Raisch v. County of Monterey

35 P.2d 587, 140 Cal. App. 627, 1934 Cal. App. LEXIS 1088
CourtCalifornia Court of Appeal
DecidedSeptember 13, 1934
DocketCiv. No. 8911
StatusPublished
Cited by3 cases

This text of 35 P.2d 587 (Raisch v. County of Monterey) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Raisch v. County of Monterey, 35 P.2d 587, 140 Cal. App. 627, 1934 Cal. App. LEXIS 1088 (Cal. Ct. App. 1934).

Opinion

STURTEVANT, J.

In an action to recover an alleged balance due under a construction contract the trial court made findings in favor of the defendant and from the judgment entered thereon the plaintiff lias appealed and has brought up typewritten transcripts.

The' plaintiff alleged a contract for an agreed price in his first count and he alleged the reasonable value in his second count. In its answer the defendant denied that there was any balance due, alleged full payment and discharge, and alleged that the controversy arose out of a •written contract which it pleaded in haec verba. On the trial it was the theory of the plaintiff that the written contract provided the terms of the contract and a specified sum for its performance and that it also provided for the payment of the additional sum of $1 per yard if, by order of the defendant’s agent, the county surveyor, the plaintiff should lay the concrete road base in strips, one-half at a time. On the other hand, it was the contention of the defendant that although the general printed specifications contained a passage, as claimed by the plaintiff, such passage was subordinate to and gave way in the presence of certain special written specifications inconsistent therewith, and further, even though the contract contained the provisions claimed by the plaintiff, that the plaintiff never came within its provisions and is not entitled to any relief thereunder.

That the contract is ambiguous is manifest. That both parties so viewed the instrument appears from the fact that before the plaintiff made a bid and several times thereafter the representative of the plaintiff deemed it necessary to call, and therefore called on the county surveyor of the defendant county and asked for his interpretation of subdivision “K” of section 28 of the printed specifications. That officer freely stated his interpretation. It also appears that before the bid was let the members of the board of supervisors, the county surveyor, and the plaintiff’s representative held a meeting at which said clause was discussed and the plaintiff was specifically advised that the defendant [629]*629would not pay the dollar charge provided in said subdivision “K”. The ambiguity arose in this manner. In framing the contract a printed form of specifications was used. That form contains over four hundred folios. It covers specifications of roads of various types, also of bridges, etc. To it are annexed certain special specifications comprising about thirty-five folios. The latter contained among other provisions the following:

“In case of conflict between these Special Provisions and the Standard Specifications, the Special Provisions shall take precedence over and be used in lieu of such completed portions. . . .
“Section 6—Maintaining Traffic.
“The Contractor shall conduct his operations so that all traffic coming from ranches facing along the road between the Hilltown Bridge and the Monterey-Castroville road and all traffic coming from any roads leading into the Salinas-Monterey road may be cared through construction without interruption and with as little inconvenience to said travel as possible. . . .
“All through traffic over the Salinas-Monterey road shall be detoured over the Monterey-Castroville road and signals and lights with proper signs shall be maintained by the contractor at his expense at the junction of the Monterey-Castroville road and the Monterey-Salinas road, and at a point southeasterly from the Hilltown Bridge. . . .
“(i) The pavement shall be poured in two ten foot sections, and a cold joint left between the sections. The edges along the cold joint shall be rounded as shown on plan.” On the other hand the general specifications contained a passage as follows:
“Placing Concrete Pavement: . . .
“(k) Half Width Construction.—Where ordered by the County Surveyor, concrete pavement shall be constructed one-half (½) width at a time and the roadway opposite the side under construction shall at all times be kept clear and open to public traffic.
“No portion of the equipment used for mixing the concrete for pavement shall be allowed to stand on or project over that portion of the roadbed open to public traffic as herein provided.
[630]*630“Concrete work shall be adequately barricaded longitudinally to protect the work and safeguard the public traffic.
“For all pavement ordered placed one-half (½) width at a time, the Contractor will be paid one dollar ($1.00) per cubic yard in addition to the contract price for Class ‘A’ Portland cement concrete pavement, when not otherwise provided in the Special Provisions.” The general specifications also provided:
“ Section 4—Scope of Work. . . .
“The Contractor shall do such extra work and furnish such materials as may be required for the proper completion or construction of the work contemplated and he shall do no extra work except upon written order from the County Surveyor, and in the absence of such written order he shall not be entitled to payment for such extra work. All bills for extra work done shall be filed in writing with the County Surveyor.” Also they provided, section 5, subdivision (a) that the county surveyor should decide “ . . . all questions which may arise as to the interpretation of the plans and specifications . . . (and) His decision shall be final. ...” They further provided:
“Section 5. Control of the Work. . . .
“(d) Coordination of Plans, Specifications and Special Provisions.—These specifications, the plans, special provisions, and all supplementary documents are essential parts of the contract, and a requirement occurring in one is as binding as though occurring in all. They are intended to be cooperative, to describe and provide for a complete work. Plans shall govern over specifications, special provisions shall govern over both specifications and plans.
“(e) Interpretation of Plans and Specifications.—Should it appear that the work to be done or any of the matters relative thereto, are not sufficiently detailed or explained in these specifications and the Special Provisions, the Contractor shall apply to the County Surveyor for such further explanations as may be necessary and shall conform to the same as part of the contract so far as may be consistent with the original specifications; and in the event of any doubt or question arising respecting the true meaning of the specifications, reference shall be made to the Board of Supervisors, whose decision thereon shall be final. . . .
[631]*631“Section 7. Legal Relations and Responsibility to the Public. . . .
“(e) . . . Residents along the road must be provided for as far as practicable. Convenient access to driveways, houses and buildings along the line of the work must be maintained and temporary approaches to crossings or intersecting highways shall be provided and kept in good condition, where required by the County Surveyor. . . .
“Joints. . . .
“(p) Contract Joints shall be formed by pouring the concrete on one side of the joint and allowing it to set before the adjacent concrete is placed. . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Parnell v. Stanfield
288 P.2d 118 (California Court of Appeal, 1955)
American Marine Paint Co. v. Tooley
127 P.2d 960 (California Court of Appeal, 1942)
People v. Ganahl Lumber Co.
75 P.2d 1067 (California Supreme Court, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
35 P.2d 587, 140 Cal. App. 627, 1934 Cal. App. LEXIS 1088, Counsel Stack Legal Research, https://law.counselstack.com/opinion/raisch-v-county-of-monterey-calctapp-1934.