Ralston Dry-Wall Co. v. United States Gypsum Co.

740 F. Supp. 926, 15 U.C.C. Rep. Serv. 2d (West) 67, 1990 U.S. Dist. LEXIS 8157, 1990 WL 91807
CourtDistrict Court, D. Rhode Island
DecidedJune 29, 1990
DocketCiv. A. 89-0156 L
StatusPublished
Cited by6 cases

This text of 740 F. Supp. 926 (Ralston Dry-Wall Co. v. United States Gypsum Co.) is published on Counsel Stack Legal Research, covering District Court, D. Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ralston Dry-Wall Co. v. United States Gypsum Co., 740 F. Supp. 926, 15 U.C.C. Rep. Serv. 2d (West) 67, 1990 U.S. Dist. LEXIS 8157, 1990 WL 91807 (D.R.I. 1990).

Opinion

*927 MEMORANDUM AND ORDER

LAGUEUX, District Judge.

This matter is presently before the Court on the motion of both defendants for summary judgment pursuant to Rule 56 of the Federal Rules of Civil Procedure.

The instant action arises as a result of a discussion between representatives of plaintiff, Ralston Drywall Company, Inc. (Ralston), and defendant, United States Gypsum Company (USG), regarding the purchase of certain materials manufactured and sold by USG for use by Ralston in the performance of its work as a subcontractor on a construction project known as the Bryant Center. Prior to the submission of Ralston’s bid on the project, an estimator employed by the company met with one or more employees of USG to determine 1) whether certain products manufactured by USG could be used by Ralston in its work on the Bryant Center and 2) if so, to ascertain an estimate of the cost of such materials. Plaintiff alleges that during this meeting USG recommended that Ralston bid the project based on a particular system of light gauge metal framing known as a “fly-by” system. Plaintiff further alleges that USG assured Ralston that this system would comply with project drawings and specifications. As a result of this discussion with USG, Ralston submitted its bid assuming that it could use the “fly-by” system and subsequently entered into a binding contract to perform certain work on the Bryant Center project. Ultimately, Ralston’s design was rejected by the architect for the project because the “fly-by” system did not comply with the contract specifications. Ralston was then required to submit a second design proposal and perform additional work at the contract price.

In the case now before this Court, plaintiff asserts four theories for the recovery of damages against defendants. In Count I of the complaint, plaintiff alleges that USG breached an express warranty that the “fly-by” system would comply with project drawings and specifications. In Count II, plaintiff alleges breach of an implied warranty of fitness for a particular purpose. In Count III, plaintiff asserts that USG made false and fraudulent misrepresentations that the “fly-by” system would comply with project specifications. Finally, in Count IV, plaintiff alleges that Robert J. Clark, while acting within the scope of his duties as a technical sales representative for USG, was negligent in recommending the “fly-by” system to Ralston for use in its bid on the Bryant Center project.

Plaintiff’s claims contained in Counts I, II and III of the complaint are asserted only against USG. The claims contained in Count IV are asserted against both defendants, USG and Clark.

The Court, after having heard arguments on the motion of both defendants for summary judgment on all counts, took the matter under advisement. The motion is now in order for decision.

BACKGROUND

The background in this case is as follows. On August 14,1985, Ralston entered into a subcontract with H.V. Collins Company to perform certain work on the Bryant Center project located at Bryant College in North Smithfield, Rhode Island. The work to be performed by Ralston included the erection of a light gauge steel curtain wall and the subcontract required that Ralston perform all work in accordance with the plans and specifications prepared by the firm of Architectural Resources Cambridge, Inc. (ARC).

Prior to the submission of Ralston’s bid on the project, J. Howard Johnson, an estimator employed by Ralston, met with one or more representatives of USG to discuss the purchase of certain products manufactured and sold by USG and to obtain an estimate of the cost of such products to assist Ralston in placing a dollar value on its bid. Richard Tierney, a technical sales representative for USG, attended this meeting on behalf of USG. Robert J. Clark, a structural engineer and also a technical sales representative for USG, was also *928 present. 1

According to the deposition testimony of Johnson, it was during this meeting that Tierney assured him that USG’s “fly-by” system of light gauge metal framing would comply with the plans and specifications for the Bryant Center project and recommended that Ralston submit its bid based on the use of this system. The “fly-by” system is characterized by the fact that it distributes wind and gravity loads to the perimeter spandrel beams rather than to the columns and requires that the studs be connected to these perimeter beams. In a “truss” system, on the other hand, the wind and gravity loads are supported by columns. The plans and specifications for the Bryant Center project were somewhat ambiguous in that they depicted a “fly-by” system in certain areas but the phrase “truss system” also appeared in the specifications. Johnson stated at his deposition that although he was familiar with the “fly-by” system, he had never heard of a “truss” system until he came across the phrase while reviewing the specifications for this particular project.

Prior to the time of the meeting between Johnson and Tierney, Clark had met with Robert Quigley, an architect employed by ARC, to discuss the load bearing requirements for the Bryant Center. At that time, Quigley informed Clark that the perimeter beams of the building in which the light gauge steel curtain wall was to be incorporated were not designed to be load bearing and that the columns were to bear the load of the framing system and the exterior veneer. Clark testified at his deposition that he had not come away from the meeting with Quigley knowing exactly how ARC wanted to build the project. He also stated, however, that although he does not recall whether he specifically mentioned that he had met with the architect on this project, he did notify both Tierney and Johnson that the intention of the plan for the Bryant Center was for the panels to be connected to the columns. Both Tierney and Johnson deny having had any knowledge that the plans and specifications intended that the wall panels be connected to the columns. This dispute of fact, however, is not material to the outcome of the instant case.

Following his meeting with Tierney, Johnson telephoned in a bid to H.V. Collins. According to Johnson’s deposition testimony, Ralston’s bid was qualified in that it was based 6n Ralston using USG’s “fly-by” system. Johnson also testified that he would generally qualify a bid if there was “a question in his mind” or to make “sure that there was no misunderstanding.”

After receiving a letter of intent indicating that its bid was accepted, Ralston entered into a written contract with H.V. Collins for that part of the work for. which Ralston had submitted a bid. This written contract did not include the qualification that the bid price (now contract price) concerning the erection of the light gauge steel curtain wall was based on the use of the “fly-by” system. Subsequent to the signing of the contract, Ralston submitted to H.V. Collins the technical information package that it had received from USG. H.V. Collins then submitted these materials to the architect for the Bryant Center project, ARC.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
740 F. Supp. 926, 15 U.C.C. Rep. Serv. 2d (West) 67, 1990 U.S. Dist. LEXIS 8157, 1990 WL 91807, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ralston-dry-wall-co-v-united-states-gypsum-co-rid-1990.