Rainier, Inc. v. United States

147 F. Supp. 709, 137 Ct. Cl. 210, 1957 U.S. Ct. Cl. LEXIS 148
CourtUnited States Court of Claims
DecidedJanuary 16, 1957
DocketNo. 49390
StatusPublished

This text of 147 F. Supp. 709 (Rainier, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rainier, Inc. v. United States, 147 F. Supp. 709, 137 Ct. Cl. 210, 1957 U.S. Ct. Cl. LEXIS 148 (cc 1957).

Opinion

JoNes, Chief Judge,

delivered the opinion of the court:

The plaintiff sues for $338,371.88, which it claims is the balance due it on 90,050 overcoats which it manufactured for the Army under a contract originally entered into on or about September 16, 1946, and dated June 28, 1946. Plaintiff’s contract was one of 18 awarded about that time for the manufacture of 1,262,000 field overcoats for the Army for a consideration of approximately $22,647,650.

The facts, which are extensive and somewhat complicated, are set forth in detail in the court’s findings of fact.

On June 14, 1946, invitations to bid were sent out to 150 clothing manufacturers by the Quartermaster Purchasing Office at New York, hereinafter called the New York Office, but there was such a strong civilian demand in the clothing market at that time that only 18 bids were received. The request for bids recited that the informal bids would be used as a basis for negotiating contracts.

After considerable discussion as to the inclusion of a price revision clause, the plaintiff submitted a unit price bid of $19.09 per garment.

Telegraphic notices of conditional awards were sent to the 18 bidders, including plaintiff, on June 29, 1946, just prior to the end of the fiscal year. By telegram, dated August 9, 1946, plaintiff was advised by the contracting officer that the award of the contract for the manufacture of 90,000 overcoats had been confirmed by the War Department.

After the overcoat contracts had been executed, the Quartermaster General criticized the New York Office for its failure to make a cost analysis of the bids before the awards were made, called attention to the high administrative expense and high rate of profit in plaintiff’s contract, and returned the file relating to all of the overcoat contracts, except three, to the New York Office with the suggestion that a renegotiation with some of the contractors as to the unit prices specified in their contract would probably be necessary.

Negotiations for a reduction in the unit bid prices were [212]*212conducted during the period November 1 to November 15, 1946, under the supervision of Major Voiers who was then Director of Procurement of the New York Office and who became successor contracting officer on or about December 1, 1946. Plaintiff’s representatives were called upon to attend two meetings held in the New York Office. At the first meeting plaintiff’s officers refused to agree to any adjustment in the bid price, but a few days later they signed Modification “C” of the contract, whereby plaintiff’s unit price was reduced from $19.09 to $18.99. Major Voiers reported the reduction in plaintiff’s unit price to the Quartermaster General with the statement that all elements of cost included in plaintiff’s bid had been refigured and substantiated.

On May 19, 1947, Major Voiers notified plaintiff that almost 30 percent of the overcoats had been delivered, and called attention to a provision in the price revision article which required the contractor to submit cost data within five days after such delivery. Cost data were submitted by plaintiff and a field audit was recommended by defendant’s Cost and Price Analysis Section. But in the meantime effort was made to get the profit items reduced.

A Price Adjustment Review Board, composed of various officials of defendant’s New York Office, met to consider the matter of negotiating a revision of the profit items of the contract. No decision on that question was made, but the Board voted that the field audit be made.

On July 28, 1947, the Price Adjustment Advisory Group met to consider what amount should be withheld from payments on plaintiff’s delivery, pending the completion of the field audit. After discussion the members voted to withhold $3.06 per unit from plaintiff and to proceed with the field audit.

On July 29, 1947, the contracting officer notified plaintiff that $3.06 per unit would be withheld as a temporary expedient, pending the result of the field audit. Plaintiff protested this action and after it agreed to furnish a bond all but $50,000 of the funds withheld were released to it.

On October 16, 1947, after the Army Audit Agency had submitted its report, Major Voiers, the contracting officer, [213]*213telephoned the plaintiff’s president and demanded that he appear at once at the former’s office to negotiate a revised price. Plaintiff’s president, Oberman, stated that he was unable to appear immediately because one of plaintiff’s officers was in the hospital and he himself was needed at the factory. He suggested a meeting be set for Monday, October 20,1947. This was refused. Major Voiers insisted that he come at once and when Oberman declined, the contracting officer declared that he would then and there negotiate by telephone, and he proceeded to read off proposed unit prices in the various cost classifications.

Mr. Oberman objected to this procedure, whereupon Major Voiers stated that he would issue a unilateral determination of a unit price of about $15 per unit and that the fiscal officer would be instructed to adjust payments accordingly.

Plaintiff filed a telephone protest in Washington, and, as a result, the contracting officer agreed to a meeting with plaintiff on October 20, 1947. However, at that meeting at which plaintiff’s officers appeared with their accountants, Major Voiers refused to go into the cost items and insisted that he was interested only in reducing the profits. He refused to furnish plaintiff’s representatives a copy of the Army Audit Agency’s report or any other cost data on which he relied. He did mention the revised cost figures that had been submitted to him by the Cost and Price Analysis Section. The conference lasted about 20 minutes. The two sets of cost data which plaintiff had previously submitted were not used as a basis for negotiation. Plaintiff’s representatives had no opportunity to determine which of plaintiff’s claims had been deleted, and they were given no information as to how the unit cost figure supplied by the Cost and Price Analysis Section was computed.

The conference of October 20th was the first and only one afforded plaintiff by the contracting officer for negotiating a revision of price. As to this conference, our trial commissioner who heard the testimony recommended the following finding:

The evidence establishes that the contracting officer had made a determination of the unit price he intended to allow before the conference began, that he did not [214]*214negotiate with plaintiff in accordance with the terms and provisions of the price revision article, and that he acted arbitrarily in making his determination.

We approve the finding, since we have seldom had our attention called to a more arbitrary attitude on the part of a constituted official. Certainly, when the testimony is read, there appears to have been a complete failure on the part of the contracting officer to negotiate in good faith as required by section 14 (d) of the contract, which is set out in the court’s finding 3.

In fact, defendant’s counsel does not strongly contend that there was negotiation in good faith by the contracting officer and his associates. But he earnestly contends that regardless of the circumstances plaintiff is entitled only to its costs plus a profit of $1.65 per unit.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
147 F. Supp. 709, 137 Ct. Cl. 210, 1957 U.S. Ct. Cl. LEXIS 148, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rainier-inc-v-united-states-cc-1957.