RCIS Enterprises, LLC v. Houser Fabrication, LLC
This text of RCIS Enterprises, LLC v. Houser Fabrication, LLC (RCIS Enterprises, LLC v. Houser Fabrication, LLC) is published on Counsel Stack Legal Research, covering Texas Court of Appeals, 6th District (Texarkana) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
In the Court of Appeals Sixth Appellate District of Texas at Texarkana
No. 06-23-00088-CV
RCIS ENTERPRISES, LLC, Appellant
V.
HOUSER FABRICATION, LLC, Appellee
On Appeal from the 336th District Court Fannin County, Texas Trial Court No. CV-21-45560
Before Stevens, C.J., van Cleef and Rambin, JJ. Memorandum Opinion by Justice Rambin MEMORANDUM OPINION
RCIS Enterprises, LLC, (RCIS) appeals a part of the trial court’s judgment entered
following a bench trial in which Houser Fabrication, LLC, (Houser) recovered breach of contract
damages in the amount of $78,491.10, prejudgment interest under the Texas Prompt Payment
Act, attorney fees, post-judgment interest, and costs.1 On appeal, RCIS contends that there is
legally insufficient evidence supporting the trial court’s findings of fact and conclusions of law
that (1) the parties entered into a legally enforceable contract, (2) the amount of damages
awarded to Houser, and (3) the award of prompt payment interest. RCIS also contends that the
trial court erred in awarding Houser attorney fees and that the amount of fees awarded was
excessive. RCIS further contends that the trial court erroneously released interpleaded funds to
Houser. We find that legally sufficient evidence supports the trial court’s findings and
conclusions that the parties entered into a legally enforceable contract. However, the evidence is
legally insufficient to support the amount of damages, in part, and the award of prompt payment
interest. We will remand this case for a new trial on attorney fees, a determination of
prejudgment interest, and the entry of a final judgment consistent with this opinion.
I. The Trial Court’s Finding of a Legally Enforceable Contract is Supported by Legally Sufficient Evidence
A. Standard of Review
In a legal sufficiency challenge, we determine “whether the evidence at trial would
enable reasonable and fair-minded people to reach the verdict under review.” City of Keller v.
1 In the trial court’s judgment, RCIS recovered $10,478.37 and prejudgment interest on its counterclaim for damages related to an unrelated contract (the Bellaire Project). That part of the judgment awarding damages to RCIS was not appealed. The amount of Houser’s award was offset by RCIS’s award. 2 Wilson, 168 S.W.3d 802, 827 (Tex. 2005). For a bench trial, the trial court’s findings of fact “are
of the same force and dignity as a jury’s answers to jury questions.” .39 Acres v. State, 247
S.W.3d 384, 387 (Tex. App.—Texarkana 2008, pet. denied) (citing Anderson v. City of Seven
Points, 806 S.W.2d 791, 794 (Tex. 1991)). As a result, “[w]e review the findings of fact by the
same standards that are applied in reviewing the legal or factual sufficiency of the evidence
supporting a jury’s answer to a jury question.” Lambright v. Trahan, 322 S.W.3d 424, 430 (Tex.
App.—Texarkana 2010, pet denied) (citing .39 Acres, 247 S.W.3d at 387).
In determining legal sufficiency, “we credit favorable evidence if a reasonable fact-finder
could, and disregard contrary evidence unless a reasonable fact-finder could not.” Ramsay v.
Tex. Trading Co., 254 S.W.3d 620, 625 (Tex. App.—Texarkana 2008, pet. denied) (citing City of
Keller, 168 S.W.3d at 827). “[W]e consider the evidence in a light most favorable to the
challenged findings, indulging every reasonable inference that supports them, [but] we may not
disregard evidence that allows only one inference.” Id. (citing City of Keller, 168 S.W.3d at
822). Also, “we credit favorable evidence if a reasonable fact-finder could, and disregard
contrary evidence unless a reasonable fact-finder could not.” Id. (citing City of Keller, 168
S.W.3d at 827). Because the trial court is the trier of fact, it “is the sole judge of the credibility
of the witnesses and the weight to give their testimony.” Id. (citing City of Keller, 168 S.W.3d at
819).
“When determining whether legally sufficient evidence supports a jury finding, we must
consider evidence favorable to the finding if a reasonable factfinder could and disregard
evidence contrary to the finding unless a reasonable factfinder could not.” Albertsons, LLC v.
3 Mohammadi, 689 S.W.3d 313, 318 n.2 (Tex. 2024) (per curiam) (quoting 4Front Engineered
Sols., Inc. v. Rosales, 505 S.W.3d 905, 908 (Tex. 2016)). “The evidence is legally sufficient if
[there] is more than a scintilla of evidence on which a reasonable juror could find the fact to be
true.” Id. (alteration in original) (quoting 4Front Engineered Sols., Inc., 505 S.W.3d at 909).
“More than a scintilla of evidence exists when the evidence reaches a level enabling reasonable
and fair-minded people to differ in their conclusions.” Petrohawk Props., L.P. v. Jones, 455
S.W.3d 753, 770 (Tex. App.—Texarkana 2015, pet. dism’d) (citing Merrell Dow Pharms., Inc.
v. Havner, 953 S.W.2d 706, 711 (Tex. 1997)). “Less than a scintilla of evidence exists when the
evidence is ‘so weak as to do no more than create a mere surmise or suspicion’ of a fact.” King
Ranch, Inc. v. Chapman, 118 S.W.3d 742, 751 (Tex. 2003) (quoting Kindred v. Con/Chem, Inc.,
650 S.W.2d 61, 63 (Tex. 1983)).
B. Applicable Law
“The requirements of written and oral contracts are the same and must be present for a
contract to be binding.” Lloyd Walterscheid & Walterscheid Farms, LLC v. Waltersheid, 557
S.W.3d 245, 258 (Tex. App.—Fort Worth 2018, no pet.) (citing Critchfield v. Smith, 151 S.W.3d
225, 233 (Tex. App.—Tyler 2004, pet. denied)). To form a binding contract there must be
“(1) an offer, (2) an acceptance in strict compliance with the terms of the offer, (3) a meeting of
the minds, (4) each party’s consent to the terms, and (5) execution and delivery of the contract
with the intent that it be mutual and binding.” KW Const. v. Stephens & Sons Concrete
Contractors, Inc., 165 S.W.3d 874, 883 (Tex. App.—Texarkana 2005, pet. denied) (citing
Buxani v. Nussbaum, 940 S.W.2d 350, 352 (Tex. App.—San Antonio 1997, no writ)).
4 “To be enforceable, a contract must address all of its essential and material terms with ‘a
reasonable degree of certainty and definiteness.’” Fischer v. CTMI, L.L.C., 479 S.W.3d 231, 237
(Tex. 2016) (quoting Pace Corp. v. Jackson, 284 S.W.2d 340, 345 (Tex. 1955)). At the least, a
contract “must . . . be sufficiently definite to confirm that both parties actually intended to be
contractually bound.” Id. (citing Fort Worth Indep. Sch. Dist. v. City of Fort Worth, 22 S.W.3d
831, 846 (Tex. 2000)). Further, “the agreement’s terms must . . . be sufficiently definite to
‘enable a court to understand the parties’ obligations,’” id. (quoting Forth Worth Indep. Sch.
Free access — add to your briefcase to read the full text and ask questions with AI
In the Court of Appeals Sixth Appellate District of Texas at Texarkana
No. 06-23-00088-CV
RCIS ENTERPRISES, LLC, Appellant
V.
HOUSER FABRICATION, LLC, Appellee
On Appeal from the 336th District Court Fannin County, Texas Trial Court No. CV-21-45560
Before Stevens, C.J., van Cleef and Rambin, JJ. Memorandum Opinion by Justice Rambin MEMORANDUM OPINION
RCIS Enterprises, LLC, (RCIS) appeals a part of the trial court’s judgment entered
following a bench trial in which Houser Fabrication, LLC, (Houser) recovered breach of contract
damages in the amount of $78,491.10, prejudgment interest under the Texas Prompt Payment
Act, attorney fees, post-judgment interest, and costs.1 On appeal, RCIS contends that there is
legally insufficient evidence supporting the trial court’s findings of fact and conclusions of law
that (1) the parties entered into a legally enforceable contract, (2) the amount of damages
awarded to Houser, and (3) the award of prompt payment interest. RCIS also contends that the
trial court erred in awarding Houser attorney fees and that the amount of fees awarded was
excessive. RCIS further contends that the trial court erroneously released interpleaded funds to
Houser. We find that legally sufficient evidence supports the trial court’s findings and
conclusions that the parties entered into a legally enforceable contract. However, the evidence is
legally insufficient to support the amount of damages, in part, and the award of prompt payment
interest. We will remand this case for a new trial on attorney fees, a determination of
prejudgment interest, and the entry of a final judgment consistent with this opinion.
