Raleigh County Construction Co. v. Amere Gas Utilities Co.

169 S.E. 785, 113 W. Va. 854, 1933 W. Va. LEXIS 261
CourtWest Virginia Supreme Court
DecidedJune 10, 1933
Docket7571
StatusPublished
Cited by1 cases

This text of 169 S.E. 785 (Raleigh County Construction Co. v. Amere Gas Utilities Co.) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Raleigh County Construction Co. v. Amere Gas Utilities Co., 169 S.E. 785, 113 W. Va. 854, 1933 W. Va. LEXIS 261 (W. Va. 1933).

Opinion

KenNA, Judge:

Tbe Raleigb County Construction Company brought suit in tbe circuit court of Raleigb County against Amere Gas Utilities Company for a balance claimed to be due under a contract by which! tbe defendant engaged the plaintiff to dig certain ditches, estimated at eighteen miles, preparatory to tbe installation of a gas distributing system in tbe City of Beckley. Tbe form of tbe suit was for tbe enforcement of a labor liep filed against the defendant company, and tbe controversy resolves itself into tbe question of what charges tbe plaintiff is entitled to make under its contract. The cause was successively referred to two commissioners in chancery and was beard on two commissioners’ reports. Exceptions were taken to the reports by both tbe plaintiff and tbe defendant. It is upon tbe rulings of tbe court upon these respective exceptions that tbe appeal and cross-error assignments by the appellee are based.

An account filed with tbe plaintiff’s bill covers all the charges, including tbe amounts of estimates that were paid from time to time as tbe work progressed, made for the entire performance of tbe contract. It will probably facilitate and clarify a discussion of the items of tbe controversy to set this account up and to deal with the several items embraced in it seriatim, instead of attempting a comprehensive general discussion of tbe entire matter of controversy. The account is as follows:

“Beckley, West Virginia, April 17, 1930.
Amere Gas Utilities Company,
To Raleigb County Construction Co. Dr.
1. 147,790 lineal feet of ditch dug and back filled (exclusive of work hereinafter *856 shown) at contract price oí 14c per lineal foot .$ 20,830.60
2. 10,650.8 lineal feet of bituminous macadam, concrete and brick cut and replaced at contract price of 39c per lineal foot ...$ 4,153.81
3. 10,650.8 lineal feet of ditch dug under same at contract price of 14c per lineal foot . 1,491.11
4. Total amount of extra bituminous macadam, brick and concrete cut and replaced because of extra width of ditch at various places beyond the standard width fixed by contract price of 39e per lineal foot, figured and based upon the same ratio of yardage to price of 39e per lineal foot for standard width, being equal to 1183 lineal feet of standard width @ contract price of 39c per lineal foot. 463.32
5. Total amount of extra ditching dug and back-filled because of extra width or depth of ditch at various places beyond the standard width or depth fixed by contract price of 39c per lineal foot, figured and based upon the same ratio of yardage to price of 14c per lineal foot per standard width and depth, being equal to 9794 lineal feet of standard width and depth at contract of 14c per lineal foot (including 1183 feet under pavement mentioned in last item.) . 1,371.16
6. 4360 lineal feet of slate macadam cut, and not replaced at 35c per lineal foot.... 1,526.00
7. Force account rendered for labor performed in addition to the labor hereinbe-fore described under contract with said Amere Gas Utilities Company for digging ditches thru stony ground and other ditching for which the standard prices fixed as above did. not apply; for employees used in laying out ditches and sundry other labor as shown on sheet hereto attached marked ‘Force account rendered ’ . 2,449.78
8. Additional labor performed in addition to labor hereinbefore shown by shaping bottoms and sides of ditches not required to be done under standard specifications *857 for ditching @ 14c per lineal foot; which labor was performed at the request of Amere Gas Utilities Company; which labor is shown on sheet hereto attached marked ‘Additional Force Account’. 2,743.34
9. Bonus amount allowed under contract for performing contract before November 1, of digging 18 miles of ditch @ $200.00 per day, the work being performed on October 21; 10 days at $200.00 per day; which amount was to be paid by Amere Gas Utilities Company for this labor in addition to unit price set for ditching....$ 2,000.00
Total .$37,029.12
Cash paid on account . 21,361.98
Balance due ,.$15,667.34.”

Item 1. The commissioner in chancery allowed this item subject to a deduction of $610.40, representing 4,360 lineal feet of ditching under slate macadam cut and not replaced, at fourteen cents per lineal foot. The trial court confirmed the commissioner’s report in this respect, and the appellee assigns the ruling of the trial court as cross-error, it having excepted to the commissioner’s report in that respect. The contract provided a charge of thirty-nine cents for cutting paving, digging the ditch thereunder and replacing the pavement. The lineal foot deduction from this item represents that number of lineal feet which had been included in a separate charge under Item 6. The defendant’s theory is that the charge of thirty-nine cents includes both the breaking and the replacing of the pavement as well as the charge for the digging of the ditch thereunder. The plaintiff, on the other hand, contends that the charge for breaking and replacing the pavement, that is, thirty-nine cents, does not include the fourteen cents per lineal foot for the completion of the ditch itself. On this theory, plaintiff would be entitled to include the item under Item 6 and also under Item 1. The contract provision, in paragraph 12 which governs payment to be made.and what is included therein for breaking pavement and replacing the same is as follows: “* * * thirty-nine cents per lineal foot for breaking concrete, brick and macadam, and digging ditches under the same and replacing the same, as aforesaid.”- The *858 plaintiff contends that this question is governed by sections 3 and 7 of the contract, which, it says, make it plain that the contract requirement is simply to break the pavement and dig a ditch therein, not going below the undersurface of the pavement for the thirty-nine cents, with the fourteen cents to be added for any ditch extending below the undersurface of the pavement. We cannot subscribe to this construction of the contract. It would seem impossible that the contract should mean that the paving is to be broken, which, of course, means broken clear through, and removed, and should not include in the operation of breaking and replacing everything that was to be done with reference to the pavement itself. To say that the contract contemplates that the pavement is to be broken at one cost and that a different and additional price is to be paid for digging a ditch in it would be to attach to language a meaning not consonant with the common acceptation of its effect. We believe that the commissioner and the trial court were correct in the disposition made of this item.

Item No. 2 was allowed in full by both the commissioner in chancery and the trial court. Neither party excepted to this.

Item No. 3 was disallowed by the commissioner and disallowed by the court. The plaintiff (appellee) assigns this as cross-error.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sturm v. City of Saint Albans
78 S.E.2d 462 (West Virginia Supreme Court, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
169 S.E. 785, 113 W. Va. 854, 1933 W. Va. LEXIS 261, Counsel Stack Legal Research, https://law.counselstack.com/opinion/raleigh-county-construction-co-v-amere-gas-utilities-co-wva-1933.