Ray Bell Construction Co. v. State of Tennessee, Department of Transportation

CourtCourt of Appeals of Tennessee
DecidedNovember 24, 2010
DocketE2009-01803-COA-R3-CV
StatusPublished

This text of Ray Bell Construction Co. v. State of Tennessee, Department of Transportation (Ray Bell Construction Co. v. State of Tennessee, Department of Transportation) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ray Bell Construction Co. v. State of Tennessee, Department of Transportation, (Tenn. Ct. App. 2010).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE August 31, 2010 Session

RAY BELL CONSTRUCTION CO., INC. v. STATE OF TENNESSEE, TENNESSEE DEPARTMENT OF TRANSPORTATION

Appeal from the Claims Commission No. T20071215-1 William O. Shults, Commissioner 1

No. E2009-01803-COA-R3-CV - Filed November 24, 2010

This case concerns an alleged breach of contract involving the incentive clause of a Tennessee Department of Transportation (“TDOT”) road construction contract. Before the Claims Commission, TDOT argued that the contract language was clear in prohibiting an extension, alteration, or amendment of the incentive clause. The Claims Commission agreed with the position of Ray Bell Construction Company (“RBCC”) that it was entitled to a modification of the incentive provision. To so find, the Commission held that “a definite latent ambiguity exists for which parol evidence not only is admissible, but frankly, absolutely necessary in both understanding and deciding the issues in this case.” TDOT has appealed. We affirm the decision of the Claims Commission.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Claims Commission Affirmed; Case Remanded

J OHN W. M CC LARTY, J., delivered the opinion of the Court, in which H ERSCHEL P. F RANKS, P.J., joined, and D. M ICHAEL S WINEY, J., filed separate dissenting opinion.

Robert Cooper, Jr., Attorney General & Reporter; Michael E. Moore, Solicitor General; and Melissa Moreau, Assistant Attorney General, Nashville, Tennessee, for the appellant, State of Tennessee.

Gregory L. Cashion, Matthew J. DeVries, and Craig N. Mangum, Nashville, Tennessee, for the appellee, Ray Bell Construction Company, Inc.

1 Sitting by interchange for Commissioner Nancy Miller-Herron, Commissioner for the Western Grand Division. OPINION

I. BACKGROUND

The project at issue was located at the I-40/I-240 Midtown Interchange beginning at Ayers Street and extending to Vollintine Avenue in Memphis, Shelby County, Tennessee (the “Midtown Interchange Project”).2 RBCC’s scope of work included grading, drainage and paving work, as well as the construction of seven bridges, 22 retaining walls and 12 noise barriers. Funding for the $52.8 million contract was split between TDOT at 10 percent participation and the Federal Highway Administration (“FHWA”) at 90 percent participation.

When TDOT refused to agree that RBCC was entitled to recover an incentive payment upon completion of its work, RBCC filed a claim in the Claims Commission on May 4, 2007. The trial was conducted in this matter October 27-30, 2008.

PROVISIONS REGARDING CONTRACT TIME

The contract between RBCC and TDOT contained two distinct sections that address time extensions – the Standard Specifications and the Special Provisions. Standard Specification 108.06 allowed RBCC to receive a time extension where the work quantities have been increased and the work has been delayed due to reasons beyond RBCC’s control:

The number of days for performance allowed in the Contract as awarded is based on the original quantities as defined in Subsection 102.03. If satisfactory fulfillment of the Contract requires performance of work in greater quantities than those set forth in the proposal, the contract time allowed for performance shall be increased on the basis commensurate with the amount and difficulty of the added work. If the Engineer determines that an increase in the contract working time proportionate to the value of the increase in quantities is commensurate with the amount and difficulty of the added work and a written request to extend the time as provided below has not

2 As noted by the Commission, “[t]he planning stages for this project began in the late 1960’s and at one point involved a case which resulted in an important United States Supreme Court decision.” See Citizens to Preserve Overton Park, Inc. v. Volpe, 401 U.S. 402, 91 S.Ct. 814, 28 L.Ed. 136 (1971). When the interchange at issue was originally designed, the plans had it extending through the center of Memphis and through Overton Park. The revisions to the plans resulted in an interchange with I-40 traffic making an awkward turn onto a one-lane, 25-mile-per-hour ramp. The project at issue was designed to correct the perceived deficiencies.

-2- been made, he may proportionately increase the contract working time.