I. The Trial Court’s Finding of a Legally Enforceable Contract is Supported by Legally Sufficient Evidence
A. Standard of Review
In a legal sufficiency challenge, we determine “whether the evidence at trial would
enable reasonable and fair-minded people to reach the verdict under review.” City of Keller v.
1 In the trial court’s judgment, RCIS recovered $10,478.37 and prejudgment interest on its counterclaim for damages related to an unrelated contract (the Bellaire Project). That part of the judgment awarding damages to RCIS was not appealed. The amount of Houser’s award was offset by RCIS’s award. 2 Wilson, 168 S.W.3d 802, 827 (Tex. 2005). For a bench trial, the trial court’s findings of fact “are
of the same force and dignity as a jury’s answers to jury questions.” .39 Acres v. State, 247
S.W.3d 384, 387 (Tex. App.—Texarkana 2008, pet. denied) (citing Anderson v. City of Seven
Points, 806 S.W.2d 791, 794 (Tex. 1991)). As a result, “[w]e review the findings of fact by the
same standards that are applied in reviewing the legal or factual sufficiency of the evidence
supporting a jury’s answer to a jury question.” Lambright v. Trahan, 322 S.W.3d 424, 430 (Tex.
App.—Texarkana 2010, pet denied) (citing .39 Acres, 247 S.W.3d at 387).
In determining legal sufficiency, “we credit favorable evidence if a reasonable fact-finder
could, and disregard contrary evidence unless a reasonable fact-finder could not.” Ramsay v.
Tex. Trading Co., 254 S.W.3d 620, 625 (Tex. App.—Texarkana 2008, pet. denied) (citing City of
Keller, 168 S.W.3d at 827). “[W]e consider the evidence in a light most favorable to the
challenged findings, indulging every reasonable inference that supports them, [but] we may not
disregard evidence that allows only one inference.” Id. (citing City of Keller, 168 S.W.3d at
822). Also, “we credit favorable evidence if a reasonable fact-finder could, and disregard
contrary evidence unless a reasonable fact-finder could not.” Id. (citing City of Keller, 168
S.W.3d at 827). Because the trial court is the trier of fact, it “is the sole judge of the credibility
of the witnesses and the weight to give their testimony.” Id. (citing City of Keller, 168 S.W.3d at
819).
“When determining whether legally sufficient evidence supports a jury finding, we must
consider evidence favorable to the finding if a reasonable factfinder could and disregard
evidence contrary to the finding unless a reasonable factfinder could not.” Albertsons, LLC v.
3 Mohammadi, 689 S.W.3d 313, 318 n.2 (Tex. 2024) (per curiam) (quoting 4Front Engineered
Sols., Inc. v. Rosales, 505 S.W.3d 905, 908 (Tex. 2016)). “The evidence is legally sufficient if
[there] is more than a scintilla of evidence on which a reasonable juror could find the fact to be
true.” Id. (alteration in original) (quoting 4Front Engineered Sols., Inc., 505 S.W.3d at 909).
“More than a scintilla of evidence exists when the evidence reaches a level enabling reasonable
and fair-minded people to differ in their conclusions.” Petrohawk Props., L.P. v. Jones, 455
S.W.3d 753, 770 (Tex. App.—Texarkana 2015, pet. dism’d) (citing Merrell Dow Pharms., Inc.
v. Havner, 953 S.W.2d 706, 711 (Tex. 1997)). “Less than a scintilla of evidence exists when the
evidence is ‘so weak as to do no more than create a mere surmise or suspicion’ of a fact.” King
Ranch, Inc. v. Chapman, 118 S.W.3d 742, 751 (Tex. 2003) (quoting Kindred v. Con/Chem, Inc.,
650 S.W.2d 61, 63 (Tex. 1983)).
B. Applicable Law
“The requirements of written and oral contracts are the same and must be present for a
contract to be binding.” Lloyd Walterscheid & Walterscheid Farms, LLC v. Waltersheid, 557
S.W.3d 245, 258 (Tex. App.—Fort Worth 2018, no pet.) (citing Critchfield v. Smith, 151 S.W.3d
225, 233 (Tex. App.—Tyler 2004, pet. denied)). To form a binding contract there must be
“(1) an offer, (2) an acceptance in strict compliance with the terms of the offer, (3) a meeting of
the minds, (4) each party’s consent to the terms, and (5) execution and delivery of the contract
with the intent that it be mutual and binding.” KW Const. v. Stephens & Sons Concrete
Contractors, Inc., 165 S.W.3d 874, 883 (Tex. App.—Texarkana 2005, pet. denied) (citing
Buxani v. Nussbaum, 940 S.W.2d 350, 352 (Tex. App.—San Antonio 1997, no writ)).
4 “To be enforceable, a contract must address all of its essential and material terms with ‘a
reasonable degree of certainty and definiteness.’” Fischer v. CTMI, L.L.C., 479 S.W.3d 231, 237
(Tex. 2016) (quoting Pace Corp. v. Jackson, 284 S.W.2d 340, 345 (Tex. 1955)). At the least, a
contract “must . . . be sufficiently definite to confirm that both parties actually intended to be
contractually bound.” Id. (citing Fort Worth Indep. Sch. Dist. v. City of Fort Worth, 22 S.W.3d
831, 846 (Tex. 2000)). Further, “the agreement’s terms must . . . be sufficiently definite to
‘enable a court to understand the parties’ obligations,’” id. (quoting Forth Worth Indep. Sch.
Dist., 22 S.W.3d at 846), “and to give ‘an appropriate remedy’ if they are breached,” id.
(RESTATEMENT (SECOND) OF CONTRACTS § 33(2) (1981) (footnote omitted) (citations omitted)).
However, only “those terms that are ‘material and essential’ to the parties’ agreement”
are required to “be definite and certain.” Id. (quoting Radford v. McNeny, 104 S.W.2d 472, 475
(Tex. 1937)). “[M]aterial and essential terms are those that parties would reasonably regard as
‘vitally important ingredient[s]’ of their bargain.” Id. (second alteration in original) (quoting
Neeley v. Bankers Tr. Co. of Tex., 757 F.2d 621, 628 (5th Cir. 1985)). Which terms are material
is “determined on a case-by-case basis.” Id. (quoting McCalla v. Baker’s Campground, Inc., 416
S.W.3d 416, 418 (Tex. 2013) (per curiam)).
The Texas Supreme Court has set forth several principles in analyzing whether a contract
is enforceable. See id. at 239–40. The following are those principles applicable to this case.
First, “because the law disfavors forfeitures, we will find terms to be sufficiently definite
whenever the language is reasonably susceptible to that interpretation.” Id. at 239. Concomitant
to this principle, “if the parties clearly intended to agree and a ‘reasonably certain basis for
5 granting a remedy’ exists, we will find the contract terms definite enough to provide that
remedy.” Id. (quoting RESTATEMENT (SECOND) OF CONTRACTS § 33 cmt. b). Further,
[w]hen “the actions of the parties . . . show conclusively that they have intended to conclude a binding agreement, even though one or more terms are missing or are left to be agreed upon[,] . . . courts endeavor, if possible, to attach a sufficiently definite meaning to the bargain.”
Id. (second alteration in original) (quoting RESTATEMENT (SECOND) OF CONTRACTS § 33 cmt. a).
