Raytheon Co. v. Exelon Mystic Development, LLC

17 Mass. L. Rptr. 86
CourtMassachusetts Superior Court
DecidedNovember 25, 2003
DocketNo. 034183BLS
StatusPublished

This text of 17 Mass. L. Rptr. 86 (Raytheon Co. v. Exelon Mystic Development, LLC) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Raytheon Co. v. Exelon Mystic Development, LLC, 17 Mass. L. Rptr. 86 (Mass. Ct. App. 2003).

Opinion

van Gestel, J.

The Court addresses here a motion by defendants Exelon Mystic Development, LLC, Ex-elon Fore River Development, LLC, and Exelon Boston Generating, LLC (the “Exelon defendants”), to dismiss the first amended complaint.2

BACKGROUND

This case involves a complex series of construction contracts, guarantee agreements, letters of credit, and other negotiated instruments concerning the construction of two electric generating facilities in Everett, Massachusetts (the “Mystic Facility”), and in Weymouth, Massachusetts (the “Fore River Facility”). Through its first amended complaint, Raytheon Company (“Raytheon”) seeks various forms of equitable and other relief concerning its obligations under the construction contracts and the guarantee agreements, with regard to certain letters of credit, and for certain assurances of compensation.

The Exelon defendants claim that the complaint should be dismissed in favor of an earlier-filed action in New York and because the first amended complaint fails to state valid claims for relief.

On December 31, 1999, Raytheon Engineers & Constructors, Inc. (“RE&C”), then a wholly owned subsidiary of Raytheon, entered into an agreement (the “Mystic EPC Agreement”) with Sithe Mystic Development, LLC (“Sithe Mystic”).3 Pursuant to the Mystic EPC Agreement, RE&C was to design, engineer, procure, start up, test, deliver, and warrant the Mystic Facility. On May 8, 2000, RE&C entered into a similar agreement (the “Fore River EPC Agreement”) with Sithe Fore River Development, LLC (“Sithe Fore River”) for construction of the Fore River Facility. Raytheon, the parent of RE&C, signed Guarantee Agreements for each Facility, guaranteeing the obligations of its subsidiary, RE&C, under those Agreements.

Sithe Mystic and Sithe Fore River are, respectively, the predecessors to Exelon Mystic and Exelon Fore River.

Each of the EPC Agreements and the Guarantee Agreements dictates that New York law should apply. Further, the Agreements provide that the parties thereto submitted to the non-exclusive jurisdiction of the New York courts, and waived any objections to improper venue or inconvenience in New York.

During the time of construction of both Facilities, RE&C was acquired by Washington Group International, Inc. (“WGI”). In March 2001, WGI stopped performing under its agreements and subsequently declared Chapter 11 bankruptcy.

After WGI stopped performing, also in March 2001, Sithe Mystic and Sithe Fore River filed an action in New York Supreme Court (the “New York Action”) seeking to compel Raytheon to honor its guarantees. See Sithe Fore River Development, LLC et al. v. Raytheon Company, Supreme Court, New York County, Index No. 601206/01. This case is being handled by Justice Charles E. Ramos. In the New York litigation, Raytheon entered into an agreement, on the record, to perform its obligations under the EPC and Guarantee Agreements. The New York Court entered the following order: “(T]his Court reserves jurisdiction to determine whether in light of the for[e]going, defendant, Raytheon Corporation, is performing the guaranty obligations in accordance with the guaranty agreements.”

The New York Action is still pending because no final judgment has yet been entered in that case.

Further, recently there has been filed another action in the New York Supreme Court, which is also pending before Justice Ramos. The new action is captioned Mitsubishi Heavy Industries, Ltd. et al v. Exelon Mystic Development, LLC, Supreme Court, New York County, Index No. 603104/03 (the “Mitsubishi Action”). In the Mitsubishi Action, Mitsubishi claims monies due from the owners of the two electric generating plants in issue for work performed by Mitsubishi as a sub-contractor on the two projects. The Exelon entities assert that Raytheon, as guarantor of the obligations of the former general contractor, is the [111]*111party that owes any monies that may be due to Mitsubishi.

