims the court erred by dismissing its Consumer

Fraud Act (CFA), N.J.S.A. 56:8-1 to 56:8-224, claims against plaintiff and its

owner, defendant Mark Ciullo, and employee, Ryan Ciullo; by incorrectly

admitting into evidence a letter defendant claims constituted inadmissible

hearsay; and by dismissing a portion of defendant's damage claim by applying

the economic waste doctrine. Having reviewed the record and arguments of the

parties in light of the applicable law, we affirm.

I.

We summarize the facts to provide context for the specific issues raised

on appeal.

Defendant has been in the retail furniture business for many years. This

appeal arises out of the construction of defendant's Manahawkin furniture store.

Robert Himmelstein is defendant's president, and he acted as the general

contractor for the store's construction. As the general contractor, he hired the

A-1077-17T2 3 professionals and contractors for the work required for the building's

construction, from obtaining the necessary municipal approvals through the

excavation of the land and the completion of the site work after the building was

fully constructed and ready for occupancy. He testified that, as the general

contractor, he "directed [the contractors as to] what to do on . . . their job[s]."

As designed, the store consists of a prefabricated metal building that sits

on a 175-foot by 100-foot concrete slab. The building has an open floor plan

with a second-floor concrete mezzanine deck, which abuts three sides of the

building in the shape of a "U," that is open to the first floor.

Plaintiff is a concrete contractor. Mark Ciullo is plaintiff's president and

his son, Ryan Ciullo, is an employee. In 2012, Himmelstein sought referrals for

concrete contractors and was referred to plaintiff. Himmelstein met with three

or four other concrete contractors, but in September 2012, he selected plaintiff

as the project's concrete contractor.

Himmelstein also hired other contractors and professionals in connection

with the construction of the building. He employed an architect, a civil engineer,

a steel contractor, Stephlynn Ironworks, LLC (Stephlynn), and many other

contractors. During his testimony at trial, Himmelstein denied he directly

employed a structural engineer for the project, but he relied on the work of

A-1077-17T2 4 Nelson Structural Engineering, which did business by the tradename Nel-Struct,

during the project. Dennis S. Nelson (Nelson) is an employee of Nel-Struct.

Himmelstein also employed Craig Testing to test "the concrete and inspect[] the

job" for plaintiff.

In September 2012, plaintiff provided defendant with a proposal for the

concrete work on the project. Himmelstein testified he had "a lot" of

conversations with Ryan Ciullo prior to the proposal, and it can be reasonably

inferred the proposal was the product of many discussions between Himmelstein

and plaintiff because the proposal identifies ten separate tasks plaintiff offered

to perform. The proposal also references Nel-Struct's plans for the building that

Himmelstein testified were supplied to him by Stephlynn. The plans did not

include wire mesh reinforcement for the mezzanine concrete, but, according to

Himmelstein, Ryan Ciullo suggested the inclusion of wire mesh during their pre-

proposal discussions. The proposal included wire mesh in the mezzanine

concrete.

Himmelstein accepted plaintiff's proposal, but Nel-Struct's final plans

were not provided until November 2012. Himmelstein testified about the goods

and services plaintiff was required to provide and perform under the proposal.

Plaintiff was responsible for laying out the building from established points to

A-1077-17T2 5 ensure it was located where it was "supposed to be." Plaintiff was also retained

to perform the "[f]ooting, pier and elevator pit excavation," "[s]upply and install

steel reinforcement in footings, pier footings, and elevator pit," pour concrete

for the building's elevator, form the walls, and place and finish the concrete for

the elevator pit foundation.

Plaintiff was also responsible for digging out the area where the building

slab was to be placed and making a "monolithic pour" of concrete for the

footings and a 175 foot by 100 foot slab "at the same time." According to

Himmelstein, plaintiff was also required to construct a concrete block elevator

shaft, pour concrete for the mezzanine slab, and install concrete stair pans.

In January 2013, plaintiff completed what is described as a "monolithic"

two-day pour of over 700 cubic feet of concrete for the building's footings and

slab. Himmelstein was present for the pour, as was Craig Testing, an inspection

service Himmelstein employed to "test[] . . . the concrete and inspect[] the job

for" plaintiff. Prior to the pour, Himmelstein agreed to an increase in the price

for the concrete because a chemical additive was necessary due to the winter

conditions. Himmelstein approved the price increase after receiving

correspondence from Stephlynn indicating that Nelson from Nel-Struct

indicated the change in the concrete mix was acceptable.

A-1077-17T2 6 Himmelstein later approved a change order for the addition of fiber mesh

to the concrete that was poured in May 2013 for the mezzanine. He testified he

agreed to the price increase because he understood the fiber mesh was being

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anthony D'agostino v. Ricardo Maldonado (068940)
78 A.3d 527 (Supreme Court of New Jersey, 2013)
Verdicchio v. Ricca
843 A.2d 1042 (Supreme Court of New Jersey, 2004)
State v. Reddish
859 A.2d 1173 (Supreme Court of New Jersey, 2004)
Bosland v. Warnock Dodge, Inc.
964 A.2d 741 (Supreme Court of New Jersey, 2009)
State v. Moore
385 A.2d 867 (New Jersey Superior Court App Division, 1978)
Godfrey v. Princeton Theological Seminary
952 A.2d 1034 (Supreme Court of New Jersey, 2008)
State v. Mays
729 A.2d 1074 (New Jersey Superior Court App Division, 1999)
Estate of Roach v. Trw, Inc.
754 A.2d 544 (Supreme Court of New Jersey, 2000)
Cox v. Sears Roebuck & Co.
647 A.2d 454 (Supreme Court of New Jersey, 1994)
Finderne Mgmt. Co. v. Barrett
955 A.2d 940 (New Jersey Superior Court App Division, 2008)
D'Ercole Sales, Inc. v. Fruehauf Corp.
501 A.2d 990 (New Jersey Superior Court App Division, 1985)
State v. Lykes
933 A.2d 1274 (Supreme Court of New Jersey, 2007)
Coastal Group v. Dryvit Systems
643 A.2d 649 (New Jersey Superior Court App Division, 1994)
Princeton Healthcare v. Netsmart
29 A.3d 361 (New Jersey Superior Court App Division, 2011)
State v. Rose
19 A.3d 985 (Supreme Court of New Jersey, 2011)
Tahir Zaman v. Barbara Felton (072128)
98 A.3d 503 (Supreme Court of New Jersey, 2014)
State v. Julie Kuropchak
113 A.3d 1174 (Supreme Court of New Jersey, 2015)
Hon. Dana L. Redd v. Vance Bowman(073567)
121 A.3d 341 (Supreme Court of New Jersey, 2015)
State of New Jersey v. Walter A. Tormasi
128 A.3d 182 (New Jersey Superior Court App Division, 2015)
State of New Jersey v. Kason D. Hockett
129 A.3d 1116 (New Jersey Superior Court App Division, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
RDM CONCRETE & MASONRY, LLC VS. SURFSIDE CASUAL FURNITURE (L-2182-13, OCEAN COUNTY AND STATEWIDE), Counsel Stack Legal Research, https://law.counselstack.com/opinion/rdm-concrete-masonry-llc-vs-surfside-casual-furniture-l-2182-13-ocean-njsuperctappdiv-2020.