Second, “[p]art performance under an agreement may remove uncertainty and establish
that a contract enforceable as a bargain has been formed.” Id. at 240 (alteration in original)
(quoting RESTATEMENT (SECOND) OF CONTRACTS § 34(2)). Further, “the parties’ actions ‘in
reliance on an agreement may make a contractual remedy appropriate even though uncertainty is
not removed.’” Id. (quoting RESTATEMENT (SECOND) OF CONTRACTS § 34(3)). Thus, “[w]hen
the parties’ actions demonstrate that they intended to ‘conclude a binding agreement, even
though one or more terms . . . are left to be agreed upon . . . , courts endeavor, if possible, to
attach a sufficiently definite meaning to the bargain.’” Id. (quoting RESTATEMENT (SECOND) OF
CONTRACTS § 33(2) cmt. a). “The law favors finding agreements sufficiently definite for
enforcement, ‘particularly . . . where one of the parties has performed his part of the contract.’”
Id. (quoting Tanenbaum Textile Co. v. Sidran, 423 S.W.2d 635, 637 (Tex. App.—Dallas 1967,
writ ref’d n.r.e.)).
C. The Evidence at Trial Regarding the Contract
Garney Companies, Inc. (Garney) was the general contractor for the Lower Bois D’Arc
Creek Reservoir Program – Water Treatment Plant and Pump Station Project, Project Numbers
384 and 358 (the “Leonard Project”). In March 2020, Garney entered into a subcontract with 6 RCIS to perform steel-erection work for the Leonard Project. The original contract price was
$348,800.00 for RCIS’s scope of work.
Scott Houser (Scott), Houser’s owner, had known the owner of RCIS, Benjamin Castro,
since 2015. Scott testified that Houser had done five or six steel-erection projects for RCIS,
including the Leonard Project. According to Scott, in early October 2020, Castro called Scott
and said he had started the Leonard Project but might need Houser to finish it because Castro
was having trouble with his crew.2 On the morning of October 19, RCIS lost all of its workers
on the Leonard Project. Later that day, Castro began negotiations with Houser to finish the
structural steel work on the Leonard Project.3 Within the next few days, Castro provided Houser
with the steel-erection drawing submittals from HME, Inc. (HME),4 which detailed the steel-
2 Garney’s daily reports for the Leonard Project state that RCIS had two welders and one helper working on October 1 thru October 5, 2020. The reports state that RCIS had one welder and one helper working on October 6 thru October 9. From October 13 thru October 16, the reports state that RCIS had one welder and four workers at the worksite. Regarding RCIS, the report for Monday, October 19, states, “Lost all workers by 10am. Should have more welders tomorrow. Working at East Chem deck.” Also, for RCIS, the reports from October 20 thru October 22, state, “Working at East Chem deck,” but do not indicate whether any welders or other workers were present. The report for October 27, also states, “RCIS to have a full crew on Monday to erect East Chem canopies.” 3 Scott explained that there were four buildings in the Leonard Project called the north chemical, east chemical, west chemical, and lime. He described the project as follows:
You had tilt wall buildings that are essentially concrete walls that are stood up by another contractor. And inside of those buildings, you have what we call bar joists that basically make up the roof structure for those enclosed buildings. And then on top of the bar joists, you get what we call B decking, and it’s just a decking -- decking materials that go down. And then they’re not a waterproof barrier. They then come back and lay the -- another contractor will come back and lay the waterproof barrier on top of the decking that we install, as well as the galvanized canopies that are outside that were connected to the concrete tilt wall buildings. Those needed to be installed as well.
That was the -- the full scope of the project for Ben and [Scott]. 4 HME was the manufacturer of all of the steel for the Leonard Project.
7 erection work for the Leonard Project.5 Castro never gave Houser a copy of RCIS’s contract
with Garney.
In determining the scope of work, Scott asked Castro, by text message, whether the
exterior wall panels were in Houser’s scope of work. Castro replied, “Nope. Steel only.” Scott
explained that he was referring to the fascia and panels attached to the canopies depicted on the
HME drawings and that the reason he asked was because a qualified person was required to
install them. He also explained that the panels were metal cladding that goes on the exterior of
the building and that they were “outside [the] normal structural steel scope.” A few minutes
after telling Scott that the scope of work was steel only, Castro sent Scott a text message stating,
“You have the construction drawings. That’s the metal packages.”
Based on the information Castro gave Scott, and his inspection of the project, Scott
offered to finish the steel-erection work for $180,000.00. He testified that he based his offer on
the square footage, the bid of his subcontractor, Steel Ruiz,6 and equipment and crane rentals.
Scott testified that by October 27, Houser and RCIS had come to an agreement that Houser
would complete the remaining steel-erection work for $180,000.00 and that Houser would cover
the cost of equipment and cranes. On November 3, Castro sent text messages to Scott stating,
5 Scott testified that initially he was not provided with the full set of drawings but that Castro explained to him the scope of work on the north chemical building. 6 Houser subcontracted with Steel Ruiz to provide the labor for the steel-erection work. Scott testified that Steel Ruiz gave him an initial offer “not to exceed” $117,000.00 and that its final price was $80,500.00. 8 “Keep it at $180k. You must provide allll [sic] equipment. And we will have a signed
contract[.][7] If a crane is needed, like you said, then provide it.”
On October 27, Steel Ruiz’s crew began working on the Leonard Project. By November
19, according to Scott, seventy-five percent of the work was done, and Houser sent its first pay
application to RCIS.8 Scott testified that before the pay application was sent, he confirmed with
Castro and Garney’s superintendent, Dana Savidge, that they agreed on the percentage. Steel
Ruiz worked on the Leonard Project through December 11. Scott explained that Steel Ruiz was
not able to complete a section of the west chemical building upper canopy and the lower canopy
because of manufacturer deficiencies, and a small canopy at the north chemical building because
it had been fabricated incorrectly. He testified that if RCIS had asked Houser to return to the
jobsite and finish the steel-erection work, it would have done so. On December 12, RCIS paid
Houser $65,000.00 on its first pay application.
Houser sent its second pay application to RCIS on December 18, for work performed on
the Leonard Project from November 19 to December 17. At that time, Houser estimated that it
had completed ninety-five percent of the steel-erection work. The total amount requested was
$102,675.00, which included both the $56,500.00 not paid on the first pay application and a
$5,500.00 change order. Scott also testified that on November 18, RCIS invoiced Garney a net
7 Scott testified that he normally required a signed contract before starting work. On the Leonard Project, although Castro said they would have a written contract, he never sent one to Scott despite Scott’s repeated requests to send him one. Scott testified that when he asked Castro for a contract, Castro “either sidestepped” the issue, said he would have it in a few days, or said he was out of the office. Text messages between Scott and Castro sent in October, November, and December 2020, support Scott’s testimony. 8 The first pay application requested payment of $121,500.00, which was seventy-five percent of $180,000.00 less ten percent retainage (($180,000.00 x 75%) less $13,500.00 retainage). 9 amount of $132,739.35 and that on December 1, RCIS invoiced Garney a net amount of
$61,750.00. He noted that those amounts were very similar to the amounts Houser had requested
from RCIS in its two pay applications.
Castro acknowledged that RCIS sent a pay application to Garney for work performed
through October 15 and represented that thirty-four percent of its steel-erection work was
complete. He also acknowledged that RCIS sent a pay application to Garney for work through
November 15 and represented that seventy-four percent of the steel-erection work was complete.
For work done December 1 through December 15, he acknowledged that RCIS represented on its
pay application that ninety-two percent of the steel-erection work was complete.
Castro admitted that he did not provide Houser a copy of RCIS’s contract with Garney
before Houser began working on the Leonard Project. However, he maintained that grout work
under the steel columns, the exterior horizontal ribbed metal wall panels, and supervision of
Houser’s crew9 were included in Houser’s scope of work because those items were included in
RCIS’s scope of work under its contract with Garney. He also testified that Scott’s inquiry
regarding the exterior wall panels was referring to the tilt wall concrete panels.