The Exelon defendants in the Mitsubishi Action have moved before Judge Ramos to join Raytheon as a necessary party to that case and to consolidate it with the original New York Action mentioned above.

As recently as October 22, 2003, in the Mitsubishi Action, Judge Ramos held a hearing regarding issues relating to, among other things, the joining of Raytheon as a party in that case.4 A further hearing was scheduled for November 21, 2003. This Court is not aware of the results of that hearing, or even if it was held.

Raytheon’s claims in this case arise out of public announcements first made by or on behalf of Exelon Mystic and Exelon Fore River on July 29, 2003, that the Mystic Facility and the Fore River Facility are being turned over to the group of lenders for the projects, in whole or partial satisfaction of a $1.1 billion debt on which they are in default. Since that announcement was made, Raytheon has continued to perform under its guarantees, allegedly expending approximately $350,000 per day.

Raytheon has requested the Exelon defendants to provide assurances that, despite their planned abandonment of the Facilities, they will honor their payment obligations to Raytheon, including a refund of approximately $38 million in pre-paid, contingent liquidated damages alleged to be due and owing to Raytheon.

Raytheon claims that it is entitled, under New York law, to demand adequate assurance of future performance by the Exelon defendants and that, in the absence thereof, Raytheon is entitled to suspend or terminate performance under its guarantees. Raytheon also contends that, as evidenced by the Exelon defendants’ public announcements and their failure to respond to Raytheon’s demands for adequate assurances of future performance, the Exelon defendants are insolvent, which also enables Raytheon to suspend or terminate performance under its guarantees. Still further, Raytheon alleges that the Exelon defendants have defaulted on certain payment obligations to it, thereby jeopardizing Raytheon’s ability to be paid for its performance.

Section 33.1.1 of the EPC Agreements requires the parties to engage in executive-level negotiations prior to arbitrating or litigating any dispute under the contracts and permits litigation only for claims in excess of $25 million (or claims for personal injury or property damage). There are other dispute resolution and remedial provisions in the EPC Agreements which address nearly every disagreement between the parties. The Exelon defendants claim that two remedial provisions in particular are directly implicated by the first amended complaint.

First, the EPC Agreements contain a standard “retainage” clause providing that Exelon Mystic and Exelon Fore River may retain 10% of each milestone payment to Raytheon as security for Raytheon’s performance. In lieu of actually retaining 10% of each payment, the Agreements give Raytheon the option “to deliver to Owner an irrevocable bank letter of credit.” The Owner is then entitled to draw on the letter of credit “without right of objection” by Raytheon to complete the work. During construction at the Mystic Facility, Raytheon opted to provide three retainage letters of credit in lieu of the 10% retainage amounts. Raytheon, in this suit, seeks to have the Court enjoin all draws on those letters of credit (and on an additional letter of credit for the Fore River Facility).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

W.R. Grace & Co. v. Hartford Accident & Indemnity Co.
555 N.E.2d 214 (Massachusetts Supreme Judicial Court, 1990)
Doe v. the Governor
412 N.E.2d 325 (Massachusetts Supreme Judicial Court, 1980)
Joly v. Albert Larocque Lumber Ltd.
489 N.E.2d 698 (Massachusetts Supreme Judicial Court, 1986)
Rogaris v. Albert
730 N.E.2d 869 (Massachusetts Supreme Judicial Court, 2000)
Schaer v. Brandeis University
735 N.E.2d 373 (Massachusetts Supreme Judicial Court, 2000)
Green v. Manhattanville College
661 N.E.2d 123 (Massachusetts Appeals Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
17 Mass. L. Rptr. 86, Counsel Stack Legal Research, https://law.counselstack.com/opinion/raytheon-co-v-exelon-mystic-development-llc-masssuperct-2003.