Rauhauser v. Owatonna Canning Co.

208 N.W. 194, 166 Minn. 487, 1926 Minn. LEXIS 1227
CourtSupreme Court of Minnesota
DecidedApril 1, 1926
DocketNo. 25,179.
StatusPublished
Cited by1 cases

This text of 208 N.W. 194 (Rauhauser v. Owatonna Canning Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rauhauser v. Owatonna Canning Co., 208 N.W. 194, 166 Minn. 487, 1926 Minn. LEXIS 1227 (Mich. 1926).

Opinion

Holt, J.

Plaintiff, a farmer, made an agreement with defendant, a canning company, to seed 6| acres to peas when and as directed by defendant, and to harvest and deliver the crop when the latter determined that it was fit for canning. The plot of ground on plaintiff’s farm where the crop was to be raised was selected by defendant who also furnished the seed, 2á bushels at $5 per bushel. Defendant agreed to pay plaintiff 2¿ cents a pound for the peas as shelled at the factory. The crop was planted as agreed. When approaching the canning condition, plaintiff claims he brought in samples, and urged defendant to go out and examine the crop to see if it was ready for harvesting, that defendant delayed doing so, and finally when its manager came out plaintiff was informed that the peas were too far matured for canning, refused them and advised that the only thing plaintiff could do was to try and save the crop for seed; that plaintiff attempted to so do, but rain and hail ruined the crop so that nothing could be saved. Defendant contended that it was plaintiff’s fault that the crop was not cut and brought to the factory in time, and that, before the peas were ready for canning, plaintiff voluntarily elected to let them mature for seed peas. In the answer, in addition to the defense that plaintiff breached the contract, defendant set up two counterclaims, viz: The amount due for the seed furnished, and for the profit it would have made had plaintiff delivered his crop under the contract. There was a verdict for plaintiff. Defendant’s motion for a new trial was denied, and it appeals from the judgment entered on the verdict.

Of the contract there is no dispute. Plaintiff undertook to raise a crop of peas for canning upon a plot of ground selected by defendant, from seed furnished by it, and was to plant, cultivate, cut and *489 deliver the crop under the direction of defendant. Nor is there any contention that plaintiff did not fully perform or did not raise a fine crop of peas to the canning stage. The dispute is over the defense that plaintiff broke the contract by refusing to harvest the peas when directed to, instead electing to let the peas mature for seed, and the contrary claim of plaintiff that defendant breached the contract by delaying, against plaintiff’s urgent protest, to examine the crop, in order to determine when it was fit to cut and deliver, as under the contract it had agreed to do, until the peas became too mature for canning, and then refused to accept them. The jury accepted plaintiff’s contentions. With the issues thus settled in plaintiff’s favor, defendant nevertheless claims the verdict should not stand because of its amount and the faulty instructions as to the measure of damages.

It is well to see what situation plaintiff was in when defendant breached this executory contract for the planting, growing, cutting and delivering at defendant’s factory of a crop of canning peas. The peas were then beyond the canning stage and there was no market for that sort of peas. The only thing for plaintiff to do was to seek to reduce his damages by allowing the peas to mature and then harvest them. This he attempted to do, but rain and hail destroyed the entire crop and it had to be plowed under. Every one would recognize the propriety of full recovery for the crop at the contract price, had a hailstorm utterly destroyed the peas, say an hour after defendant had informed plaintiff that the peas were too ripe for canning, therefore it would not accept them, it being its fault or breach of duty that they were not earlier cut. This is not like the case of a breach of an executory contract to manufacture or prepare marketable articles or articles not liable to destruction before they can be fully prepared and disposed of for some price. This was a crop past use for canning, but not fully matured for any other purpose for which there was a market when the breach occurred, and the preparation of which for any use was subject to uncertainty and utter disappointment. The rule approved by this court is the one stated in 2 Sutherland, Dam. (4 ed.) § 648: “A party to a contract *490 which has been broken by the other party must so conduct his affairs, after he has knowledge of the breach, as to lessen the damage he may sustain as the result of it; and to the extent that loss can thus be avoided the vendee will be relieved from liability.” Baessetti v. Shenango Furnace Co. 122 Minn. 335, 142 N. W. 322. Where there is a breach of a contract of the sort here in question, it became the duty of plaintiff upon whose land the crop was growing to mitigate the damage resulting to him from defendant’s breach. However, it was not for plaintiff to show how much the damages could have been reduced. He satisfied the law when he showed that he made bona fide efforts to save or harvest the crop. This he did. The result of his work was nothing.

The situation here was akin to where a master dismisses a servant before the contract of employment ends. The servant may sue for the instalments of wages as they become due, notwithstanding he has done no work, provided he has made bona fide effort to find other like employment without success. The burden is upon defendant to show that he could have obtained other employment, and the amount that thereby the damages should be reduced. In Schommer v. Flour City Iron Works, 129 Minn. 244, 152 N. W. 535, the court said, citing cases: “It has already been determined in prior decisions that a servant discharged without cause is presumptively entitled, as damages, to an amount equaling his wages for the unexpired portion of the term; but that the employer may reduce the amount by showing that the servant obtained, or by reasonable effort on his part could have obtained, other employment.” This rule is also applied to kindred contracts. B. G. Collier, Inc. v. Kindy, 146 Minn. 279, 178 N. W. 584. This contract involved services.

When this crop was fit to can, plaintiff had earned the full contract price, less the expense of the cutting and delivering. The cutting had to be done in any event. When defendant breached its contract it became liable for the damages then resulting to plaintiff, namely 2-¿ cents a pound of shelled peas which had been produced fit for canning. The burden was upon defendant to show how much those damages should be reduced by what plaintiff thereafter by *491 proper effort could have realized out of the crop. He had a growing crop on hand, thrust upon him by defendant’s wrong. He could not dispose of it as it stood. And it is proper to regard it as defendant’s in the hands of plaintiff whose duty it was to handle it for defendant’s account. This is in line with the theory of the case of Berquist v. N. J. Olsen Co. 165 Minn. 406, 206 N. W. 931. We appreciate there was evidence adduced by defendant that seed peas brought a good price, and that another person in the vicinity had made more by letting half of his crop mature than he made from the half delivered to defendant for canning, he having stacked the peas, allowed to mature, before the hailstorm. Also that defendant was cutting and stacking peas for seed, at the time plaintiff was cutting his, without experiencing difficulty on account of weather conditions.

No issue was made by the answer that there was a failure by plaintiff to minimize the damages. The court was not requested to submit such an issue to the jury, and no objection was made at the trial to the charge.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hess v. Koskovitch
62 N.W.2d 806 (Supreme Court of Minnesota, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
208 N.W. 194, 166 Minn. 487, 1926 Minn. LEXIS 1227, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rauhauser-v-owatonna-canning-co-minn-1926.