D. Analysis
In its first issue, RCIS contends that there is no evidence of a meeting of the minds by the
parties on the essential terms of the contract. Specifically, RCIS contends that there is no
9 At trial, Castro testified that he supervised Houser’s crew in November and December because Houser did not. The only text message that he relied on in support of that contention was a text message he sent to Houser on February 12, 2021, stating, “You didn’t have 1 guy from your company to foreman like you said you were going too [sic]. I was there every week.” Rafael Ruiz, who worked on the Leonard Project for Steel Ruiz, testified that Castro was at the worksite “almost every day.” However, he testified that Castro only observed who was working and never instructed the Steel Ruiz crew about how to do their work or where they should work. 10 evidence that there was a meeting of the minds on the scope of Houser’s work. RCIS points to
portions of Scott’s testimony it contends establishes the terms of Houser’s scope of work were
not sufficiently defined. It also relies on Castro’s testimony that Houser’s scope of work was
broader than the scope of work identified by Scott.
“Whether there was a meeting of the minds is based on an objective standard of what the
parties said and did rather than their subjective state of mind.” Ho v. Benco Mach., LLC, No. 06-
20-00061-CV, 2020 WL 7268586, at *3 (Tex. App.—Texarkana Dec. 11, 2020, no pet.) (mem.
op.) (quoting Moe’s Home Collection, Inc. v. Davis St. Mercantile, LLC, No. 05-19-00925-CV,
2020 WL 3637623, at *2 (Tex. App.—Dallas July 6, 2020, no pet.) (mem. op.)). Further,
“evidence of a party’s subjective misunderstanding has no bearing on the definiteness of the
agreement, which is an objective inquiry.” Id. at *4 (quoting Moe’s Home Collection, Inc., 2020
WL 3637623, at *4).
Initially, we note that at trial, although Castro disagreed about the scope of work Houser
was obligated to perform, he did not deny that RCIS and Houser had an agreement that Houser
would finish the steel-erection work on the Leonard Project. To determine whether there was
more than a scintilla of evidence that the parties had a meeting of the minds regarding Houser’s
scope of work, we look not only to the parties’ testimony, but to the other relevant evidence
introduced at trial: the text messages between the parties, HME’s steel-erection drawings, and
the parties’ conduct and experience.
Both parties were experienced in steel-erection work and had worked on other steel-
erection projects together. The evidence shows that during their discussions of the Leonard
11 Project, Castro sent Scott HME’s steel-erection drawings, which showed the details of the steel
components and the erection of the buildings. When Scott had questions regarding the scope of
work and dimensions of the buildings, Castro replied, “You have the construction drawings.
That’s the metal packages,” and instructed Scott to “[g]o off the construction drawings.” That is
evidence that both parties understood that the scope of Houser’s work would be determined by
the construction drawings that Castro supplied to Scott.10 The only exception to the work shown
on the drawings was the exterior wall panels that were to be connected to the canopies, about
which Scott specifically asked, and Castro replied that they were not in RCIS’s scope of work.11
Both parties agreed that Houser would also pay for all equipment and any cranes used by Houser
on the project, as evidenced by their text messages. Finally, the evidence shows that Houser and
Steel Ruiz performed all of the steel-erection work they could from October 27 through
December 11, without any complaint from RCIS that Houser was not complying with the scope
of work under the agreement.
On this record, we find that more than a scintilla of evidence supports the trial court’s
implied finding that the parties had a meeting of the minds regarding the scope of Houser’s work
10 The HME construction drawings state:
FOR FIELD USE FINAL PLANS NOTE TO CONTRACTOR AND ERECTOR RESPONSIBILITY FOR FIELD MODIFICATIONS OF ADDITIONAL MATERIAL WILL NOT BE ACCEPTED UNLESS PREVIOUSLY AUTHORIZED BY HME, INC. 11 Although Castro testified that Scott’s inquiry about exterior wall panels was referring to the tilt wall concrete panels, the trial court, as fact-finder, “is the sole judge of the credibility of the witnesses and the weight to give their testimony.” Ramsay, 254 S.W.3d at 625. As a result, it could have given more weight to Houser’s testimony that the reference was to the metal panels that were to be connected to the canopies. 12 on the Leonard Project. As a result, legally sufficient evidence supports the trial court’s implied
finding. We overrule RCIS’s first issue.
II. Legally Insufficient Evidence Supports the Trial Court’s Damages Findings, in Part
RCIS’s second issue challenges the legal sufficiency of the evidence supporting the trial
court’s findings on damages and RCIS’s affirmative defense of waiver and release. RCIS argues
that the evidence conclusively establishes that Houser waived and released any claim for unpaid
work covered under its first pay application, except the unpaid retainage. It also argues that no
evidence supports the trial court’s damages findings because Houser presented no evidence of
the reasonable cost to complete the work it contracted to perform, to remedy the alleged defects
in its work, or of equipment and crane rental and fuel charges. We will address these arguments
separately.
A. Conclusive Evidence Established Waiver and Release of Unpaid Balance of the First Pay Application
1. Evidence Relating to Waiver and Release
As discussed above, on November 19, Houser sent its first pay application to RCIS. In
the application, Houser claimed that seventy-five percent of the steel-erection work was
complete, and billed RCIS seventy-five percent of $180,000.00 ($135,000.00), less ten percent
retainage ($13,500.00), for a net of $121,500.00. On December 12, RCIS paid Houser a progress
payment of $65,000.00. In return, on behalf of Houser, Scott executed an “UNCONDITIONAL
WAIVER AND RELEASE ON PROGRESS PAYMENT” (the Release) that provided, in
relevant part:
Project Leonard WTP 13 Job No. __________________
The signer of this document has been paid and has received a progress payment in the sumof [sic] $65,000.00 for all labor, services, equipment, or materials furnished to the property or to RCIS Enterprises, LLC. on the property of North Texas Municipal (owner) located at 361 County Rd. 4965___ (location) to the following extent: Steel Erecting/Welding______ (job description). The signer therefore waives and releases any mechanic’s lien right, any right arising froma [sic] payment bond that complies with a state or federal statute, any common law payment bond right, any claim for payment, and any rights under any similar ordinance, rule, or statute related to claim orpayment [sic] rights for persons in the signer’s position that the signer has on the above referenced project to the following extent:
This release covers a progress payment for all labor, services, equipment, or materials furnished to the property or to RCIS Enterprises, LLC.. [sic] as indicated in the attached statement(s) or progress payment request(s), except for unpaid retention, pending modifications and changes, or other items furnished.
....
NOTICE: THIS DOCUMENT WAIVES RIGHTS UNCONDITIONALLY AND STATES THAT YOU HAVE BEEN PAID FOR GIVING UP THOSE RIGHTS. THIS DOCUMENT IS ENFORCEABLE AGAINST YOU IF YOU SIGN IT, EVEN IF YOU HAVE NOT BEEN PAID. IF YOU HAVE NOT BEEN PAID, USE A CONDITIONAL RELEASE FORM.
Date 12-11-2020 Houser Fabrication, LLC (Company name) By [/s/Scott Houser] (Signature) Owner (Title)
The undisputed evidence at trial established that the $65,000.00 progress payment was toward
Houser’s first pay application and that it was the only monies Houser received from RCIS on the
Leonard Project.
On December 18, Houser sent its second pay application to RCIS for work performed on
the project from November 19 to December 17. That pay application represented that ninety-
14 five percent of the steel-erection work was completed, billed RCIS ninety-five percent of
$180,000.00 ($171,000.00), plus $5,500.00 for a change order, less five percent retainage
($8,825.00), and less the previous payment ($65,000.00), for a net amount of $102,675.00. In
other words, the net amount included $56,500.00 that was withheld from the first pay
application.
In its original answer and original counterclaim, RCIS asserted the affirmative defenses
of waiver and release.
2. Findings of Fact and Conclusions of Law Relevant to Waiver and Release
The trial court entered the following findings of fact relevant to the waiver and release
issue:
22. On December 11, 2020, the value of Houser’s unpaid work, less offsets for equipment, was $78,491.10. .... 30. The total amount of the work to be performed by Houser on the Leonard job was $180,000.00 less work not performed by Houser ($18,414.48) and a credit for equipment ($18,094.42). $180,000.00-$18,414.48-$18,094.42 = $143,491.10. .... 32. On Nov[ember] 19, 2020[,] Houser emailed its first payment application and certificate for payment to RCIS, therein billing for unpaid work in the amount of $121,500. .... 35. On December 11, 2020, RCIS paid Houser $65,000.00, leaving a balance owed of $56,500.00. 36. RCIS never issued any further payments to Houser on the Leonard [P]roject. 37. Houser’s principal damages are calculated as the net amount for which it billed (after deductions for work not performed and an equipment credit) of $143,491.10 - $65,000.00 paid by RCIS = Principal Damages of $78,491.10.
