Rajala v. Holland Corp. (In Re Chesapeake Associates, Ltd. Partnership)

141 B.R. 737, 1992 Bankr. LEXIS 940, 1992 WL 151203
CourtUnited States Bankruptcy Court, D. Kansas
DecidedJune 30, 1992
Docket19-20063
StatusPublished
Cited by4 cases

This text of 141 B.R. 737 (Rajala v. Holland Corp. (In Re Chesapeake Associates, Ltd. Partnership)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rajala v. Holland Corp. (In Re Chesapeake Associates, Ltd. Partnership), 141 B.R. 737, 1992 Bankr. LEXIS 940, 1992 WL 151203 (Kan. 1992).

Opinion

MEMORANDUM OPINION AND ORDER

BENJAMIN E. FRANKLIN, Chief Judge.

This matter comes on before the Court pursuant to cross-motions for summary judgment in the trustee’s action to avoid and recover an alleged preferential transfer. The trustee is represented by Laurence M. Frazen and Phillip G. Greenfield of Bryan, Cave, McPheeters & McRoberts. The Holland Corporation is represented by Peter V. Ruddick of Speer, Austin, Holli-day & Ruddick. Upon the filing of stipulations and memorandum briefs by the parties, the Court took the matter under advisement.

FINDINGS OF FACT

The parties stipulated to the relevant facts necessary for a determination of the issues in this case. The facts as stipulated to by the parties are as follows:

1. The Court has jurisdiction over this matter pursuant to Title 28 U.S.C. §§ 157 and 1334, as this is a proceeding which arises in the Chapter 7 proceeding of Chesapeake Associates, Limited Partnership, d/b/a Chesapeake Estates Apartments (hereinafter “Chesapeake”).

2. Venue is proper in this Court pursuant to Title 28 U.S.C. § 1409.

3. This is a core proceeding pursuant to Title 28 U.S.C. § 157(b)(2)(F).

4. The Holland Corporation (hereinafter “Holland”) is a Kansas Corporation engaged in the business of aggregate production, as well as the business of grading, asphalt paving, and concrete construction.

5. Holland owns its own quarries and produces raw aggregate from limestone. The aggregate is then utilized in the paving and asphalt aspects of Holland’s work. Holland’s concrete construction business focuses on curb and gutter installation and parking lot construction.

6. Chesapeake is a Kansas limited partnership in which Thomas Martin and Marion Martin are the sole limited and general partners.

7. On or about July 9, 1985, Holland and Mid-America Construction, Inc. (“Mid-America”) entered into a subcontract agreement (“Subcontract Agreement”) in which Holland contracted to perform various aspects of the construction of Chesapeake Estates Apartments for the owner of that project (Chesapeake).

8. Thomas Martin was a principal in Mid-America.

9. Pursuant to § 3 of the Subcontract Agreement, Holland was to be paid, subject to additions and deductions for Change Orders or Field Orders, the total sum of $1,541,800 in consideration for its performance under the Subcontract Agreement.

10. Pursuant to § 4 of the Subcontract Agreement, Mid-America agreed to pay Holland for progress on the project on a monthly basis. Mid-America was to make monthly payments to Holland pursuant to written requisitions for payment submitted *740 by Holland for work performed during the current month and work performed from the 20th day of the previous month.

11. Pursuant to § 4, 11 C of the Subcontract Agreement, Holland would issue an invoice to Mid-America by the 23rd of each month. Mid-America would then review the invoice and prepare a check for Holland between the 15th and the 20th of the following month.

12. Holland’s work entailed installation of sanitary and storm systems, grading of the site, preparation of the apartment building sites, preparation of the roadway subgrade, preparation of the parking lot subgrade, installation of the concrete curbs and gutter on the parking lot subgrade, installation of the parking lots and the roadways, and the installation of the asphalt. When all of the above was complete, Holland was to place four inches of top soil on the site to prepare it for landscaping.

13. Section 4, 11B of the Subcontract Agreement provides for the withholding of “retainage” by Mid-America. From each monthly payment due to Holland, Mid-America would retain 10% of that amount. The custom and practice of the construction industry is to require retainage to insure that the contractor completes the work in a timely fashion.

14. The custom and practice of the industry provides retained funds would not be used as potential set-off against disputes surrounding performance under the Subcontract Agreement. Under the Subcontract Agreement, the money was due and owing to Holland. The sole purpose of the retainage was to motivate Holland to complete the job and, upon satisfactory completion, Holland was to receive the full amount of the retainage.

15. Pursuant to § 4, 11E, the total amount retained as described above was to be paid to Holland within thirty (30) days after the work required under the Subcontract Agreement had been completed and, among other things, accepted by the architect. In practice, the retention is paid when the project is substantially complete.

16. Throughout the term of the Subcontract Agreement, Mid-America exercised its rights under the Subcontract Agreement and retained 10% of all monies due and owing to Holland.

17. After the Subcontract Agreement was executed in July of 1985, Holland’s work began on the Chesapeake project immediately.

18. Holland’s work on the project was completed in or about November of 1987.

19. The final invoice from Holland to Mid-America is Invoice No. 3418 dated November 19, 1987.

20. Invoice No. 3418 from Holland to Mid-America reveals the total completed contract amount was $1,911,734.14. The $369,934.14 difference between the original contract price and the amount ultimately billed to Mid-America is due to Change Orders or Field Orders which accumulated from 1985 to 1987. A Change Order or Field Order memorialized agreements between Mid-America and Holland for additional work over and above the work required by the Subcontract Agreement.

21. With respect to Change Orders and Field Orders, Holland would obtain a written agreement with respect to the additional work from Mid-America before it began the work. Holland would complete the work and invoice Mid-America. Mid-America would then write their Change Orders or Field Orders from Holland’s invoice.

22. As of November 19, 1987, Holland had completed its contract obligations at a total contract price of $1,911,734.14. Mid-America had retained, pursuant to § 4,11D, $191,173.44, leaving a total current payment obligation of $1,720,560.70. Mid-America had previously paid $1,669,779.75. Accordingly, as of November 19, 1987, Mid-America owed Holland $50,780.94 under the Subcontract Agreement.

23. Between July of 1985 and November of 1987, complete ownership of Chesapeake was transferred to Thomas and Marion Martin. Prior to that ownership change, Holland was looking to Mid-America for payment on the Subcontract Agree *741 ment. Following the ownership change, Holland was looking to Chesapeake for payment on the balance due under the Subcontract Agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Urban Commons 2 West LLC
S.D. New York, 2023
Hofmann v. Drabner (In re Baldwin)
514 B.R. 646 (D. Utah, 2014)
Low v. Lan
118 Cal. Rptr. 2d 60 (California Court of Appeal, 2002)
Miller v. Kibler (In Re Winters)
182 B.R. 26 (E.D. Kentucky, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
141 B.R. 737, 1992 Bankr. LEXIS 940, 1992 WL 151203, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rajala-v-holland-corp-in-re-chesapeake-associates-ltd-partnership-ksb-1992.