Razorback Marble Mfg. Co., Inc. v. D.D. Roberts Construction Company, Naran P. Patel, Kusum N. Patel, and Heritage Bank

CourtCourt of Appeals of Tennessee
DecidedJuly 1, 1998
Docket01A01-9709-CH-00512
StatusPublished

This text of Razorback Marble Mfg. Co., Inc. v. D.D. Roberts Construction Company, Naran P. Patel, Kusum N. Patel, and Heritage Bank (Razorback Marble Mfg. Co., Inc. v. D.D. Roberts Construction Company, Naran P. Patel, Kusum N. Patel, and Heritage Bank) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Razorback Marble Mfg. Co., Inc. v. D.D. Roberts Construction Company, Naran P. Patel, Kusum N. Patel, and Heritage Bank, (Tenn. Ct. App. 1998).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE FILED July 1, 1998 RAZORBACK MARBLE ) MANUFACTURING CO., INC., ) Cecil W. Crowson ) Appellate Court Clerk Plaintiff/Appellee, ) ) Appeal No. ) 01-A-01-9709-CH-00512 VS. ) ) Montgomery Chancery ) No. 96-07-0012 D.D. ROBERTS, ROBERTS ) CONSTRUCTION COMPANY, ) NARAN P. PATEL, KUSUM N. ) PATEL, and HERITAGE BANK, ) ) Defendant/Appellant. )

APPEALED FROM THE CHANCERY COURT OF MONTGOMERY COUNTY AT CLARKSVILLE, TENNESSEE

THE HONORABLE ALEX W. DARNELL, CHANCELLOR

RODGER N. BOWMAN 601 North Second Street, Suite 4 Clarksville, Tennessee 37041-1404 Attorney for Plaintiff/Appellee

LARRY J. WALLACE 118 Franklin Street Clarksville, TN 37040 Attorney for Defendants/Appellants

AFFIRMED AS MODIFIED AND REMANDED

BEN H. CANTRELL, JUDGE

CONCUR: TODD, P.J., M.S. KOCH, J. OPINION

In this construction contract dispute, the Chancery Court of Montgomery

County granted a judgment plus prejudgment interest to Razorback Marble

Manufacturing Company, Inc. On appeal, Roberts Construction Company, Inc. and

D. D. Roberts, Individually, raise issues pertaining to the Contractor’s Licensing

statutes and the Notice of Non-Payments statute. Razorback insists that it was due

a larger judgment and a greater award of prejudgment interest.

I.

Roberts Construction Company, Inc. received the contract to construct

a Fairfield Inn in Clarksville. D. D. Roberts, president of the company, entered into a

contract with Razorback Marble Manufacturing Company, Inc., an Arkansas

corporation, to install marble products in the motel for a total contract price of

$39,850.16. Razorback does not have a contractor’s license in Tennessee.

Razorback, however, completed its work and some extra work it claims

the general contractor’s agents authorized and requested. When it did not receive

payment, Razorback sued Roberts Construction and Mr. Roberts. The complaint

alleged that pursuant to Tenn. Code Ann. § 66-11-145 Razorback gave notice of non-

payment to the defendants on May 22, 1996. The defendants’ answer admitted the

allegation. The chancellor entered judgment in favor of Razorback in the amount of

the original contract plus $3,800.75 of extras, and allowed prejudgment interest on the

original contract amount to run from December 8, 1996.

II.

-2- The first three issues raised by the defendants on appeal pertain to

Razorback’s failure to have a contractor’s license in Tennessee. Because of this fact,

the defendants allege that Razorback’s recovery must be limited to actual

documented expenses that can be shown by clear and convincing proof. See Tenn.

Code Ann. § 62-6-103(b). Since the record does not contain proof of specific

expenses, the appellants argue that the judgment in favor of the plaintiff must be

reversed.