15 38. On December 17, 2020, Houser issued an invoice to RCIS in the amount $102,675.00, which represent[ed] a carry-forward amount owed from the previous invoice of $56,500.00, plus new work for $46,175.00. .... 42. Prompt pay interest of 18% on $56,500.00 from 12/21/2020 through 8/21/2023 (973 days at $27.86/day) = $27,107.78. .... 44. Houser has been damaged for RCIS’s failure to pay the net sum due to Houser of $78,491.10. .... 65. Houser did not release any claims or defenses in this lawsuit. 66. Houser’s application of the payment it received from RCIS did not prejudice either RCIS, or Houser’s ability to assert the claims and defenses it brought in this lawsuit. .... 70. Houser did not act in a manner as to intentionally surrender any known right, claim, cause of action, or defense regarding the Leonard Project. 71. Houser did not engage in intentional conduct inconsistent with claiming any right or asserting any claim, cause of action, or defense regarding the Leonard Project.
Relevant to the waiver and release issue, the trial court entered the following conclusions of law:
9. Houser substantially performed its work at the project. 10. Because Houser substantially performed its work, it is entitled to full payment under the Leonard [c]ontract less the value of its unperformed work and rental equipment provided by RCIS. .... 15. RCIS’s affirmative defenses asserted against Houser are without merit and should be denied in their entirety.
3. Standard of Review and Applicable Law
“When a party attacks the legal sufficiency of the evidence supporting an adverse finding
on an issue on which [it] has the burden of proof, [it] must demonstrate on appeal that the
evidence establishes, as a matter of law, all vital facts in support of the issue.” Pettit v. Tabor,
No. 06-19-00002-CV, 2020 WL 216025, at *8 (Tex. App.—Texarkana Jan. 15, 2020, pet.
denied) (mem. op.) (quoting Dow Chem. Co. v. Francis, 46 S.W.3d 237, 241 (Tex. 2001) (per 16 curiam)). “To prevail on appeal, the party must first show that no evidence supported the trial
court’s finding and then, if there was none, that the evidence conclusively established the finding
urged by the party.” Id. (citing PlainsCapital Bank v. Martin, 459 S.W.3d 550, 557 (Tex.
2015)). “To determine whether no evidence supported the finding, we ‘first examine the record
for evidence that supports the finding, while ignoring all evidence to the contrary.’” Id. (quoting
Dow Chem. Co., 46 S.W.3d at 241). “If no evidence supports the finding, then we ‘examine the
entire record to determine if the contrary proposition is established as a matter of law.’” Id.
(quoting Dow Chem. Co., 46 S.W.3d at 241).
At trial, it was undisputed that Scott signed the Release on behalf of Houser in exchange
for the $65,000.00 payment on its first pay application. “A release is a contract, so we construe
it as such.” Finley Res., Inc. v. Headington Royalty, Inc., 672 S.W.3d 332, 339 (Tex. 2023).
“The construction of an unambiguous contract is a question of law which we review de novo.”
Petrohawk Props., L.P., 455 S.W.3d at 765 (citing Tawes v. Barnes, 340 S.W.3d 419, 425 (Tex.
2011)). “When the contract is unambiguous, ‘the instrument alone will be deemed to express the
intention of the parties for it is objective, not subjective, intent that controls. Generally[,] the
parties to an instrument intend every clause to have some effect and[,] in some measure[,] to
evidence their agreement.’” Id. (quoting City of Pinehurst v. Spooner Addition Water Co., 432
S.W.2d 515, 518 (Tex. 1968)). “[A]ll the usual ‘rules of construction’ apply, like the familiar
presumptions favoring consistent usage, disfavoring surplusage, and using the plain meaning of
undefined terms.” Mosaic Baybrook One, L.P. v. Simien, 674 S.W.3d 234, 257 (Tex. 2023)
(alteration in original) (quoting Perthuis v. Baylor Miraca Genetics Labs., LLC, 645 S.W.3d 228,
17 236 (Tex. 2022)). “[W]e examine the entire [Release] and attempt to harmonize all its parts,
even if different parts appear contradictory or inconsistent.” Id. (first alteration in original)
(quoting Endeavor Energy Res., L.P. v. Energen Res. Corp., 615 S.W.3d 144, 148 (Tex. 2020)).
“Further, when construing a contract, a court is ‘to take the wording of the instrument, consider
the same in the light of the surrounding circumstances, and apply the pertinent rules of
construction thereto and thus settle the meaning of the contract.’” Petrohawk Props., L.P., 455
S.W.3d at 765 (quoting City of Pinehurst, 432 S.W.2d at 519). Nevertheless, evidence of the
surrounding circumstances “may only be used to aid the understanding of an unambiguous
contract’s language, not change it or ‘create ambiguity.’” URI, Inc. v. Kleberg Cnty., 543
S.W.3d 755, 757 (Tex. 2018) (citing Cmty. Health Sys. Pro. Servs. Corp. v. Hansen, 525 S.W.3d
671, 688 (Tex. 2017)).
“[T]o effectively release a claim in Texas, the releasing instrument must ‘mention’ the
claim to be released. Even if the claims exist when the release is executed, any claims not
clearly within the subject matter of the release are not discharged.” Victoria Bank & Tr. Co. v.
Brady¸ 811 S.W.2d 931, 938 (Tex. 1991) (quoting Vela v. Pennzoil Producing Co., 723 S.W.2d
199, 204 (Tex. App.—San Antonio 1986, writ ref’d n.r.e.)).
4. Analysis
At trial, Scott did not dispute that he signed the Release on behalf of Houser in exchange
for the $65,000.00 payment on its first pay application. Rather, the only evidence was that he
did so. As a result, unless the Release was ineffective to release any claims by Houser, there is
18 no evidence to support the trial court’s finding that Houser did not release any claims or
defenses.
As the Texas Supreme Court has noted, “[t]he purpose of progress payment releases is to
ensure that the contractor will not accept payment for work performed and then insist on
additional payment for that work.” Zachry Constr. Corp. v. Port of Houston Auth. of Harris
Cnty., 449 S.W.3d 98, 119 (Tex. 2014). A release “operates to extinguish the claim or cause of
action as effectively as would a prior judgment between the parties and is an absolute bar to any
right of action on the released matter.” Dresser Indus., Inc. v. Page Petroleum, Inc., 853 S.W.2d
505, 508 (Tex. 1993) (citing Hart v. Traders & Gen. Ins. Co., 189 S.W.2d 493, 494 (Tex. 1945)).
As relates to Houser’s claims against RCIS, under the plain language of the Release, in
exchange for a $65,000.00 “progress payment for all labor, services, equipment, or materials” it
furnished to RCIS on the Leonard Project related to “Steel Erecting/Welding,” Houser waived
and released any claim for payment that it had on the Leonard Project to the extent the claim was
“for labor, services, equipment, or materials furnished to the property or to RCIS Enterprises,
LLC.. [sic] as indicated in the attached statement(s) or progress payment request(s),” except for
unpaid retention.
RCIS argues that the Release extinguished Houser’s actions against it for breach of
contract and quantum meruit insofar as those actions were for unpaid labor, services, equipment,
or materials covered by Houser’s first pay application, except for unpaid retainage. In its brief,
Houser only argues that the Release “makes it clear that any release therein is limited in scope to
work already performed, as indicated in any attachment.” Left unaddressed by both parties are
19 the fact that there was no document attached to the Release and how the lack of an attachment
affects the scope of the Release.
Nevertheless, the undisputed evidence in this case establishes that at the time the Release
was executed, Houser had only submitted its first pay application. It is also undisputed that the
$65,000.00 payment was on Houser’s first pay application and that it was the only payment
Houser received from RCIS related to the Leonard Project.
