Ray M. Lee Co. v. Satcher Co.

93 S.E.2d 797, 94 Ga. App. 130, 1956 Ga. App. LEXIS 485
Court of Appeals of Georgia·Decided July 5, 1956·No. 36188·Published

Opinion

Felton, C, J.

The court did not err in overruling the objection to the amendment of paragraph 4. Paragraph 4 of the original petition merely alleged that the defendants were indebted to the plaintiff in a certain amount because the plaintiff “furnished” the defendant certain materials. The amendment was merely an elaboration and amplification of the original allegation and was in response to a special demurrer to that paragraph, the demurrer being, “Defendant demurs specially to the 4th paragraph of said petition as being vague, indefinite and uncertain because it is not alleged in said paragraph, or elsewhere in said petition, to whom plaintiff 'furnished’ the 8040 sq. feet of roof decking insulation referred to in said paragraph.” The amendment did not set out a new and different cause of action from that originally alleged.

The plaintiff contends that the defendant is liable for the material purchased because: “The defendant, R. H. White Company, Inc., ordered the materials herein described for its own use as subcontractor of Ray M. Lee Company, but prior to the completion of the services agreed to be performed under said subcontract, Ray M. Lee Company took possession of the materials which had been delivered to the job site by this plaintiff, together with materials which had been delivered by others, and physically took over the subcontract and ousted R. H. White Company, Inc., from the j oh and completed said subcontract itself and in so doing, it adopted the subcontract as its own, it received the benefits [132] of said contract and it is liable for all of the obligations of R. H. White Company, arising under said subcontract.” The pertinent evidence is as follows: C. H. Stinson, an employee of the defendant, Ray M. Lee Company, was called for the purpose of cross-examination as an agent of the opposing party, and after being sworn, testified that he was secretary and treasurer of Ray M. Lee Company. Ray M. Lee Company was the general contractor that built the hospital commonly known as “St. Joseph.” In the construction of the hospital, the Lee Company subcontracted a good part of its work, and there were working on the job approximately twenty-six or twenty-eight subcontractors from time to time. The subcontract with R. H. White Company was to install insulation around the heating and cooling ducts which were being installed by Modem Roofing & Metal Works, which had a subcontract for that duct work. The subcontract with the White Company provided that the cost of the work would be $26,505.00. The subcontract was not introduced in evidence, but was available for inspection at the trial. Work was begun under the subcontract in August, 1951. During the month of October, 1951, Lee Company paid to White Company $2,000.00 on account of the subcontract. On or about October 29, 1951, after White had begun work, one of the materialmen to White Company, Noland Company, notified Ray M. Lee Company that White Company was past due in the amount of $4,691.00, its account with them for the hospital job. R. H. White Company was working on two or three other jobs at the same time. On October 31, 1951, laborers working for White Company did not receive their week’s wages because the checks given them by White Company did not clear the bank on account of insufficient funds. At this time R. H. White, as the General Manager of R. H. White Company, came to Atlanta, Georgia, to discuss his financial difficulties with this witness. It was estimated at this conference that the subcontract would cover the cost, and White would make several thousand dollars. Lee Company gave the checks to the employees of White Company to cover the payroll, and Lee Company paid off the Noland account, charging these advances against White on the subcontract. From November, 1951, until the completion of the insulation work on January 18, 1953, Lee Company paid with its own checks all wages of men employed by White on [133] St. Joseph’s Hospital, and charged the advances to the White subcontract. A total of about $14,723 was paid in this manner for labor. It did not take many men to work on this insulating; many times there were only two on the weekly payroll. If Lee Company had not paid for a great deal of the materials and for the labor to complete the insulation of the ducts, it would never have been completed by White Company.

Mr. Stinson further testified on cross-examination that V. C. Hughes was the general superintendent of this job; that Hughes, as a general superintendent, had the duty to check all materials and merchandise delivered on the site, and to see that nO‘ materials were taken off the job site; he made regular reports on progress of the work. Mr. Hughes was instructed to watch R. H. White Company closely after Lee discovered that White was in financial difficulties. The following communication was identified by the witness and introduced in evidence by the plaintiff, without objection: “11/10/51. Mr. Hughes: Please keep a close check so that we can charge telegrams or telephone charges to It. H. White acct. (Signed) Stinson.” Mr. Stinson explained that this message was to prevent White or his employees from making calls or sending telegrams that were not charged to the White subcontract.

Mr. Stinson further testified on cross-examination that White Company could not get delivery of a great deal of the materials to complete the work of White Company unless Lee Company guaranteed payment to the materialmen, and this Lee Company did in an effort to get the White Company work done. From the beginning of November, 1951, until April 7, 1953, Ray M. Lee Company paid for all materials which they guaranteed, and which was all that they knew about, for White Company which were used by White Company on the job, and this totaled $10,417.00; that toward the end of the job it became apparent that the work which was being done by White Company under his subcontract was going to cost White Company more than the subcontract price; the witness identified the following communication, which was written at that time, and it was introduced in evidence by the plaintiff without objection: “Inter-office correspondence, 8/16/52. To: V. C. Hughes, From: C. H. Stinson, Subj: R. H. White—Men & material. Confirming Mr. Lee’s instructions re[134] garding R. H. White men and material, this is to advise you to continue to keep a close check, and not to let any material be moved from the job. Concerning the men, White has to trim down to Mauldin and one man. The excess material on the job belongs to Ray M. Lee Company, and we are going to return it for credit in our name. Hold tight! Very truly yours, Ray M. Lee Company, Inc. By: C. H. Stinson.”

Free access — add to your briefcase to read the full text and ask questions with AI

Ray M. Lee Co. v. Satcher Co., 93 S.E.2d 797, 94 Ga. App. 130, 1956 Ga. App. LEXIS 485 (Ga. Ct. App. 1956).

93 S.E.2d 797 (Ray M. Lee Co. v. Satcher Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.