Ramos v. Florida Power & Light Co.

21 So. 3d 91, 2009 Fla. App. LEXIS 15801, 2009 WL 3364872
CourtDistrict Court of Appeal of Florida
DecidedOctober 21, 2009
Docket3D08-1694
StatusPublished
Cited by2 cases

This text of 21 So. 3d 91 (Ramos v. Florida Power & Light Co.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ramos v. Florida Power & Light Co., 21 So. 3d 91, 2009 Fla. App. LEXIS 15801, 2009 WL 3364872 (Fla. Ct. App. 2009).

Opinion

SALTER, J.

Leonardo Ramos appeals a final summary judgment in favor of Florida Power & Light (FPL) regarding his second *92 amended complaint for gross negligence. Ramos alleged that FPL was grossly negligent when it terminated electrical service to his farm and family residence, and that the wrongful power cutoff resulted in substantial losses to his ornamental plant crops and livestock. FPL maintained that it had already prevailed on a critical element of Ramos’ claim — the question of whether Ramos engaged in meter tampering and electric current diversion — in a prior administrative proceeding before the Florida Public Service Commission (PSC), with the result that Ramos was precluded as a matter of law from establishing his claim in the later circuit court case. The circuit court agreed with that analysis and entered the final summary judgment in favor of FPL.

We reverse, finding that the PSC’s limited authority to conduct administrative fact-finding regarding billing disputes and rates for electric power does not preclude a trial court’s adjudication of a gross negligence claim for compensatory damages based on the totality of FPL’s conduct regarding its customer. In particular, the PSC’s administrative determination that FPL’s written report provided “sufficient evidence of an unauthorized meter and meter tampering at Mr. Ramos’ address” — a conclusion based on nothing but hearsay presented to the PSC, and vigorously disputed by Ramos (then a self-represented party with no legal training)— does not bar the adjudication of that question in a later court proceeding.

The Farm and the Meters

During the period 1989-97, Ramos used electrical power supplied by FPL to operate his family farm. FPL alleges, but Ramos has denied, that from 1993 to 1997, FPL removed six different unauthorized meters from Ramos’ farm. When a billing and meter-related dispute arose in 1997, FPL could not produce (a) those allegedly-unauthorized meters or (b) any prior written notices to Ramos that his meters were unauthorized or had been tampered with.

In April 1997, an FPL meter reader discovered what he believed to be an unauthorized meter number at Ramos’ property. He also noted that the outer seal on the meter was missing, but he did not determine whether the inner seal was missing. FPL’s “revenue protection department” investigated the matter and concluded that the meter had been switched several times over the last five years.

A meter specialist then visited the property in May 2007 to remove the recently-discovered and allegedly-unauthorized meter for further testing. During this visit, however, yet another meter number was found at the property, and this one was reportedly missing the outer and inner seals. This meter was tested at FPL’s meter test center and was allegedly a “foreign” meter with evidence of meter tampering. FPL then reviewed Ramos’ billing history and allegedly found significantly less usage during the period of the allegedly-unauthorized meters. Thereafter, and applying the methodology specified in its official tariff, FPL billed Ramos approximately $17,800 for allegedly-unauthorized use of electricity over the preceding five and one-half years.

Ramos received a back bill for this amount in July 1997. FPL and Ramos made various offers and counter-offers on settling the alleged backcharges but were unable to reach agreement. In November 1997, FPL disconnected electrical service to Ramos’ property. The following month, Ramos filed a complaint with the PSC alleging unfair baekbilling for meter tampering and disputing FPL’s allegations that Ramos had used an unauthorized meter.

*93 Although the PSC received FPL’s written report regarding those issues, it did not conduct an evidentiary hearing. The PSC determined, however, that “because of the particular circumstances of this case, we believe that the fair and reasonable amount of backbilling is $1,386.82.” The PSC’s order also stated “FPL has indicated that it agrees with this amount.”

The order detailed FPL’s difficulties in substantiating its allegations of multiple unauthorized meters and tampering:

Between September 13, 1993 and January 9, 1997 six different meters have been identified at this address. At no time during this period did FPL initiate a current diversion investigation. When Commission staff asked FPL to explain why it had not acted when each of the six different meters were discovered, it responded that the company was going through a period of reorganization and the policy in place at the time called for the meter reader to input whatever meter was found at an address as the new meter of record if there were no obvious signs of meter tampering. The Company further stated that after 1995 their procedures were modified to minimize this type of problem. Even though FPL indicated that their procedures changed after 1995, the same problem occurred on January 9, 1997, when the sixth foreign meter was found and FPL again entered it as a new meter set and meter of record. We believe FPL failed to provide adequate proof of meter tampering prior to January 9, 1997. FPL had ample opportunity to notice any alleged meter tampering when six new meters were recorded on the customer’s account in a four year time period. We find it problematic that so many unauthorized meter changes did not trigger an investigation on FPL’s part. However, FPL did not test, nor was it able to locate, any of the six meters in question. 1

In 2000, Ramos commenced a circuit court lawsuit against FPL alleging that the termination of power to his home and farm was grossly negligent, and that he suffered a foreclosure of the property, loss of crops, and other compensatory damages as a result. After pretrial discovery and two amendments to the complaint, FPL’s motion for final summary judgment was heard and granted.

The PSC, the Rules, and the Tariff

Section 366.04, Florida Statutes (1997), grants to the PSC jurisdiction “to regulate and supervise each public utility with respect to its rates and service....” Section 366.05(1) grants to the PSC “power to prescribe fair and reasonable rates and charges, classifications, standards of quality and measurements, and service rules and regulations to be observed by each public utility,” and further authorizes the PSC to promulgate rules to implement and enforce these powers. The PSC has promulgated such rules, including a set of rules in Part VI of Chapter 25-6, Florida Administrative Code, “Customer Relations,” that are pertinent to the billing dispute between Ramos and FPL. In addition, FPL and other public utilities promulgate a set of rates, rules, and regulations collectively referred to as a “tariff,” subject to review and approval by the PSC. The FPL Tariff contains several provisions addressing “unauthorized re-metering,” meter tampering, billing disputes, and discontinuance of service.

Exclusive PSC Jurisdiction and the “Nature of the Relief Sought”

Citing Storey v. Mayo, 217 So.2d 304 (Fla.1968), and Richter v. Florida Power Corp., 366 So.2d 798 (Fla. 2d DCA 1979), *94

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Florida Power & Light Company v. Heydi Velez
District Court of Appeal of Florida, 2024

Cite This Page — Counsel Stack

Bluebook (online)
21 So. 3d 91, 2009 Fla. App. LEXIS 15801, 2009 WL 3364872, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ramos-v-florida-power-light-co-fladistctapp-2009.