Considering the wording of the Release, “in the light of the[se] surrounding
circumstances,” we conclude, as a matter of law, that under the Release, Houser waived and
released any claim for additional payment covered by its first pay application, except for unpaid
retainage. See Petrohawk Props., L.P., 455 S.W.3d at 765 (quoting City of Pinehurst, 432
S.W.2d at 519). As a result, the Release extinguished Houser’s breach of contract and quantum
meruit actions asserted against RCIS, to the extent it claimed damages for unpaid labor, services,
equipment, or materials covered by Houser’s first pay application, except for unpaid retainage.
We find that the evidence establishes as a matter of law that Houser released and waived
any claim for additional payment covered by its first pay application, except for unpaid
retainage, i.e. the unpaid $56,500.00. We sustain RCIS’s second issue, in part. As a result, we
will reduce the actual damages award by $56,500.00.12
12 Houser also contends that RCIS waived its complaint that Houser released its claim to future payments by executing the first pay application because it did not make this argument to the trial court. However, RCIS did not make this complaint on appeal. To the extent Houser contends that RCIS waived its complaint that Houser released and waived its claim for payment of the unpaid balance of the first pay application, we note that the record shows RCIS asserted the affirmative defenses of release and waiver and presented evidence in support of those defenses. Also, the trial court made findings of fact regarding those defenses, which shows the trial court was aware that RCIS was asserting and relying on them. Under this record we find that RCIS did not waive its complaint on appeal. 20 B. Legally Sufficient Evidence Supported the Other Damage Findings of Fact
RCIS challenges the remainder of the damages awarded to Houser because, it argues,
“Houser presented no evidence of the reasonable cost to complete the work [Houser] agreed to
perform, the reasonable cost to remedy the defects in [Houser’s] work, [and] the reasonable
equipment-rental and crane expenses” incurred for Houser’s work. We disagree.
1. Applicable Law and Standard of Review
A contractor who has substantially performed its building contract is entitled to recover
“the contract price, less the reasonable cost of remedying the defects or omissions in such a way
as to make the building conform to the contract.” Vance v. My Apartment Steak House of San
Antonio, Inc., 677 S.W.2d 480, 482 (Tex. 1984) (quoting Atkinson v. Jackson Bros., 270 S.W.
848, 850 (Tex. Comm’n App. 1925, holding approved)). “This deduction measures the damages
allowed the owner for failure on the part of the contractor to fully comply with the
specifications.” Id. (quoting Atkinson, 270 S.W. at 850). Because Houser asserted an
affirmative claim for relief, it had the burden to prove each element of its claim, including the
reasonable cost of remedying the defects and omissions of its work. See id. Nevertheless, it was
not required to prove the exact amount of the cost. Rather, it was required to produce sufficient
evidence “to afford [the fact-finder] a reasonable basis for determining” the reasonable cost. Id.
at 484.
In this case, the trial court made a finding of fact that “RCIS is entitled to an offset of
$18,094.42 for equipment it provided for the Leonard Project” and an implied finding of fact that
21 the reasonable cost for remedying the defects and omissions of its work was $18,414.48.13
“When determining whether legally sufficient evidence supports a [fact] finding, we must
consider evidence favorable to the finding if a reasonable factfinder could and disregard
evidence contrary to the finding unless a reasonable factfinder could not.” Albertsons, LLC, 689
S.W.3d at 318 n.2 (quoting 4Front Engineered Sols., Inc., 505 S.W.3d at 908). “The evidence is
legally sufficient if [there] is more than a scintilla of evidence on which a reasonable juror could
find the fact to be true.” Id. (alteration in original) (quoting 4Front Engineered Sols., Inc., 505
S.W.3d at 909). “More than a scintilla of evidence exists when the evidence reaches a level
enabling reasonable and fair-minded people to differ in their conclusions.” Petrohawk Props.,
L.P., 455 S.W.3d at 770 (citing Havner, 953 S.W.2d at 711). “Less than a scintilla of evidence
exists when the evidence is ‘so weak as to do no more than create a mere surmise or suspicion’
of a fact.” Chapman, 118 S.W.3d at 751 (quoting Kindred, 650 S.W.2d at 63).
2. Analysis
As noted above, Scott testified that one of the terms of Houser’s contract with RCIS was
that Houser would be responsible for the cost of the equipment and crane rental attributable to
Houser’s work. In explaining what was due under the contract, Scott testified that the equipment
and crane rentals attributable to Houser, as well as the fuel costs, should be deducted from what
was due under the contract. In its brief, RCIS acknowledges that Scott testified that the amount
of those items was $18,094.42. RCIS does not challenge the sufficiency of Scott’s testimony
13 The trial court entered the following finding of fact:
68. RCIS is entitled to a credit in the amount of $18,414.48 for work not performed by Houser on the Leonard Project.
22 regarding the actual cost of those items. Rather, it faults Houser for “present[ing] no evidence
that $18,094.42 represented the reasonable equipment-rental and crane expenses and fuel
charges that RCIS incurred for Houser’s work on the Leonard [P]roject.” (Emphasis added).
However, because Houser was entitled to recover its “contract price, less the reasonable
cost of remedying the defects or omissions in such a way as to make the building conform to the
contract,” see Vance, 677 S.W.2d at 482 (quoting Atkinson, 270 S.W. at 851), Houser’s burden
of proof included establishing what was owed under the contract. Since Houser was responsible
under the contract for the rental cost of the equipment and crane, and the fuel expenses
attributable to its work, RCIS was entitled to an offset against what was owed under the contract
for the rental and fuel expenses it incurred that were attributable to Houser’s work. As a result,
Houser’s burden was to establish the actual cost of the equipment and crane rental and the fuel
costs, not the reasonable cost of those items.
Houser also provided sufficient evidence to give the trial court a reasonable basis for
determining the reasonable cost of remedying its defects or omissions of its work. Scott testified
that the Steel Ruiz crew left the Leonard Project because it was not able to complete a section of
the west chemical building upper canopy and the lower canopy because of manufacturer
deficiencies, and a small canopy at the north chemical building because it had been fabricated
incorrectly. He estimated that at that time, Houser had completed 92.4 percent of its scope of
work. Scott also estimated that the total square footage that Houser was not able to complete
was 2,500 to 2,700 square feet.
23 Scott also testified that he based his bid at $7.70 per square foot, which he opined was the
market value.14 He testified that Houser’s base minimum was $7.15 per square foot, and that
RCIS’s price was $12.00 to $13.00 per square foot. He also testified that Steel Ruiz initially bid
the labor for $117,000.00 and ultimately completed the work for $80,500.00.
Although Scott never testified regarding the exact cost to complete Houser’s scope of
work, he provided the trial court with a description of the items that had not been completed, the
approximate square footage of those items, the per-square-foot charges of both Houser and
RCIS, and the amount Steel Ruiz was paid for completing approximately ninety-two percent of
Houser’s scope of work. The trial court’s finding of the reasonable cost of remedying the defects
and omissions in Houser’s work fell within that testimony.15 As a result, we find that Houser
produced sufficient evidence to give the trial court a reasonable basis to determine the reasonable
cost for remedying the defects and omissions of its work. We overrule RCIS’s second issue, in
part.
III. Houser Was Not Entitled to Prompt Payment Interest
In its judgment, the trial court awarded Houser prompt payment interest in the amount of
$33,423.65. The judgment recites that it arrived at this amount as follows:
14 Scott testified that he had estimated over one hundred erection projects, similar to Leonard, and that he was familiar with the typical charges for those types of projects. He based his familiarity on conversations with others in the same field and on bid tabulations from projects that give the amounts bid by each contractor on the projects. 15 The fact-finder “generally has discretion to award damages within the range of evidence presented at trial.” Sw. Energy Prod. Co. v. Berry–Helfand, 491 S.W.3d 699, 713 (Tex. 2016) (citing Gulf States Utils. Co. v. Low, 79 S.W.3d 561, 566 (Tex. 2002)).
24 (a) prompt pay interest of 18% on $65,000 [sic] from 12/21/2020 through 7/27/2023 (947 days at $32.05/day) = $30,351.35 [sic]16
(b) prompt pay interest of 18% on the remaining $13,491.10 ($78,491.10 - $65,000[.00]) from 4/21/22 through 7/27/2023 (462 days at $6.65/day) = $3,072.30.
