This text of 650 A.2d 1319 (Rajabi v. Potomac Electric Power Co.) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rajabi v. Potomac Electric Power Co., 650 A.2d 1319 (D.C. 1995).

Opinion

TERRY, Associate Judge:

Appellants, husband and wife, filed this negligence action against Potomac Electric Power Company (“Pepeo”) and the District of Columbia. They alleged in their complaint that a portion of a defective street light fixture fell on their car, causing an accident which resulted in bodily injury and property damage. The trial court granted summary judgment in favor of both defendants. We affirm.

I

On July 1,1991, appellant Rajabi was driving her husband’s car westbound on Canal Road, N.W., when a large glass globe, part of an overhead street light fixture, suddenly fell on the car. Ms. Rajabi was startled and lost control of the car, which ran up onto the curb. As a result of these events, Ms. Rajabi allegedly suffered serious injuries. At that time Pepeo was obligated under a contract with the District of Columbia to replace high-pressure sodium vapor street lamps, such as the ones on Canal Road, once every five years and to clean the fixtures once a year. The same contract required Pepeo to inspect and repair the fixtures while in the process of replacing the lamps.

According to the terms of the contract, Pepeo was scheduled to replace the Canal Road lamps and clean the fixtures in 1991. Since the previous cleaning had been performed in May of 1990, Pepeo scheduled both the cleaning and the replacement of the lamps for May 1991. However, because of budgetary constraints and the low burnout rate observed in a citywide survey, the District asked Pepeo to defer replacement of these street lights until September 1991. Pepeo complied and postponed the cleaning of the light fixtures until the same time.

Appellants 1 sued the District of Columbia and Pepeo under theories of negligence and res ipsa loquitur, arguing that both defendants had a duty to maintain the light fixtures so as to prevent harm to passing motorists. They claimed that the District and Pepeo were negligent because they had failed to perform an inspection of the street lights within twelve months after the previous inspection, as the maintenance contract required. After a hearing, the trial court granted summary judgment in favor of both defendants, ruling that appellants had not identified a defect in the light fixture, nor had they offered any evidence to demonstrate that either the District or Pepeo had actual or constructive notice of any such defect or that either of them had deviated from the applicable standard of care.

II

Our review of an order granting summary judgment is limited to determining whether the trial court properly ruled that there was no genuine issue of material fact for trial. See, e.g., Allen v. Hill, 626 A.2d 875, 877 (D.C.1993); Holland v. Hannan, 456 A.2d 807, 814-815 (D.C.1983). A material fact is one which, under the applicable substantive law, is relevant and may affect the outcome of the case. “Factual disputes that are irrelevant or unnecessary will not be counted.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 2510, 91 L.Ed.2d 202 (1986).

Appellants claim that the language in the maintenance contract which requires Pepeo to provide “one cleaning per year” is susceptible of two different interpretations 2 and thus gives rise to an issue of material *1322 fact. This argument is without merit. The asserted ambiguity of the contractual language would create an issue of material fact only if it were relevant to determining the District’s or Pepeo’s negligence. We agree with the trial court that, even if the language were construed in appellants’ favor, appellants failed to demonstrate that the contract established a standard of care. Since there was no other evidence from which the jury could determine a standard of care, the trial court correctly granted summary judgment for Pepeo and the District.

At the outset we note that, although the District of Columbia has a duty to maintain its streets in a reasonably safe condition, District of Columbia v. Freeman, 477 A.2d 713, 718 (D.C.1984), it is not an insurer of safety of those who utilize its streets and sidewalks. See District of Columbia v. Cooper, 445 A.2d 652, 655 (D.C.1982) (en banc); Hackett v. District of Columbia, 264 A.2d 298, 299 (D.C.1970). Moreover, “the mere happening of an accident does not impose liability or reveal proof of negligence.” District of Columbia v. Davis, 386 A.2d 1195, 1200 (D.C.1978). In order to recover from either the District or Pepeo for failure to maintain the street light, appellants must show that a dangerous condition existed and that the District or Pepeo had notice of the danger. See Hackett, supra, 264 A.2d at 299.

Appellants alleged that the light globe that fell on their car was defective, but they failed to identify the supposed defect. See District of Columbia v. Jones, 265 A.2d 594, 595 (D.C.1970) (no evidence showing that nonconforming shape of manhole cover caused it to slip off manhole). The mere assertion by appellants that sometime after the accident they were able to see the “poor condition” (not further described) of two other street lights nearby is insufficient to prove that there was a defect on July 1 in the one from which the globe fell. Furthermore, even if appellants had identified a defect, the District and Pepeo must have had actual or constructive notice of it before they could be held liable. Washington Metropolitan Area Transit Authority v. Davis, 606 A.2d 165, 175 (D.C.1992); District of Columbia v. Fowler, 497 A.2d 456, 461 (D.C.1985); Jones, supra, 265 A.2d at 595-596. Since it is undisputed that they did not have actual notice of the alleged defect, 3 appellants would have to prove constructive notice; ie., they would have to show that the light fixture had “remained in an unsafe condition so long that the District authorities [or Pepeo] ought to have known of it, if they had exercised reasonable care.” Jones v. District of Columbia, 123 A.2d 364, 366 (D.C.1956).

Appellants argue that the District and Pepeo would have had notice, actual or constructive, if they had exercised reasonable care by following the twelve-month cleaning schedule outlined in the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wise v. United States
145 F. Supp. 3d 53 (District of Columbia, 2015)
Briscoe v. District of Columbia
62 A.3d 1275 (District of Columbia Court of Appeals, 2013)
Paul Burke v. Air Serv International, Inc.
685 F.3d 1102 (D.C. Circuit, 2012)
Brown v. 1301 K Street Ltd. Partnership
31 A.3d 902 (District of Columbia Court of Appeals, 2011)
Burke v. Air Serv Int'l, Inc.
775 F. Supp. 2d 13 (District of Columbia, 2011)
Mixon v. Washington Metropolitan Area Transit Authority
959 A.2d 55 (District of Columbia Court of Appeals, 2008)
Tucci v. District of Columbia
956 A.2d 684 (District of Columbia Court of Appeals, 2008)
St. Paul Mercury Insurance v. Capitol Sprinkler Inspection, Inc.
573 F. Supp. 2d 152 (District of Columbia, 2008)
Cosio v. District of Columbia
940 A.2d 1009 (District of Columbia Court of Appeals, 2008)
Herbert v. District of Columbia
691 A.2d 1175 (District of Columbia Court of Appeals, 1997)
Jimenez v. Hawk
683 A.2d 457 (District of Columbia Court of Appeals, 1996)
Hartford Casualty Insurance v. Potomac Electric Power Co.
927 F. Supp. 473 (District of Columbia, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
650 A.2d 1319, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rajabi-v-potomac-electric-power-co-dc-1995.