Ramon Pacheco & Assoc. v. Betancourt Castellon Assoc.

820 So. 2d 948, 2002 Fla. App. LEXIS 5723, 2002 WL 813494
CourtDistrict Court of Appeal of Florida
DecidedMay 1, 2002
Docket3D01-3361
StatusPublished

This text of 820 So. 2d 948 (Ramon Pacheco & Assoc. v. Betancourt Castellon Assoc.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ramon Pacheco & Assoc. v. Betancourt Castellon Assoc., 820 So. 2d 948, 2002 Fla. App. LEXIS 5723, 2002 WL 813494 (Fla. Ct. App. 2002).

Opinion

820 So.2d 948 (2002)

RAMON PACHECO & ASSOC., INC., Appellant,
v.
BETANCOURT CASTELLON ASSOC., INC., Appellee.

No. 3D01-3361.

District Court of Appeal of Florida, Third District.

May 1, 2002.
Rehearing and Rehearing Denied July 19, 2002.

*949 Carlton Fields and Patricia H. Thompson, Miami, and Joseph H. Lang, Jr., St. Petersburg, and Carlos A. Zumpano, Miami, for appellant.

Stearns Weaver Miller Weissler Alhadeff & Sitterson, Fort Lauderdale, and David C. Pollack and Joy Spillis Lundeen, Miami, and Anastasia I. Kokotis, Orlando, for appellee.

Before LEVY, SHEVIN, and SORONDO, JJ.

Rehearing and Rehearing En Banc Denied July 19, 2002.

LEVY, Judge.

Appellant, Ramon Pacheco & Associates, Inc., ("Pacheco"), third-party defendant below, appeals from an Order denying its Motion for Stay and to Compel Arbitration contending that Appellee's, M & M Aerospace Hardware, Inc. ("M & M"), third-party claim for Indemnification is subject to the Mediation/Arbitration clauses in the parties' Agreement for architectural work.

Pacheco and M & M entered into an agreement for architectural work on the construction of a project. The agreement, in pertinent parts, provides:

MEDIATION.... Any claim, dispute or other matter in question arising out of or related to this Agreement shall be subject to mediation as a condition precedent to arbitration or the institution of legal or equitable proceedings by either party;
ARBITRATION.... Any claim, dispute or other matter in question arising out of or related to this Agreement shall be subject to arbitration.

After completion of the architectural plans and specifications, M & M sought bids and subsequently entered into a separate contract with Betancourt Castellon Associates, Inc. ("BCA") for construction of the project. BCA, thereafter, brought suit against M & M alleging Breach of Contract, Breach of Implied Warranty of Fitness of Plans and Specifications, Foreclosure of Construction Lien, and Equitable Lien Foreclosure. With respect to the Breach of Contract claim, BCA specifically alleged that substantial changes were made to the contract plans and specifications initially provided to it which significantly increased the scope and duration of BCA's work. BCA also alleged that conflicts and deficiencies in the plans and specifications impacted the scope of duration of the work causing delays, loss of productivity, and overtime cost and expenses. *950 With respect to the Breach of Implied Warranty of Fitness of Plans and Specifications claim, BCA alleges, in part, that the "plans, specifications and related construction documents were inadequate incomplete and deficient."

As a result of BCA's Complaint against M & M, M & M filed a Third-Party Claim for Indemnification against Pacheco claiming that Pacheco was liable for any liability against M & M. In response, Pacheco filed a Motion to Stay Proceedings and for Arbitration claiming that the architectural contract executed between M & M and Pacheco requires arbitration. After a hearing on the matter, the trial court denied Pacheco's motion. We reverse.

The trial court relied on Seifert v. U.S. Home Corp., 750 So.2d 633 (Fla.1999) to deny Pacheco's Motion to Stay and for Arbitration. We find that Seifert is factually distinguishable from the instant case by virtue of the fact that in Seifert the builder was attempting to compel arbitration of a wrongful death claim brought by the homeowner. In the instant case, on the other hand, Pacheco seeks to compel arbitration of a third-party indemnification claim that arises out of allegations that the architectural design and specifications are faulty—the very heart of the architectural agreement.