RCIS asserts that the trial court erred in awarding prompt payment interest on the unpaid amount
under the first pay application because, among other things, Houser waived and released its
rights to the unpaid balance, except unpaid retainage. It asserts that the trial court erred in
awarding prompt payment interest on the unpaid retainage and the balance owed under the
second pay application because RCIS never received payment from Garney for those items, as
required by Section 28.002(c) of the Texas Property Code. See TEX. PROP. CODE ANN. §
28.002(c). For these reasons, RCIS asserts that there is legally insufficient evidence supporting
the trial court’s findings of fact in support of its prompt payment interest award.
A. Applicable Law
Section 28.002(c) provides, in relevant part:
(c) A subcontractor who receives a payment . . . from a contractor in connection with a contract to improve real property shall pay each of its subcontractors the portion of the payment, including interest, if any, that is attributable to work properly performed . . . as provided under the contract by that subcontractor, to the extent of that subcontractor’s interest in the payment. The payment required by this subsection must be made not later than the seventh day after the date the subcontractor receives the contractor’s payment.
TEX. PROP. CODE ANN. § 28.002(c). Thus, under the statute, a subcontractor that receives a
payment from a contractor must “pay each of its subcontractors the portion of th[at] payment” 16 As noted above, the trial court’s findings of fact state, “On December 11, 2020, RCIS paid Houser $65,000.00, leaving a balance owed of $56,500.00,” and “[p]rompt pay interest of 18% on $56,500.00 from 12/21/2020 through 8/21/2023 (973 days at $27.86/day) = $27,107.78.” The trial court’s judgment mistakenly based its award on the $65,000.00 prior payment, rather than the $56,500.00 balance it found was owed under the first pay application. 25 that is attributable to the work performed by its subcontractor no “later than the seventh day after
the date the subcontractor receives the contractor’s payment.” Id. (emphasis added); see Henry
Bldg., Inc. v. Milam, No. 05-99-01400-CV, 2001 WL 246882, at *3 (Tex. App.—Dallas Mar. 14,
2001, pet. denied) (not designated for publication). If the subcontractor fails to timely pay its
subcontractor, the “unpaid amount bears interest at the rate of 1 ½ percent each month.” TEX.
PROP. CODE ANN. § 28.004(b).
B. Analysis
Because we have previously held that Houser waived and released its claim to any unpaid
amounts under the first pay application, except unpaid retainage, RCIS was not liable under
Section 28.002(c) for prompt payment interest attributable to these unpaid amounts. As a result,
we find that legally insufficient evidence supports the trial court’s award of $30,351.35 based on
these unpaid amounts.
Regarding the remaining amounts, in order to show that RCIS was liable for prompt
payment interest, Houser was required to show that (1) RCIS received a payment from a Garney,
(2) a portion of which was attributable to work properly performed by Houser covered by the
unpaid retainage in the first pay application and covered by the second pay application, and
(3) RCIS failed to pay Houser within seven days after it received payment from Garney. See
TEX. PROP. CODE ANN. §§ 28.002(c), 28.004(b). Thus, under the statute, RCIS’s liability was
only triggered if it received a payment from Garney that was attributable to work performed by
Houser and it failed to pay Houser within seven days of its receipt of the payment.
26 Because the statute does not define “receives,” “we will use the plain and ordinary
meaning of the term and interpret it within the context of the statute.” Tex. Health & Hum.
Servs. Comm’n v. Est. of Burt, 689 S.W.3d 274, 280 (Tex. 2024) (quoting Hogan v. Zoanni, 627
S.W.3d 163, 169 (Tex. 2021)). The plain and ordinary meaning of “receive[s]” is “to come into
possession of: ACQUIRE.” Receive, MERRIAM—WEBSTER’S COLLEGIATE DICTIONARY (11th
ed. 2003); see Receive, BLACK’S LAW DICTIONARY (10th ed. 2019) (“To take (something offered,
given, sent, etc.); to come into possession of or get from some outside source.”). Thus, Houser
had to show that RCIS came into possession of a payment from Garney that was attributable to
work performed by Houser covered by the unpaid retainage in the first pay application and
covered by the second pay application.
Castro testified that the last payment RCIS received from Garney for Houser’s work was
on December 10, 2020, from which Houser was paid $65,000.00 on the first pay application.
Houser offered no evidence to contradict that testimony, and it does not dispute it on appeal.
The evidence also shows that on December 16, 2021, Garney interpleaded $86,649.19 into the
registry of the court. Garney represented it owed those funds to RCIS under their contract for the
Leonard Project, and for which amount Houser alleged was due it from RCIS. Those funds
remained in the registry of the court until November 3, 2023, when the funds were released to
Houser pursuant to the trial court’s order.
Because the record shows that RCIS never received, or came into possession of, a
payment from Garney that was attributable to work performed by Houser covered by the unpaid
retainage in the first pay application and covered by the second pay application, we find that
27 legally insufficient evidence supports the trial court’s award of the remaining $3,072.30 of
prompt payment interest.
We sustain this issue, and we will strike the trial court’s award of $33,423.65 in prompt
payment interest from the trial court’s judgment.17 Nevertheless, because Houser pleaded for
“pre-judgment . . . interest . . . at the highest rate allowed by law,” we will remand this case for a
determination of this issue.
IV. Attorney Fees
A. The Trial Court Did Not Abuse its Discretion in Finding a Lack of Unfair Surprise or Prejudice
RCIS also challenges the trial court’s award of attorney fees for Houser. It asserts that
the trial court abused its discretion in allowing Houser’s attorney-fee evidence because the
record does not support the trial court’s finding that RCIS was not unfairly surprised or
prejudiced by Houser’s failure to disclose documentation of its attorney fees before trial.
1. Background
The trial of this case began on April 3, 2023. Approximately three months earlier, RCIS
served requests for production and interrogatories and requested, among other things, documents
supporting Houser’s claim for attorney fees, including the resume of each person called to testify
concerning the claim, and documents showing the itemization of attorney fees and costs, and the
identities of persons for whom attorney fees were sought. On February 8, 2023, Houser
responded to the requests and interrogatories, produced no documents, and indicated that it
would “provide relevant documents in compliance with all required pre-trial deadlines regarding
17 Because we sustain this issue, we need not address RCIS’s other arguments. 28 exhibits.” It is undisputed that Houser did not produce any documents related to its claim for
attorney fees before the trial began.
Before the trial began on April 3, the parties and the trial court agreed that the issue of
attorney fees would be taken up after the determination of the outcome of the substantive case.
The trial of the substantive case concluded on April 12. On April 27, Houser filed its motion to
reopen evidence to present evidence in support of its claim for attorney fees, and it served the
motion on RCIS. Attached to the motion was the resume of Houser’s attorney, Karen Ensley,
her affidavit in which she gave detailed testimony in support of Houser’s claim for attorney fees,
and billing records. The billing records contained itemized descriptions of the work performed,
the date it was performed, the hours worked, hourly rate, dollar amounts billed, the name of the
person performing the work, and whether it pertained to the Leonard Project or to the Bellaire
Project.
On May 26, RCIS filed its response opposing the motion to reopen evidence, and the trial
court, after a hearing, granted the motion to reopen evidence. After a hearing on June 23, the
trial court awarded Houser its attorney fees.
2. Applicable Law and Standard of Review
“Under Rule 193.6 of the Texas Rules of Civil Procedure, when a party fails to timely
[make, amend, or] supplement a discovery response, the untimely disclosed evidence may be
excluded.” In re D.W.G.K., 558 S.W.3d 671, 679 (Tex. App.—Texarkana 2018, pet. denied)
(citing TEX. R. CIV. P. 193.6(a)). “Exclusion is mandatory and automatic unless the court finds
that there was good cause for the failure to [make,] amend or supplement, or the failure will not
29 unfairly surprise or prejudice the other party.” Id. (citing TEX. R. CIV. P. 193.6(a); Morrow v.
H.E.B., Inc., 714 S.W.2d 297, 297–98 (Tex. 1986) (per curiam); Good v. Baker, 339 S.W.3d 260,
271 (Tex. App.—Texarkana 2011, pet denied)). “The party seeking to introduce the evidence
has the burden of establishing good cause or lack of unfair surprise or prejudice.” Id. (citing
TEX. R. CIV. P. 193.6(b); Baker, 339 S.W.3d at 271).
