RCO Engineering, Inc. v. ACR Industries, Inc.

246 Mich. App. 510
CourtMichigan Court of Appeals
DecidedJune 22, 2001
DocketDocket No. 201436
StatusPublished
Cited by1 cases

This text of 246 Mich. App. 510 (RCO Engineering, Inc. v. ACR Industries, Inc.) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
RCO Engineering, Inc. v. ACR Industries, Inc., 246 Mich. App. 510 (Mich. Ct. App. 2001).

Opinion

Per Curiam.

This case returns to us on remand from our Supreme Court. In lieu of granting plaintiff leave to appeal, the Supreme Court vacated part n of our prior opinion1 and directed us to consider “whether the trial court erred in denying plaintiff’s motion in limine on the ground that defendant was permitted to present evidence regarding the cost-effectiveness of a "Type B’ cleanup despite the [Michigan Department of Natural Resources’] ‘approval’ of the ‘Type A’ cleanup.” 463 Mich 893 (2000). We conclude that had the dnr approved the Type A cleanup of the site, the trial court’s denial of defendants’ motion in limine would not have been in error. Further, because the issue whether the dnr had approved the Type A cleanup was contested below, we conclude that the trial court did not err in permitting evidence of the disputed cost-effectiveness of the cleanup to be considered by the jury.

I

The underlying facts of this case were set forth in our prior opinion:

In 1968, defendant Roger W. Blanchard and others purchased some vacant property located in Roseville, Michigan. Facilities constructed on the property by a predecessor company to defendant ACR Industries, Inc., (hereinafter ACR) were used by ACR and its predecessor from 1968 [513]*513until 1988. Both ACR and its predecessor manufactured aerospace equipment at these facilities. In 1968, ACR’s predecessor placed a three thousand-gallon underground storage tank on the property. Petroleum products used by ACR during the manufacturing process were routinely dumped into the tank. ACR continued to use the tank until ACR moved from the property in 1988.
In 1987, Paul Carollo, a founder of plaintiff corporation, purchased the property from defendants Robert and Mary Kazmarek, and Blanchard. The property was then leased to plaintiff. In 1991, plaintiff began the process of removing the storage tank. In July of that year, plaintiff confirmed that there had been a release of hazardous substances from the tank. At the time, administrative rules promulatged by the [dnr] under the then-current version of the Michigan Environmental Response Act (MERA), MCL 299.601 et seq.; MSA 13.32(1) et seq., identified three distinct types of cleanup that could be done on a site contaminated by the discharge of hazardous substances. These cleanup types were labeled “Type A,” “Type B,” and “Type C.”. . . Plaintiff chose to remediate the site using a Tfype A cleanup.
In January 1993, plaintiff brought suit against defendants under the mera. Plaintiff alleged that ACR was liable for approximately $1.5 million in response activity costs incurred in cleaning up contamination of the property caused by the leaking of hazardous substances from the storage tank. ... At trial, the parties hotly contested whether a Type A or Type B cleanup should have been used to remediate the site and whether the issue of cost should enter into any examination of the appropriate type of cleanup.
A jury found that although defendants were liable, plaintiff failed to establish that any response activity costs in excess of $990,000 were necessary. Given that plaintiff had already been reimbursed $990,000 by the state pursuant to the then-current version of the Michigan Underground Storage Tank Financial Assurance Act (mustfa), MCL 299.801 et seq.; MSA 13.29(201) et seq., plaintiff took nothing on its claim.!2!

[514]*514The mera was repealed by the Legislature effective March 30, 1995. 1994 PA 451. The mera’s provisions were recodified as Part 201 (Environmental Response), MCL 324.20101 et seq., of the Natural Resources and Environmental Protection Act (nrepa), MCL 324.101 et seq. Pursuant to MCL 324.102, repeal of the MERA “does not relinquish any penalty, forfeiture, or liability, whether criminal or civil in nature, and such statute shall be treated as still remaining in force as necessary for the purpose of instituting or sustaining any proper action or prosecution for the enforcement of the penalty, forfeiture, or liability.” Further, while Part 201 of the nrepa was amended twice in 1995, 1995 PA 71 and 1995 PA 117, those amendments do not apply to the case at hand, given that it was initiated before May 1, 1995. MCL 324.20102a(1)(a). Accordingly, all statutory references in this opinion will be to the prior provisions and compiled law numbers in effect during the relevant portions of the proceedings below.

Plaintiffs motion in limine3 asked the trial court to strike defendants’ first and second defenses and to foreclose defendants from presenting any evidence on their claim that the Type A cleanup was excessive. Defendants’ first affirmative defense stated that “[plaintiffs claims are barred for the reason that its costs associated with its alleged corrective response and/or remediation activities incurred are excessive, unnecessary and were not reasonable when paid.” Defendants’ second affirmative defense stated that

[515]*515[p]laintiff’s claims for reimbursement for costs associated with its alleged corrective, response and/or remediation activity incurred were not necessary response costs as any cleanup activity was not consistent with or required by or, alternatively, went beyond what was required by the state or federal statutes, regulations and guidelines regulating the section and/or implementation of response and/or remediation activity[4]
The trial court denied plaintiffs motion. Citing the legislative history of the 1990 amendment of the mera,5 the trial court drew the following conclusions:
Considering the purpose of the statute and rule, it would be consistent to require a private party to consider the relative criteria applicable to the dnr when selecting remedial alternatives. To allow a private party to select a type of remedy which does not offer any greater protection for the environment but is much more costly than other altema-[516]*516tives is not consistent with the intent of the legislature to control the cost of cleanup to encourage development.

The criteria found in rule 603(1)[6] should apply when a private party selects the type of cleanup. The rules require consideration of the cost of cleanup when choosing among alternatives which adequately protect the environment. 1990 AACS 299.5601(3).[7] Since the DNR has determined that type A and Type B remedies equally protect the environment, the rule should be construed to require consideration of cost. [517]*517Directly addressing the issue of possible approval of plaintiffs plan by the dnr, the trial court concluded:

The DNR’s approval of the type A plan does not preclude subsequent challenges of the selection. Plaintiff has failed to cite any authority to support a claim that potentially responsible parties (prps) can not challenge the agency’s decisions. Defendants were not parties to the decision making process at the agency level. There is evidence the dnr questioned whether this cleanup was excessive.

We do not read the first line of the immediately preceding passage as rendering a judicial finding that the DNR had approved the Type A cleanup of the site.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tennine Corp. v. Boardwalk Commercial, LLC
315 Mich. App. 1 (Michigan Court of Appeals, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
246 Mich. App. 510, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rco-engineering-inc-v-acr-industries-inc-michctapp-2001.