Rawick Manufacturing Co. v. Talisman, Inc.

706 S.W.2d 194, 17 Ark. App. 202, 1986 Ark. App. LEXIS 2121
CourtCourt of Appeals of Arkansas
DecidedMarch 26, 1986
DocketCA 85-354
StatusPublished
Cited by2 cases

This text of 706 S.W.2d 194 (Rawick Manufacturing Co. v. Talisman, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rawick Manufacturing Co. v. Talisman, Inc., 706 S.W.2d 194, 17 Ark. App. 202, 1986 Ark. App. LEXIS 2121 (Ark. Ct. App. 1986).

Opinion

Tom Glaze, Judge.

Rawick Manufacturing Company, Inc., appeals from a chancellor’s decree which found (1) that a construction project — developed by appellee Phillips Development Corporation (Phillips) — to which Rawick supplied materials was a public project not subject to a materialman’s lien, and (2) that Rawick also could not recover its claim for unpaid supplies as a third-party beneficiary under a bank’s letter of credit issued to Phillips to protect the purchaser of the project, appellee White River Regional Housing Authority (Housing Authority), against any liens filed under Arkansas law. We believe the chancellor clearly erred in finding the project was public and not subject to Rawick’s materialman’s lien.

The facts giving rise to this litigation on appeal are undisputed. On June 26, 1981, appellees Talisman, Inc. (Talisman) and Phillips entered into a contract whereby Talisman would construct twenty-five public housing units on land owned by Phillips. The project was financed with private funds. On July 7, 1981, Phillips entered into a “Turnkey Contract of Sale” with the Housing Authority, and that contract provided that Phillips would sell the project upon its completion to the Housing Authority. On July 9, 1981, Rawick submitted to Talisman a proposal to supply materials for the project, which Talisman accepted on July 22, 1981.

Rawick delivered the last of its materials for the project to Talisman in February 1982. Phillips, by warranty deed dated March 29, 1982, and recorded April 6, 1982, conveyed the “turnkey project” to the Housing Authority. On April 7, 1982, Rawick notified Phillips that it was claiming a materialman’s lien on the project, because Talisman had not paid Rawick for the materials Rawick had furnished. On July 11,1983, Rawick filed an action to enforce the lien against appellees Phillips, Talisman, the Housing Authority and its director. After the issues were joined, the chancellor dismissed Rawick’s complaint.1

Rawick contends the project was privately owned and funded during the period it supplied materials for the project’s construction, and its materialman’s lien validly attached and could not be impaired by Phillips’ subsequent sale of the turnkey project to the Housing Authority. Appellees counter, arguing the evidence clearly showed the project was a public one and, therefore, Rawick could have no liens against the subject public improvement. We believe Rawick’s argument unquestionably is correct.

Rawick’s entitlement to a materialman’s lien and its enforcement is rooted in both Arkansas’s statutory and case law. Too, while Arkansas courts have not decided the exact legal issue presented here, the Missouri Supreme Court has, and it held contrary to the decision the trial judge reached below and to what the appellees ask us to do here. See Home Building Corp. v. Ventura Corp., 568 S.W.2d 769 (Mo. 1978). Because the factual situation in Ventura is almost exactly on all fours with the one here, we discuss that holding first.

In Ventura, as here, a private developer, Ventura Corporation, had contracted to sell a “turnkey” housing project to a local housing authority. The project was to be constructed on property owned by the developer. There, like the case here, a material supplier was unpaid and, after the completed project had been conveyed to the housing authority, the supplier sought to perfect and enforce its lien against the property comprising the housing project. There, as here, the housing authority urged that the property was public property not subject to a mechanic’s or materialman’s lien. The Missouri Supreme Court disagreed, stating:

[T]he first question to be resolved is whether this property was municipally owned property at the time the lien attached. We conclude that it was not. As previously noted, Authority became the equitable owner when it contracted to buy the tract and to receive a deed thereto after the housing units had been erected. However, Ventura retained possession of the property and under its contract with Authority was to erect housing units thereon. It retained control over the tract until the units were completed and a deed executed. It continued to be an owner which had the authority to contract for erection of improvements which resulted in the statutory lien which HBC [Home Building Corporation] claims under the provisions of Chapter 429 [dealing with establishment of mechanic’s liens]. This was not municipal property at this point.

Id. at 775.

In the instant case, Phillips, like Ventura Corporation, was a private developer who retained ownership (1) while the housing project was constructed, and (2) after the Housing Authority acquired an asserted equitable interest in the project by virtue of its “Turnkey Contract of Sale” executed on July 7, 1981. All appellees concede the project was privately owned and funded during the entire period Rawick supplied materials to the project. As was true in Ventura, the project was simply not public when Rawick’s lien attached. On this point, we need only note that in Arkansas, the lien of a materialman attaches when the materials are used in the improvement, Eudora Lumber Co. v. Neal & Jones, 263 Ark. 40, 562 S.W.2d 294 (1978), and the lien relates back to the commencement of construction of the improvement. Wiggins v. Searcy Federal Savings & Loan Association, 253 Ark. 407, 486 S.W.2d 900 (1972). Again, it is undisputed that Phillips owned and funded the project when its construction commenced and when Rawick furnished supplies that were incorporated into the improvement.

Relevant to another argument made by appellees here, the Missouri court in Ventura further held the local authority’s purchase of a project upon which a lien exists does not destroy that lien bécause the project was municipally owned. Under a Missouri statute, an authority’s real property is exempt from levy and sale and no execution or judicial process can issue against the property nor can judgment against an authority be a charge or lien upon its property. See Mo. Ann. Stat. § 99.200 (Vernon 1971); cf. Ark. Stat. Ann. § 19-3022 (Repl. 1980) (identical provision).

Although an authority’s real property is exempt from liens under § 99.200, the Missouri Supreme Court determined it would be unjust to permit a municipality, by purchasing property which is subject to claims for mechanic’s lien rights, to defeat those liens simply because the property has been acquired for municipal purposes. In support of its holding, the court cited Crane Creek Irrigation District v. Portland Wood Pipe Co., 231 F. 113 (9th Cir. 1916); City of Salem v. Lane & Bodley Co., 189 Ill. 593, 60 N.E. 37 (1901); Findorff v. Fuller & Johnson Mfg. Co., 212 Wis. 365, 248 N.W. 766 (1933); and Meads v. Dial Finance Co., 56 Ala. App. 84, 319 So.2d 281 (Ct. App. 1975).

The Missouri court’s Ventura decision makes sense, especially when we consider its applicability to the facts here.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cornerstone Land Development Co. of Pittsburgh LLC v. Wadwell Group
959 A.2d 1264 (Superior Court of Pennsylvania, 2008)
Opinion No.
Arkansas Attorney General Reports, 1990

Cite This Page — Counsel Stack

Bluebook (online)
706 S.W.2d 194, 17 Ark. App. 202, 1986 Ark. App. LEXIS 2121, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rawick-manufacturing-co-v-talisman-inc-arkctapp-1986.