Ragnar Benson, Inc. v. Jacob G. Kassab, J. G. Kassab, Inc., and Jones & Laughlin Steel Corporation

325 F.2d 591, 1963 U.S. App. LEXIS 3405
CourtCourt of Appeals for the Third Circuit
DecidedDecember 18, 1963
Docket14384_1
StatusPublished
Cited by7 cases

This text of 325 F.2d 591 (Ragnar Benson, Inc. v. Jacob G. Kassab, J. G. Kassab, Inc., and Jones & Laughlin Steel Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ragnar Benson, Inc. v. Jacob G. Kassab, J. G. Kassab, Inc., and Jones & Laughlin Steel Corporation, 325 F.2d 591, 1963 U.S. App. LEXIS 3405 (3d Cir. 1963).

Opinion

MARIS, Circuit Judge.

These are cross appeals in an action brought in the District Court for the Western District of Pennsylvania by the plaintiff, Ragnar Benson, Inc., against the defendants Jacob G. Kassab, J. G. Kassab, Inc., and Jones & Laughlin Steel Corporation seeking a judgment in the amount of $541,424.00, the amount by which the defendants were allegedly enriched through the diversion of a corporate opportunity to the Kassab corporation by Kassab, a former officer of the plaintiff corporation. The defendant Jones & Laughlin was charged with knowingly, actively participating in the breach of trust. Jurisdiction was grounded on the diverse citizenship of the parties.

Involved is a contract for the construction of two warehouses at Jones & Laughlin’s works at Cleveland, Ohio; the time was the winter of 1958-1959 when Jones & Laughlin had a pressing need for additional warehouse space because of an increase in steel orders in anticipation of a prospective steel strike. The plaintiff, an Illinois corporation engaged in the construction business, maintained offices in Pittsburgh which were managed by Kassab, then a vice-president and director of the plaintiff corporation. Kassab had obtained construction contracts for plaintiff from Jones & Laughlin and others and had an excellent reputation for his ability to perform such contracts *593 expeditiously. In July 1957, more than a year prior to the events here involved, Kassab, with the plaintiff’s approval, had become an unpaid consultant to Jones & Laughlin in connection with its construction projects.

Early in October 1958 Jones & Laughlin asked Kassab to estimate the cost of constructing two warehouses in Cleveland. Kassab directed Gay E. Bodick, the plaintiff’s estimator, as well as other personnel of the plaintiff, to work on the estimate and to attend meetings in respect to the project. At the end of October, Kassab asked John W. Lindsey, vice-president of Jones & Laughlin in charge of purchasing, whether he might bid on the warehouse project on his own behalf and Kassab was told it was satisfactory with Jones & Laughlin provided Kassab cleared the matter with the plaintiff. On November 4th Jones & Laughlin received an estimate prepared by Bodick upon stationery of Tristate Construction Service Corporation, a corporation owned by Kassab the name of which shortly thereafter was changed to J. G. Kassab, Inc., one of the present defendants. The contract in the amount of $2,365,675.00 was orally awarded to Kassab’s corporation on November 12, 1958 and on February 6, 1959 a written contract was executed between Jones & Laughlin and Kassab’s corporation. When the contract was awarded on November 12th Kassab assured Lindsey that he had cleared the matter with the plaintiff and that it was all right with the plaintiff for Kassab to bid on the job on his own account. Jones & Laughlin made no inquiry of the plaintiff as to whether it was all right to do business with Kassab individually.

On or about November 4th, prior to the award of the contract, Kassab told Raymond L. Benson, the plaintiff’s president and chief executive officer, of his intention to resign and subsequently he submitted to the plaintiff his written resignation dated November 8th. Kassab had shown Lindsey his written resignation on or about November 8th. On December 1, 1958, when Benson came to Pittsburgh to deal with the problem created by Kassab’s resignation, Kassab told Benson that he had secured the Jones & Laughlin contract for himself. Benson also learned that Bodick had attended the construction meetings. It was Benson’s understanding that only the engineering portion of the project had been completed at that time and that construction work had not as yet started. The following day, December 2d, Benson visited Avery Adams, president of Jones & Laughlin. Benson testified that his purpose in making the visit was to see whether Adams knew about the contract, to tell Adams he was “a little disappointed” in the way in which it was handled, and to make him aware of the fact that plaintiff had lost the job. Benson admitted, however, that he did not say to Adams that the job actually belonged to the plaintiff. Eight days later, on December 10th, Benson visited Lindsey but did not make any claim to the contract for the plaintiff. During this period Bodick, with Benson’s knowledge, attended construction meetings with respect to the Jones & Laughlin contract in Cleveland on December 5th, 8th and 15th. On December 10th Bodick replaced Kassab as vice-president in charge of the Pittsburgh office and on December 15th, when Kassab’s resignation was accepted by plaintiff’s board of directors, Bodick replaced Kassab on the board. The construction work proceeded and was substantially completed in late April. Benson again met with both Adams and Lindsey in April 1959 when, according to his testimony, he was very careful in his “choice of words” and he did not say that plaintiff contemplated legal action against Jones & Laughlin but told them that legal action was contemplated against Kassab because of the loss of the contract. Benson also met with Kassab on several occasions but made no demand in respect to the contract until May 5th when the plaintiff, through its counsel, notified both the Kassab defendants and Jones & Laughlin that they would be held responsible for the profits made on the project. Progress payments had been made by Jones & Laughlin to Kassab’s *594 Corporation to cover operating expenses but Jones & Laughlin retained approximately $236,072.00, about 10% of the contract price. On May 25th the present suit was instituted.

Trial was had to a jury. At the conclusion of the plaintiff’s case, each of the defendants moved for a directed verdict. The trial judge granted Jones & Laughlin’s motion for a directed verdict but denied the motions of the Kassab defendants. Thereupon Kassab and his corporation rested, and the action as against them was submitted to the jury which returned a verdict in favor of the plaintiff in the amount of $118,289.00, upon which judgment was entered. Thereafter, the plaintiff filed motions for a new trial as to all the defendants, which were denied. Both the Kassab defendants moved for judgment n. o. v. which motions were also denied. These appeals followed.

We consider first the plaintiff’s contention that the verdict against the Kassab defendants was inadequate and that the court erred in denying a new trial on that ground. It is well settled that the courts will indulge all presumptions in favor of the validity of a verdict. 1 Generally, the grant of a new trial on the ground of the inadequacy of the verdict is for the trial court and its action will not be overruled unless discretion was abused 2 or unless it is clear that the jury’s verdict was influenced by partiality, passion or prejudice or by some misconception of the law. 3 With these principles in mind, we consider briefly the evidence which was before the jury on the question of damages. In a pretrial statement, referred to during the trial, the amount of profits was stated by the plaintiff as $700,000.00, to which counsel for the plaintiff in his opening statement .added $125,000.00 interest.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

FCC National Bank v. Gilmore (In Re Gilmore)
221 B.R. 864 (N.D. Alabama, 1998)
COELHO
20 I. & N. Dec. 464 (Board of Immigration Appeals, 1992)
Taylor v. Illinois
484 U.S. 400 (Supreme Court, 1988)
Danvers v. Dibra
276 F. Supp. 572 (Virgin Islands, 1967)
Kassab v. Ragnar Benson, Inc.
254 F. Supp. 830 (W.D. Pennsylvania, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
325 F.2d 591, 1963 U.S. App. LEXIS 3405, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ragnar-benson-inc-v-jacob-g-kassab-j-g-kassab-inc-and-jones-ca3-1963.