Rapid Fireproof Door Co. v. Largo Corp.

154 N.E. 531, 243 N.Y. 482, 1926 N.Y. LEXIS 776
CourtNew York Court of Appeals
DecidedNovember 16, 1926
StatusPublished
Cited by11 cases

This text of 154 N.E. 531 (Rapid Fireproof Door Co. v. Largo Corp.) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rapid Fireproof Door Co. v. Largo Corp., 154 N.E. 531, 243 N.Y. 482, 1926 N.Y. LEXIS 776 (N.Y. 1926).

Opinion

*484 Lehman, J.

The plaintiff in this action seeks to establish and foreclose a mechanic’s lien upon real property owned by the defendant Largo Corporation, for materials which have been used by the defendant in the erection of a building. A judgment in favor of the plaintiff has been reversed by the Appellate Division and the complaint dismissed. That court has held that the plaintiff did not furnish these materials “ with the consent or at the request of the owner thereof [of the premises],” and that consequently there is no basis for a claim of statutory lien. (Lien Law [Cons. Laws, chap. 33], section 3.)

The case presents a somewhat unusual situation. On the 2d day of May, 1922, the plaintiff entered into a contract with the Norab Realty Co., Inc., to furnish and install certain materials in a theatre which the Norab Realty Co. was erecting or was about' to erect on the premises upon which the plaintiff now claims a lien. The plaintiff proceeded to furnish materials and performed labor under its contract. On the 7th day of July, 1922, it filed a notice of lien upon the real property of the Norab Realty Co. The notice of lien shows that at that time the plaintiff had not fully completed its contract. Some material called for by the contract had not yet been furnished, and some labor had not yet been performed. It appears from the testimony produced at the trial that part of the material furnished by the plaintiff under its contract had been actually installed in and attached to the building, while part was still *485 lying on the ground. In September, 1923, two actions were begun to foreclose mortgages upon the real property. This plaintiff was made a party defendant in each action, and filed its answer therein, but the answer was stricken out upon motion, and judgment of foreclosure entered. The judgment constituted an adjudication that the present plaintiff had no lien upon the real property which was not inferior to the mortgages under foreclosure. The title of the defendant Largo Corporation is derived from a sale held pursuant to the judgment of foreclosure in these actions. That title is undoubtedly free from any lien for materials previously furnished by the plaintiff with the consent or at' the request of a previous owner whose title was subject to the mortgages which have been foreclosed; but the title of the new owner may obviously be subjected to a lien thereafter, if as such owner it, in turn, by consent or request, takes part in subsequent improvement of its property.

In the present case the defendant, having purchased real property with an unfinished building, proceeded to complete the building. The materials delivered and furnished by the plaintiff upon the premises, pursuant to contract with the earlier owner, but which had not been attached to the building, were used by the defendant in this work. The plaintiff thereupon filed a new notice of lien for the alleged value of the materials so used by the defendant in the improvement of its building. The action has been brought to foreclose such hen.

Undoubtedly- the plaintiff originally furnished the materials, included in this new notice of hen; under its contract with the Norab Realty Co., Inc., for the improvement of the property, and the earlier notice of hen upon the real property of that corporation included the value of the materials for which plaintiff now seeks payment. The defendant who now owns the property had nothing to do with the original contract for the improvement of the building, and is not responsible for the value of any *486 labor performed or materials furnished pursuant thereto. The plaintiff does not claim that it has delivered any materials upon the premises since the original contract was terminated and this defendant became the owner of the property. The judgment of dismissal determines that though the defendant has used the materials furnished by the plaintiff for the improvement of the premises, they were not furnished with this defendant’s consent or at its request, and, therefore, the plaintiff has no hen on defendant’s property.

This conclusion is undoubtedly sound if the plaintiff no longer had any title to the materials at the time the defendant used them in the completion of its building. It is not claimed that the plaintiff lost title to the materials merely by bringing them upon the premises with the purpose of thereafter using them in the improvement of real property. These materials lost their character of personal property, and the plaintiff parted with his title to them, only if they became actually or constructively attached to the real property. Though the defendant purchased the real property covered by the mortgages under foreclosure, and took title free from any subordinate lien thereon, the defendant obtained no title to personal property which happened to be on the premises and which was not covered by the mortgages. Title to the materials not at that time physically attached to the real property was not changed by the sale under foreclosure unless the previous notice of hen had resulted in some manner in a constructive attachment. The first question we must consider upon this appeal is whether the filing of hen had such effect.

The statute was intended to give contractors who improved real property and thereby added to its value with the consent or at the request of the owner, an interest in the property improved. (Schaghticoke Powder Co. v. Greenwich, etc., Ry. Co., 183 N. Y. 306.) Enforcement of the statutory hen provides a method by which the *487 contractor may compel payment for benefit received. It is not an exclusive remedjq nor does a contractor, by filing a notice of lien, lose his right to recover in an action on contract. Indeed, the statute specifically provides that if the lienor shall fail, “ for any reason,” to establish a valid lien in an action under the provision of the statute he may recover judgment even in that action for such sums as are due him or which he might recover in an action on a contract. (Section 54.) It follows that the filing of a notice of lien cannot possibly constitute an election by the contractor to abandon other rights which he‘might have to recover a money judgment, but it is urged that it does constitute a binding and irrevocable election by the contractor to abandon any title he may still have in the materials furnished, and to regard them as annexed to the real property.

No relevant precedent or authority has been cited to us in support of this contention, and there is nothing in the language of the statute which shows an intent on the part of the Legislature to compel a lienor to abandon any right or title to materials he has furnished before he may avail himself of the statutory provisions enacted for his protection. Reason might perhaps be advanced why a judgment which results in the creation of an interest in the real property on the ground that a contractor has furnished materials for the improvement of the property should be given the effect of an adjudication that in fact the materials have been incorporated in such improvement. We do not deal with that situation, and do not pass upon its consequences. In that case the contractor would at least have acquired an interest in real property in exchange for his title to personal property. Here the contractor has obtained nothing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Prospecting Unlimited, Inc. v. Norberg
376 A.2d 702 (Supreme Court of Rhode Island, 1977)
Guignard Brick Works v. Gantt
159 S.E.2d 850 (Supreme Court of South Carolina, 1968)
United States v. Certified Industries, Inc.
361 F.2d 857 (Second Circuit, 1966)
De Marco v. Boghossian
37 Misc. 2d 701 (New York County Courts, 1962)
Aquilino v. United States
2 A.D.2d 747 (Appellate Division of the Supreme Court of New York, 1956)
In re the Arbitration between Heath Arms, Inc. & Kemler
207 Misc. 849 (New York Supreme Court, 1955)
Heating & Plumbing Finance Corp. v. Friedman
190 N.E. 641 (New York Court of Appeals, 1934)
Compound & Pyrono Door Co. v. Keil
235 A.D. 794 (Appellate Division of the Supreme Court of New York, 1932)
Joseph Curry Co. v. Geier Construction Co.
225 A.D. 498 (Appellate Division of the Supreme Court of New York, 1929)
Rapid Fireproof Door Co., Inc. v. Largo Corporation
155 N.E. 898 (New York Court of Appeals, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
154 N.E. 531, 243 N.Y. 482, 1926 N.Y. LEXIS 776, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rapid-fireproof-door-co-v-largo-corp-ny-1926.