Seifert involved a wrongful death action by the wife of the deceased homeowner who died when the family car was left running in the garage and the air conditioning system of the house picked up and circulated the carbon monoxide emissions from the car. The Seiferts' home was built by U.S. Home pursuant to a contract for construction. Mrs. Seifert filed claims against U.S. Home for strict liability, negligence, and breach of express and implied warranties. After pre-trial motions, only the negligence claim remained which U.S. Home sought to submit to arbitration pursuant to an arbitration clause in the construction contract which provided that:

[a]ny controversy or claim arising under or related to this Agreement or to the Property ... or with respect to any claim arising by virtue of any representations alleged to have been made by the Seller or Seller's representative, shall be settled and finally determined by mediation or binding arbitration as provided by the Federal Arbitration Act ... and similar state statutes and not by a court of law.

Seifert, 750 So.2d at 635.

The Supreme Court of Florida in Seifert refused to compel arbitration on the wrongful death issue, finding that the claim did not arise out of the contract. Relying on a federal Fourth Circuit case, the Court explained that the "test for determining arbitrability of a particular claim under a broad arbitration provision is whether a `significant relationship' exists between the claim and the agreement containing the arbitration clause, regardless of the legal label attached to the dispute." Seifert, 750 So.2d at 637-38 (citing American Recovery Corp. v. Computerized Thermal Imaging, Inc., 96 F.3d 88, 93 (4th Cir.1996)). After reviewing the arbitration clause and the Complaint before it, the Seifert Court found that there was no contractual nexus between the arbitration clause and the wrongful death claim. The Court explained that the contract was a standard commercial contract containing provisions relating to the duties and obligations of the parties with respect to the construction and sale of the house. The Court read nothing in the contract from which to infer that the parties intended to include tort claims within the scope of the arbitration agreement. Further, the Court found that the Complaint did not assert that U.S. Home's duties or obligations arose from or were governed by *951 the contract. In fact, the Court explained, the obligations raised by the allegations in the Complaint would extend to anyone, "third parties as well as the Seiferts, who might be injured by U.S. Home's tortious conduct." Seifert, 750 So.2d at 641. Consequently, the Court concluded that the wrongful death claim related to duties independent from the agreement and was therefore not subject to the arbitration.

In the case at bar, Pacheco and M & M entered into an agreement for architectural work which includes an arbitration clause providing that "[a]ny claim, dispute or other matter in question arising out of or related to this Agreement shall be subject to arbitration." M & M was subsequently sued by BCA for defective and/or insufficient plans and specifications allegedly provided by Pacheco.

As a result of BCA's Complaint against M & M, M & M filed a Third Party Claim for Indemnification against Pacheco claiming that Pacheco was liable for any liability against M & M. The Third Party Complaint specifically alleges:

5.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BRICKELL BISCAYNE v. Morse/Diesel, Inc.
683 So. 2d 168 (District Court of Appeal of Florida, 1996)
Post Tensioned Engineering Corp. v. Fairways Plaza Associates
429 So. 2d 1212 (District Court of Appeal of Florida, 1983)
Brickell Biscayne Corp. v. WPL ASSOCIATES
671 So. 2d 247 (District Court of Appeal of Florida, 1996)
Anderson-Parrish v. St. Petersburg Beach
468 So. 2d 507 (District Court of Appeal of Florida, 1985)
Seaboard Coast Line RR Co. v. Smith
359 So. 2d 427 (Supreme Court of Florida, 1978)
Seifert v. US Home Corp.
750 So. 2d 633 (Supreme Court of Florida, 1999)
Holiday v. State
820 So. 2d 948 (District Court of Appeal of Florida, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
820 So. 2d 948, 2002 Fla. App. LEXIS 5723, 2002 WL 813494, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ramon-pacheco-assoc-v-betancourt-castellon-assoc-fladistctapp-2002.