“The trial court has discretion to determine whether the offering party has met its burden
to show good cause or lack of unfair surprise or prejudice, and the record must support such
finding.” Id. (citation omitted) (citing TEX. R. CIV. P. 193.6(b)). The trial court’s finding may
be supported by evidence in the record, “counsel’s uncontested representations . . . as to the state
of discovery in the case,” and “counsel’s statements made in open court without any objections .
. . if the trial court credits them.” Jackson v. Takara, 675 S.W.3d 1, 6 (Tex. 2023) (per curiam).
We “review[] a trial court’s decision under Rule 193.6(a) for abuse of discretion.” Id. (citing In
re J.P.B., 180 S.W.3d 570, 575 (Tex. 2005) (per curiam)).
3. Analysis
In In re D.W.G.K., we noted that
in order to establish the absence of unfair prejudice, the party seeking to call an untimely disclosed witness or introduce untimely disclosed evidence must establish that, notwithstanding the late disclosure, the other party had enough evidence to reasonably assess settlement, to avoid trial by ambush, and to prepare rebuttal to expert testimony.
In re D.W.G.K.¸ 558 S.W.3d at 680. RCIS argues that because Houser failed to produce
documents related to its claim for attorney fees before trial, it was unable to rebut Houser’s
expert testimony, and because the billing records produced disclosed nothing about the persons
30 listed on them (e.g., whether they were attorneys or paralegals), it was unable to properly
evaluate whether the attorney fees were reasonable and necessary.
However, as Houser’s counsel pointed out at the attorney fees hearing, if Houser had
produced documents on February 9, RCIS would have received them about eight weeks before
trial, but because the majority of work performed in the case occurred after that time, the records
would have shown only about one-quarter of the work that was performed through the end of
trial.18 Further, because Houser produced the billing records with its motion to reopen evidence
on April 27, RCIS received billing records about eight weeks before the hearing on attorney fees,
except these records showed all the work performed through the end of the trial on the
substantive trial. Also, although the billing records did not state which persons performing work
were paralegals or attorneys, it did state the work performed and the hourly rates of those
persons, and it contained several entries by an attorney for work done at a paralegal rate. As a
result, the trial court could have determined that RCIS had enough information to cross-examine
Houser’s expert regarding the rates charged and the experience of the persons shown on the
billing records.
On this record, the trial court could have reasonably concluded that, because RCIS had
the same amount of time to prepare for the cross-examination of Ensley at the attorney fees
hearing after it received the billing records and Ensley’s affidavit as it would have had to prepare
for Ensley’s cross-examination at trial, but with less information had the documents been
produced on February 8 and supplemented a few weeks later, RCIS was not unfairly prejudiced
18 Houser’s attorney also stated that even if these records had been supplemented at the end of the discovery period, they would have contained only about one-third of the total work that was performed through trial. 31 by Houser’s untimely production of the attorney-fee evidence. As a result, we find that the trial
court did not abuse its discretion in admitting the evidence. We overrule this issue, in part.
B. The Award of Attorney Fees Must Be Remanded for a New Trial
RCIS also complains that the trial court erred because the attorney fees award is
excessive in relation to the damages recoverable by Houser, and it asks us to remand the case for
a new trial to determine any attorney fees to be awarded to Houser. In this case, the trial court’s
final judgment is based on Houser prevailing on its contract claims against RCIS regarding the
Leonard Project, and awarded Houser all of its requested damages, being actual damages of
$78,491.10 and prompt payment interest of $33,423.65, for a combined total of $111,914.75.
The trial court also awarded Houser $114,896.08 in attorney fees. We have determined that
Houser released its claim to $56,500.00 of the awarded actual damages and failed to show its
entitlement to prompt payment interest. Striking these amounts from the trial court’s judgment
results in actual damages of $21,991.10, and prompt payment interest of $0.00.
The results obtained by the prevailing party is one of the factors that Texas courts take
into consideration when awarding attorney fees. In Rohrmoos Venture v. UTSW DVA
Healthcare, LLP, the Texas Supreme Court stated:
In Texas courts, the base lodestar calculation of reasonable hours times a reasonable rate should account for any results obtained up to trial. But to the extent that the results obtained are not reflected in the base lodestar, then the fact finder may determine whether the results obtained consideration necessitates an adjustment to achieve a reasonable fee under the second step of the lodestar method.
Rohrmoos Venture v. UTSW DVA Healthcare, LLP, 578 S.W.3d 469, 500 n.12 (Tex. 2019). The
Texas Supreme Court has also held that when a court of appeals substantially reduces the trial 32 court’s damages award, an award of attorney fees based in part on the results obtained may be
harmful error:
Not every appellate adjustment to the damages which a jury considered as “results obtained” when making attorney’s fees findings will require reversal. In this case, however, considering both the absolute value of the difference between the erroneous and correct amounts of damages, and the fact that the correct damages were one-seventh of the erroneous damages, we are not reasonably certain that the jury was not significantly affected by the error. Accordingly, the trial court’s error was harmful.
Barker v. Eckman, 213 S.W.3d 306, 314 (Tex. 2006).
Likewise, in this case, there is a substantial difference between the erroneous and correct
amounts of damages, and the correct damages are less than one-fifth of the erroneous damages.
As a result, we are not reasonably certain that the trial court was not significantly affected by the
error, and we find that the amount of attorney fees awarded by the trial court was harmful error.
See id. Accordingly, we sustain this issue, in part, and we will remand the case to the trial court
for a new trial as to attorney fees. See id. at 315.
V. Disposition of Interpleaded Funds
In its fifth issue, RCIS challenges the trial court’s order releasing the funds interpleaded
by Garney to Houser, and it asks us to direct the trial court on remand to order Houser to return
the released funds to the registry of the court. The trial court’s judgment ordered the clerk of the
court to release the interpleaded funds to Houser, and provided that upon release of the funds that
Houser “issue a credit in favor of [RCIS] against the Final Award, applied first against the
principal damages award and thereafter against all other amounts awarded to [Houser].”
33 “[F]unds deposited in the trial court’s registry are subject to the trial court’s control, and
the court has the equitable power to make such orders as it deems necessary to protect those
funds.” In re Scott Pelley, P.C., No. 05-21-00314-CV, 2021 WL 3891595, at *5 (Tex. App.—
Dallas Aug. 31, 2021, orig. proceeding) (mem. op.) (alteration in original) (quoting Sommers v.
Concepcion, 20 S.W.3d 27, 36 (Tex. App.—Houston [14th Dist.] 2000, pet. denied)). In this
appeal, we have substantially reduced the damages award, and we have remanded the award of
attorney fees for a new trial. Because the attorney fees award is undetermined, we are unable to
determine whether any of the released funds should be returned to the registry of the court.
As a result, we overrule this issue. That being said, because this case is being remanded,
the trial court may exercise its equitable powers to make such “further orders as it deems
necessary to protect the interpleaded funds.” US MCT, Inc. v. Brodsky, No. 05-98-00204-CV,
2001 WL 1360301, at *9 (Tex. App.—Dallas Nov. 7, 2001, no pet.) (not designated for
publication).
VI. Disposition
For the reasons stated, we affirm, in part, reverse and render, in part, and reverse and
remand, in part. We affirm the trial court’s judgment that Houser is entitled to damages. We
reverse, in part, the trial court’s judgment awarding Houser $78,491.10 in actual damages and
render judgment for $21,991.10 in actual damages. We reverse, in part, the trial court’s
judgment awarding Houser $33,423.65 in prompt payment interest and render judgment for
$0.00 in prompt payment interest. We reverse, in part, the trial court’s judgment awarding
Houser $114,896.08 in attorney fees and remand this case for a new trial on attorney fees, a
34 determination of prejudgment interest, if any, to make such further orders as it deems necessary
to protect the interpleaded funds, and to enter a final judgment consistent with this opinion.
Jeff Rambin Justice
Date Submitted: October 03, 2024 Date Decided: January 30, 2026
Related
Cite This Page — Counsel Stack
RCIS Enterprises, LLC v. Houser Fabrication, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rcis-enterprises-llc-v-houser-fabrication-llc-txctapp6-2026.