Rang v. Carter Lumber Dev. Co., H-06-025 (6-29-2007)

2007 Ohio 3314
CourtOhio Court of Appeals
DecidedJune 29, 2007
DocketNo. H-06-025.
StatusPublished
Cited by1 cases

This text of 2007 Ohio 3314 (Rang v. Carter Lumber Dev. Co., H-06-025 (6-29-2007)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rang v. Carter Lumber Dev. Co., H-06-025 (6-29-2007), 2007 Ohio 3314 (Ohio Ct. App. 2007).

Opinion

DECISION AND JUDGMENT ENTRY
{¶ 1} This case is before the court on appeal from the judgment of the Huron County Court of Common Pleas which, following a trial to the bench, awarded appellee, Michael A. Rang, judgment against appellant, Carter Lumber Development Company ("Carter Lumber"), in total amount of $10,415.66. For the reasons that follow, we affirm the decision of the trial court.

{¶ 2} On appeal, Carter Lumber raises the following assignments of error: *Page 2

{¶ 3} "Assignment of Error I :

{¶ 4} "The trial court erred, to the prejudice of Carter Lumber, by ruling that Mr. Rang's action was not barred by the applicable statute of limitations."

{¶ 5} "Assignment of Error II:

{¶ 6} "The trial court committed error, to the prejudice of Carter Lumber, by that [sic] including both the cost of the I-beam and the consequential damages in its judgment."

{¶ 7} On August 31, 2000, appellee purchased $6,185.97 worth of building materials from Carter Lumber in Norwalk, Ohio. As was customary between the parties, the materials were to remain in Carter Lumber's possession until demanded by appellee. Appellee demanded a portion of his purchase in October 2003, but was informed that Carter Lumber would not deliver the materials, or otherwise allow appellee to take possession of them, without further investigation. Because Carter Lumber would not deliver his materials at that time, appellee purchased replaced materials for the portion of material that he had demanded, which, due to an increase in material price, cost appellee $998.27 more than it had in 2000. Eventually, in October 2005, appellee repurchased the balance of materials not delivered by Carter Lumber. Again, due to an increase in material costs, appellee expended an additional $3231.42 to replace the material originally purchased from Carter Lumber in 2000. Appellee sued Carter Lumber on August 26, 2005, to recover his losses due to Carter Lumber's breach of contract and conversion of appellee's building materials. Cross motions for summary judgment, *Page 3 including Carter Lumber's statute of limitations claim, were all denied by the court. On June 2, 2006, the matter came before the court for a trial to the bench. The following relevant evidence was adduced.

{¶ 8} At trial, appellee testified that, on May 2, 1999, he bought $2,122.92 of building materials, including oriented strand board ("OSB"), from the Carter Lumber Store in Norwalk, Ohio. These materials were to be used in the construction of appellee's private residence. According to appellee, Carter Lumber never delivered the materials and never demanded appellee take possession of them. Appellee further testified that Carter Lumber was aware that these materials were not going to be needed for at least a year and a half, and that there was an understanding that Carter Lumber would maintain possession of the materials until they were needed.

{¶ 9} In August 2000, the cost of materials had dropped since appellee's May 1999 purchase. Because appellee had not yet taken possession of his building materials, Jeff Cheney, an outside salesman for Carter Lumber at that time, suggested that appellee return the items purchased in May 1999 and repurchase them along with additional materials. Appellee testified that, on August 31, 2000, he purchased $6,185.97 of materials from Carter Lumber and, on September 8, 2000, was refunded the $2,122.92 he spent in 1999. The materials purchased on August 31, 2000 included 3 different sizes of OSB, as well as 2,300 lineal feet of "I-joist." Appellee testified that it was understood by appellee and the manager of Carter Lumber at that time, Ken Hardin, that Carter Lumber was to maintain possession of the OSB until such time as appellee needed it. *Page 4

{¶ 10} Appellee testified that he ran into problems in the construction of his home and Carter Lumber maintained possession of the OSB. Appellee also testified that upon notice of a change in management at Carter Lumber, appellee would inform the new manager of the situation. At trial, appellee presented the original customer copy of his August 31, 2000 receipt with a notation that states: "Mat. Pd. For in 2000. Still owed Material. JSII." According to appellee, on February 4, 2003, the person who represented himself to be the manager at that time, John Swain II, made the notation on the original customer copy. Appellee's witness, Mark White, a former Carter Lumber employee, testified that he recognized "JSII" as the initials of John Swain II.

{¶ 11} In October 2003, appellee demanded delivery of a portion of the items paid for on August 31, 2000. Appellee testified that Carter Lumber's manager at that time, Gino Meehan, stated that he was not aware of the situation and would not honor appellee's demands without some investigation. Needing a portion of the material, appellee purchased 90 sheets of 7/16 inch OSB from Carter Lumber on October 7, 2003, to replace a portion of the materials that had been paid for on August 31, 2000, but never delivered. In so doing, appellee incurred an additional cost of $998.27 due to an increase in material price. Appellee testified that a notation was made on the October 7, 2003 receipt which stated: "credit if verification of invoice dated 2000."

{¶ 12} Appellee testified that on October 28, 2005, he purchased from another retail store the balance of the materials that he had purchased at Carter Lumber on August *Page 5 31, 2000. Appellee incurred an additional cost for materials of $3,034.20 due to an increase in material price and $197.22 in sales tax.

{¶ 13} Appellee further testified on cross-examination that it was not until 2003 that he sent a letter of any kind informing Carter Lumber of an agreement for Carter Lumber to maintain possession of the materials until needed. Appellee also stated that, even though he received regular credit card statements from Carter Lumber, which made no reference to the non-delivered goods and did not credit him for the materials that had been purchased but not yet received, he never contested them.

{¶ 14} Appellee also testified that, sometime in 2003, he knew "Carter Lumber was not going to acquiesce to the demands," but made no attempt to purchase the remainder of the materials, nor collect estimates, at that time. Upon questioning from the court, appellee testified that he did not gather prices closer to October 7, 2003 because he was unaware, at that time, that he was not going to get the materials he purchased from Carter Lumber.

{¶ 15} Also, during cross-examination of appellee, he testified that he had no written documentation of the price that he paid for the materials purchased on October 28, 2005. The only documentation that he produced was a hand-written note of a telephone conversation between appellee and the Oberlin Carter Lumber store regarding Carter Lumber's prices on that day. This hand-written note was not admitted into evidence, but appellee was permitted to testify from it. Appellee testified that the reason *Page 6 he did not have documentation from October 28, 2005 was because he purchased different quantities and different items from another retail store.

{¶ 16}

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rang v. Carter Lumber Dev. Co., H-07-032 (6-13-2008)
2008 Ohio 2876 (Ohio Court of Appeals, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
2007 Ohio 3314, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rang-v-carter-lumber-dev-co-h-06-025-6-29-2007-ohioctapp-2007.