Ralph Rogers & Co. v. Allied Construction Co.

326 S.W.2d 428, 205 Tenn. 197, 9 McCanless 197, 1959 Tenn. LEXIS 354
CourtTennessee Supreme Court
DecidedJune 5, 1959
StatusPublished
Cited by2 cases

This text of 326 S.W.2d 428 (Ralph Rogers & Co. v. Allied Construction Co.) is published on Counsel Stack Legal Research, covering Tennessee Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ralph Rogers & Co. v. Allied Construction Co., 326 S.W.2d 428, 205 Tenn. 197, 9 McCanless 197, 1959 Tenn. LEXIS 354 (Tenn. 1959).

Opinion

Me. Justice Bueuett

delivered the opinion of the Court.

The original bill was filed by Ralph Rogers & Company, Inc., on a sworn statement of account coming from Davidson County, Tennessee, against Allied Construction Company. The Allied Construction Company answered this bill denying that it owed the complainant any amount, and also, coupled with this answer, filed a cross bill against the Tennessee Asphalt Company, in which it asked for a judgment against them for some $200,000 which it alleged the Tennessee Asphalt Company owed them for defective paving done under a contract dated April 8, 1955. It alleged in this answer and cross bill that any claim that the Ralph Rogers & Company, Inc., had against them on the account on which they were sued grew out of the defective work that Ralph Rogers & Company, Inc., did as a sub-contractor for the Tennessee Asphalt Company in doing the work under the contract [201]*201which. Allied Construction Company had with the Tennessee Asphalt Company nnder its contract of April 8, 1955. This bill sought no recovery against the original complainant, Ralph Rogers & Company, Inc., but prayed that for any recovery allowed this original complainant the cross complainant be awarded a judgment over against the Tennessee Asphalt Company.

The Tennessee Asphalt Company filed its answer to this cross bill of the Allied Construction Company denying that the work done under the contract of April 8,1955, with Allied Construction Company was defectively done, but asserting that, if so, it was done by the original complainant Ralph Rogers & Company, Inc., as it, Tennessee Asphalt Company’s subcontractor. It prayed that its answer be treated as a cross bill against the original complainant, Ralph Rogers & Company, Inc., and asked that should the work done be found defective that for any decree granted in favor of Allied Construction Company, that it be granted a decree over and against the original complainant, Ralph Rogers & Company, Inc.

The original complainant, Ralph Rogers & Company, Inc., thereupon moved the court either to dismiss the cross bill filed against it or to grant a severance because the cross bill brought “in a third party defendant based upon a contract which was not the basis on which the suit was originally brought by the original complainant.”

The Chancellor granted the severance and also granted Allied Construction Company a discretionary appeal to his so ordering a severance. Briefs have been filed and after considerable study and investigation on the matter we now have it for determination.

[202]*202The assignments, and argument, of Allied Construction Company is that the amount for which they were sued on the sworn account in the original hill of some $10,000 grew out of work that the original complainant Ralph Rogers & Company, Inc., did under a contract of April 8, 1955 that it had with the Tennessee Asphalt Company to do certain work at Oak Ridge and that this work was done defectively. It denies that it, Allied Construction Company, owes Ralph Rogers & Company, Inc., anything by reason of this defective work which Ralph Rogers & Company, Inc., did for the principal contractor, Tennessee Asphalt Company, who had the contract with Allied Construction Company. Thus it is said, and forcefully argued, that since this work was defectively done by the sub-contractor of its principal contractor, Tennessee Asphalt Company, that it does not owe this sworn account. In the answer of Allied Construction Company to the original bill of Ralph Rogers & Company, Inc., it seeks by way of the answer and cross bill to bring in the Tennessee Asphalt Company and asks for judgment over and against the Tennessee Asphalt Company for defective work under this contract of some $200,000.

The answer of the Tennessee Asphalt Company to the cross bill of Allied Construction Company denies that any work that it did for Allied Construction Company was done defectively but says that if it was done defectively Ralph Rogers & Company, Inc., its sub-contractor, did this defective work and thus it is asked that Ralph Rogers & Company, Inc., the original complainant in the original bill be made a party defendant and that any judgment allowed Allied Construction Company for defective work, if any, be taken against Ralph Rogers & [203]*203Company, Inc., Tennessee Asphalt Company’s subcontractor.

Tbns it is seen by the original bill and answer and cross bill bringing in the Tennessee Asphalt Company and the answer and cross bill to the Tennessee Asphalt Company’s cross bill brings all parties before the Court where the Court can reach a just and final conclusion as to all matters. It is shown by these pleadings that the sworn account upon which the original bill was based necessarily grew out of work that it had done as a sub-contractor for Tennessee Asphalt Company and that Tennessee Asphalt Company was the general contractor with Allied Construction Company. Under this state of the pleadings it seems to us that in order to do justice that all parties must necessarily be involved in the proof herein of all three bills, answers and cross bills.

The argument of Ealph Eogers & Company, Inc., in support of the Chancellor’s allowing the severence is based on various propositions. The first being that the allowance of a severance is a discretionary matter with the trial court or the Chancellor who tries this case below. The basic case for such a rule is Tyson v. Netherton, 53 Tenn. 19. In this case the Court lays down this unquestioned rule that the allowance of a severance is a discretionary matter. The facts upon which this rule is laid down is in a law case where one defendant sought to have a severance between himself and another defendant so that he might use the other defendant as a witness on his behalf in his trial. This general proposition that the granting of a severance is a discretionary matter has been followed in other cases and is unquestionably a sound rule when the record shows that the action of the [204]*204trial court lias been based on bis discretion under a given state of facts. We tbink tbougb that we are not violating the rule of stare decisis on this question of discretionary severance because it appears to us that probably the reason the Chancellor granted this severance was more on the idea that he thought that under our Statute, Section 21-620, T.C.A., and certain authorities, that where a third party defendant, who was not a party to the original action, was brought into court based on a contract which was not shown to be the basis for the original suit that then he had no jurisdiction to require the parties to all proceed in the same action.

We think that under the allegations herein, that is, the original bill and the answers and cross bills herein, that it is necessary that all of these actions be tried together and not be severed. If they were and are severed the original complainant is not going to escape any taking of proof or things of that kind in the end because this original complainant in the end must defend the cross bill of Tennessee Asphalt Company — all actions are so combined when looking at it from a broad standpoint that equity and justice demands that they be tried together.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Haynie v. Milan Exchange. Inc.
458 S.W.2d 23 (Court of Appeals of Tennessee, 1970)
Johnson v. Aero Mayflower Transit Co.
425 S.W.2d 757 (Tennessee Supreme Court, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
326 S.W.2d 428, 205 Tenn. 197, 9 McCanless 197, 1959 Tenn. LEXIS 354, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ralph-rogers-co-v-allied-construction-co-tenn-1959.