Rankin Utility Co. v. Mississippi Public Service Commission

585 So. 2d 705, 127 P.U.R.4th 191, 1991 Miss. LEXIS 503, 1991 WL 159145
CourtMississippi Supreme Court
DecidedAugust 14, 1991
DocketNo. 90-CC-0744
StatusPublished
Cited by4 cases

This text of 585 So. 2d 705 (Rankin Utility Co. v. Mississippi Public Service Commission) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rankin Utility Co. v. Mississippi Public Service Commission, 585 So. 2d 705, 127 P.U.R.4th 191, 1991 Miss. LEXIS 503, 1991 WL 159145 (Mich. 1991).

Opinion

McRAE, Justice,

for the Court:

This is an appeal from a December, 1987, ruling of the Public Service Commission (hereinafter PSC or Commission), wherein the PSC unanimously overruled its 1986 decision by ordering a reduction of the water and sewer rates of Rankin Utility Company, Inc., (hereinafter Rankin Utility or Utility). Appeal was then taken to the Chancery Court of Rankin County, which affirmed the PSC’s order. Rankin Utility appeals to this Court citing seven (7) assignments of error. We affirm the decisions of the lower court and the PSC and address only the dispositive issues.

I.

A.

Rankin Utility is one of five subsidiaries of Castlewoods Land Development Corporation 1 (hereinafter Castlewoods) and provides water and sewage services to its parent corporation Castlewoods Subdivision. The Commission held that Rankin Utility had failed to enforce its own tariffs against its corporate affiliates, as required by law, and, as a result, the capital costs of the Utility and its existing customers were greatly increased. Further, Rankin Utility Company had invested capital in water distribution facilities sufficient to serve 701 customers2 and in production and storage facilities sufficient to serve some 2,400 customers. The Commission found the system installed by Rankin Utility was sized to be a future benefit to the private land developers affiliated with Rankin Utility Company, who have avoided payment of contributions to the construction, lawfully owed by them to the Utility, which would have benefitted the Utility’s ratepayers.

Larry Edwards, president of Rankin Utility Company, testified that when he and Zach Hederman, Jr., acquired Rankin Utility in September, 1983, its water system was under a quasi-moratorium on new connections by the Board of Health due to low water pressure. Although Rankin Utility upgraded an existing well and constructed an additional well, low water pressure remained a problem at Castlewoods.

[707]*707B.

In 1986, in proceedings U-4828 before the PSC, Rankin Utility asked for an increase in its water and sewer rates. As a result of the proceedings, the Public Service Commission Staff (hereinafter staff) and the Utility entered a stipulation proposing a substantial rate increase which the PSC approved effective October, 1986. To alleviate the low water pressure problem, the Utility began to explore the purchase of an overhead storage facility, but decided to put their plans on hold pending the outcome of the 1986 proceeding. Rankin Utility maintains that it purchased and installed the $360,000 overhead water tank because the Commission ordered it to do so in its 1986 order. The order read in pertinent part as follows:

The Commission finds that the Rankin Utility Company should be required to construct and place into operation the two hundred and fifty thousand (250,000) gallon water tower reflected in the Company’s filing and that the same shall be done prior to the expiration of twelve (12) months from the date of this order for the use and service of customers in the certificated area.

The staff admitted they had made an error during the 1986 proceedings because it failed to notice that Rankin Utility had neither received nor demanded any offsetting contributions from the developer. Additionally, the staff contended that in 1986 it was unaware that the Utility had failed to follow its service extension policy. Rule 12(C) of the Commission’s Service Rules requires each Utility to adopt an appropriate service extension tariff, (also known as a Service Extension Policy) which would govern the conditions upon which a Utility could extend service to newly-developed areas within its certificated area. The staff maintained that pursuant to the Utility’s own tariffs they were required to demand and receive from the developer, contributions in aid of construction. In support of the staff’s position, PSC’s Chief Accountant Leon Browning testified that the developer and Utility failed to follow the service extension policy.

The PSC’s Opinion and Order reflected that when management acquired the Utility in September, 1983, the number of customers and the capital investment and rate base was as follows:

[[Image here]]

Additional findings included the following:

By 1987 the Utility had increased its rate base by 165%, but the number of customers it served had only increased by 38%. The utility had also “bought and paid for” facilities to serve another 105 lots that were developed but unsold by the developer. The utility had created production and storage facilities that were adequate to meet the needs of over two thousand four hundred (2,400) customers. The evidence indicated that the private developer in this area intended to eventually develop between two thousand (2,000) and twenty four hundred (2,400) lots. Based upon past growth rates it is obvious that it would be many years before the area was fully developed yet the utility had, with one exception, never demanded nor received a single dime of contribution in aid of construction.

On cross-examination, Browning stated that he did not believe that the complete expense of the water tank should be included in the current rate base because its capacity exceeded that which was needed at the present time. He determined this after reviewing the rules and regulations of the Board of Health, talking to the Board of Health engineers, talking to the PSC’s engineer, and reviewing the service extension policy. His view of the service extension policy was that as the system is extended in the future, the new lot owners, or someone, should pay by way of contribution not only for the pipe in the system that [708]*708is extended, but also for part of the water system.

Edwards did not agree with Browning’s interpretation of the service extension policy. He testified:

My interpretation of that service extension policy would deal with isolated cases where the cost of providing service was uneconomically beneficial to the utility company. If perchance you had someone within our certificated area whose request for service was several miles from our existing services, that would be the time that that policy would be implemented. I do not interpret it to say that the utility company cannot, under its own management decisions, decide to increase the system utilizing its own funds for the potential profits to be made from the additional customers utilizing the system. That is our interpretation. That is what we have operated under since we acquired the system, and I think, as Mr. Browning has pointed out in his testimony, it appears to be that that was used by prior management.

He stated that there was only one situation where Rankin Utility charged contribution in aid of construction: the elementary school at Northwest Rankin Attendance Center. Rankin Utility argued that in 1986 Rankin Utility showed the Commission information which established that the utility company was absorbing extension costs and not charging contributions in aid of construction.

Public witnesses testified that after the 1986 rates took effect, it was not unusual to have $100 sewage and water bills, whereas, prior to the 1986 order, the residents of Castlewoods paid anywhere from $6.50 to $7.50 for their sewage and water.

II.

In August, 1987, the PSC opened a case styled

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mississippi Public Service Commission v. Dixie Land & Water Co.
707 So. 2d 1086 (Mississippi Supreme Court, 1998)
Sweet Home Water v. Lexington Estates, Ltd.
613 So. 2d 864 (Mississippi Supreme Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
585 So. 2d 705, 127 P.U.R.4th 191, 1991 Miss. LEXIS 503, 1991 WL 159145, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rankin-utility-co-v-mississippi-public-service-commission-miss-1991.