If the Contractor finds it impossible for reasons beyond his control to complete the Work within the contract time as specified or as extended in accordance with the provisions of this Subsection, he may, at any time prior to the expiration of the contract time specified or as extended, make a written request to the Engineer for an extension of time setting forth therein the reasons which he believes will justify the granting of his request. The Contractor’s plea that insufficient time was specified is not a valid reason for extension of time. If the Engineer finds that the Work was delayed because of conditions beyond the control and without the fault of the Contractor, he may extend the time for completion by a properly executed Supplemental Agreement in such amount as the conditions justify. The extended time for completion shall then be in full force and effect the same as though it were the original time for completion.

(Emphasis added). Fred Clayton, formerly employed by TDOT for 17 years and RBCC’s Project Manager3 on the Midtown Interchange Project, testified at trial that the first paragraph above invokes the use of the “pro-rata method” for determining a time extension when there are quantity overruns – i.e., a time extension will be granted on a pro-rata basis for the increased quantities of work above and beyond the original bid. According to Mr. Clayton, the second paragraph deals with those delays beyond a contractor’s control, such as a change in design or TDOT’s inability to secure an easement to property.

Special Provision 108(B) (“SP108B”) addressed liquidated damages, incentive payments and disincentive payments as follows:

The project shall be completed in its entirety on or before December 15, 2006.

For each calendar day prior to December 15, 2006, that all work in the original contract has been completed and all lanes are opened to the free, safe and unrestricted passage of traffic, an incentive payment of ten thousand dollars ($10,000) per day shall be made to the contractor as an incentive. However, the maximum amount of incentive payments shall not exceed two million five hundred thousand dollars ($2,500,000).

For each day after December 15, 2006, that all work in the original contract is

3 As Project Manager, Mr. Clayton was generally involved in the day-to-day operations of the project. He was also the primary point of contact for TDOT and its engineer of record, Allen & Hoshall.

-3- not completed, the sum of ten thousand dollars ($10,000) per day shall be deducted from monies due the Contractor as a disincentive. The amount of monies that may be deducted as a disincentive shall be unlimited except that the disincentive may be waived if the working time is extended in accordance with the Standard Specifications.

. . . The December 15, 2006, completion date may be extended in accordance with the Standard Specifications, however, no incentive payment will be made if work is not completed in its entirety by December 15, 2006.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Citizens to Preserve Overton Park, Inc. v. Volpe
401 U.S. 402 (Supreme Court, 1971)
Christenberry v. Tipton
160 S.W.3d 487 (Tennessee Supreme Court, 2005)
Win Myint and wife Patti KI. Myint v. Allstate Insurance Company
970 S.W.2d 920 (Tennessee Supreme Court, 1998)
Wilson v. Moore
929 S.W.2d 367 (Court of Appeals of Tennessee, 1996)
Burlison v. United States
533 F.3d 419 (Sixth Circuit, 2008)
Story v. Lanier
166 S.W.3d 167 (Court of Appeals of Tennessee, 2004)
Gredig v. Tennessee Farmers Mutual Insurance Co.
891 S.W.2d 909 (Court of Appeals of Tennessee, 1994)
Allstate Insurance Co. v. Watson
195 S.W.3d 609 (Tennessee Supreme Court, 2006)
Estate of Burchfiel v. First United Methodist Church of Sevierville
933 S.W.2d 481 (Court of Appeals of Tennessee, 1996)
Union Carbide Corp. v. Huddleston
854 S.W.2d 87 (Tennessee Supreme Court, 1993)
Airline Construction, Inc. v. Barr
807 S.W.2d 247 (Court of Appeals of Tennessee, 1990)
Coble Systems, Inc. v. Gifford Co.
627 S.W.2d 359 (Court of Appeals of Tennessee, 1981)
Stickley v. Carmichael
850 S.W.2d 127 (Tennessee Supreme Court, 1992)
Planters Gin Co. v. Federal Compress & Warehouse Co.
78 S.W.3d 885 (Tennessee Supreme Court, 2002)
Bonastia v. Berman Bros., Inc.
914 F. Supp. 1533 (W.D. Tennessee, 1995)
Wells v. Tennessee Board of Regents
9 S.W.3d 779 (Tennessee Supreme Court, 1999)
Penske Truck Leasing Co. v. Huddleston
795 S.W.2d 669 (Tennessee Supreme Court, 1990)
Richland Country Club, Inc. v. CRC Equities, Inc.
832 S.W.2d 554 (Court of Appeals of Tennessee, 1991)
Minor v. Minor
863 S.W.2d 51 (Court of Appeals of Tennessee, 1993)
Brungard v. Caprice Records, Inc.
608 S.W.2d 585 (Court of Appeals of Tennessee, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
Ray Bell Construction Co. v. State of Tennessee, Department of Transportation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ray-bell-construction-co-v-state-of-tennessee-depa-tennctapp-2010.