We note, however, that the issue of the license was not raised as a

defense in the defendants’ answer. When the question was first asked at the trial,

Razorback’s lawyer objected because the defense had not been pled. In the ensuing

discussion the court immediately ruled that Razorback did not have to have a license

if they were doing work for a contractor. There the issue died in the trial court.

Although the issues in this court relate to the question of whether a

contractor in Razorback’s position needs to be licensed in Tennessee, we think the

defense has been waived by the defendants’ failure to plead it in the court below. See

Tenn. R. Civ. Proc. 12.08. The defendants rely on the fact that Razorback did not put

on any proof of its actual documented expenses in order to recover anything under

Tenn. Code Ann. § 62-6-103(b), but since the licensing statute had not been raised

as a defense Razorback was not on notice that it needed to do so. Thus, it would not

be fair to reject the claim at this stage based on a defense that was not raised below.

We, therefore, pretermit the question of whether Razorback was

required to have a Tennessee license. We do note, however, that in the massive

overhaul of the licensing statute in 1994, the legislature repealed the statute that

specifically exempted sub-contractors from the statute’s requirements. And we find

no comparable exemption in the present statute, although the sponsor of the 1994 act

stated on the House floor that his bill had no effect on the sub-contractors. We defer

-3- any judgment on the proper interpretation of the statute until the question is squarely

presented to us.

III.

The appellants also rely on Tenn. Code Ann. § 66-11-145(a), which

requires a notice of nonpayment to be given to the owner and the contractor

contracting with the owner within sixty days of the last day of the month in which work

was performed. While we note, parenthetically, that the only consequence of failing

to comply with the statute is a loss of lien rights, see Tenn. Code Ann. § 66-11-145(c),

the complaint in this case alleged that the notice had been given and the defendants’

answer admitted it.

For these reasons we think this issue is without merit.

IV.

The appellants assert that the chancellor erred in admitting evidence of

an offer to compromise Razorback’s claim. The record reveals that the issue came

up in the following way:

Q. [Mr. Bowman] Okay. Mr. Roberts, this FAX contains the total billing for the project as far as Razorback was concerned. And you received this on April 4th, 1996?

A. Yes.

Q. Did you ever call Razorback when you received this and complain to them in any fashion about the work that had been done or the charges that had been made? A. Yes, I called them, even wrote them a letter.

Q. Could I see the letter that you wrote to them?
A. I don’t have the letter. I have their reply to my letter.
Q. Where is the letter that you sent? Do you know?
A. I don’t know. We got it lost somewhere.

-4- Q. May I see the reply to the letter?

A. Here’s the reply to the letter.
Q. May I see that, please?

(Document passed to Mr. Bowman.)

This was in response to your offer to settle this matter, is that correct?

A. That’s right.

MR. WALLACE: Objection, Your Honor.

THE COURT: No, he can use it, whatever the letter says.

MR. BOWMAN: Let’s make this Exhibit 5 to your testimony.

MR. WALLACE: For the record again, I’m going to object that settlement offers are not admissible.

THE COURT: Of course, the question comes down, counselor, to whether the work was done or not. And the letter itself may reveal certain things. It has nothing to do with settlement.

The letter made an exhibit at that point was actually a letter from

Razorback to Mr. Roberts and it contained the following:

We will settle the account on the Fairfield Inn for a certified check of $40,000.00 for the marble work, also a $1,350.00 certified check for plumbing and wood work around the whirlpools.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 47-14-123
Tennessee § 47-14-123
§ 62-6-103
Tennessee § 62-6-103(b)
§ 66-11-145
Tennessee § 66-11-145

Cite This Page — Counsel Stack

Bluebook (online)
Razorback Marble Mfg. Co., Inc. v. D.D. Roberts Construction Company, Naran P. Patel, Kusum N. Patel, and Heritage Bank, Counsel Stack Legal Research, https://law.counselstack.com/opinion/razorback-marble-mfg-co-inc-v-dd-roberts-construct-tennctapp-1998.