Radon Construction, LLC v. Land Endeavor 0-2, Inc.

2019 Pa. Super. 314, 221 A.3d 654
CourtSuperior Court of Pennsylvania
DecidedOctober 18, 2019
Docket3527 EDA 2018
StatusPublished
Cited by3 cases

This text of 2019 Pa. Super. 314 (Radon Construction, LLC v. Land Endeavor 0-2, Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Radon Construction, LLC v. Land Endeavor 0-2, Inc., 2019 Pa. Super. 314, 221 A.3d 654 (Pa. Ct. App. 2019).

Opinion

J-S35016-19

2019 PA Super 314

RADON CONSTRUCTION, LLC AND IN THE SUPERIOR COURT GREGORY RADON OF PENNSYLVANIA

Appellants

v.

LAND ENDEAVOR 0-2, INC., JOHN ARCIDIACONO & DONNA ARCIDIACONO

Appellees No. 3527 EDA 2018

Appeal from the Order entered May 26, 2017 In the Court of Common Pleas of Philadelphia County Civil Division at No: 1601-00329

BEFORE: OLSON, J., STABILE, J., and STRASSBURGER, J.*

OPINION BY STABILE, J.: FILED OCTOBER 18, 2019

Appellants, Radon Construction, LLC and Gregory Radon (“Greg”)

(collectively “Radon”), appeal from the May 26, 2017 order entered in the

Court of Common Pleas of Philadelphia County, granting partial summary

judgment in favor of Appellees, Land Endeavor 0-2, Inc., John Arcidiacono

(“John”) (collectively “Land Endeavor”), and Donna Arcidiacono (“Donna”).1

Radon argues that Greg was under duress when he signed a June 2015

____________________________________________

* Retired Senior Judge assigned to the Superior Court.

1 The May 26, 2017 order was made final on October 30, 2018 when the trial

court rendered its decision on the remaining claim between the parties. J-S35016-19

contract between Radon and Land Endeavor, a contract that Land Endeavor

terminated on November 24, 2015. Following review, we affirm.

In an opinion issued following its May 26, 2017 order, the trial court

explained:

This lawsuit arises from a failed joint venture agreement between [Radon] and [Land Endeavor] to develop real estate in Philadelphia. The parties’ agreement provided that [Radon] would provide the labor and supplies for the project, and [Land Endeavor] would provide the financing and construction plans. [Radon was] to provide labor “at cost” so that the final cost of each home was $126,000. When the properties were eventually sold, [Land Endeavor] would receive 51% of the profits and [Radon] would receive 49%.

Subsequent to signing the joint venture agreement, the parties entered into two separate subcontract agreements—in March 2015 and June 2015. The March 2015 agreement allowed [Land Endeavor] to “terminate” the agreement “upon 48 hours notice” to [Radon] of [Radon’s] default “on any of the terms or conditions” in the contract. One of those conditions required [Radon] to complete each project phase within seven days “unless otherwise specified in a work order.” The contract did not give [Radon] an opportunity to cure any alleged default.

The later executed June subcontract was largely the same as the March 2015 subcontract; however, it included more specific paragraphs regarding default. The provision provided [Radon] with 48 hours to cure any breach of the parties’ agreement. If [Radon] did not cure within that allotted period of time, [Land Endeavor] had the sole right to terminate the parties’ venture. If [Land Endeavor] chose that route, however, [Radon] would be provided a “termination payment” which would be “equal to the sum of payment for all work performed and unpaid to the date of termination and all direct costs reasonably incurred by [Radon] in connection with the termination period.”

The joint venture was ultimately terminated in November 2015 when [Radon] installed improper structural beams. On November 11, 2015, [John] notified [Radon] of the issue with the beams via e-mail. Apparently, on November 19, 2015, [Greg] met with a

-2- J-S35016-19

structural engineer, Chris Menna, to review the issue and determine a solution. [Greg], however, misinformed Mr. Menna of [Land Endeavor’s] concerns with the beams, and, as a result, Mr. Menna’s proposed solution did not solve the identified problem. Therefore, pursuant to ¶ 14 of the June 2015 subcontract, [John] terminated the parties’ venture in a detailed letter to [Greg] on November 24, 2015.

Trial Court Opinion, 7/11/17, at 2-3 (unnumbered) (citations to contract

provisions omitted).

The trial court noted that Pa.R.C.P. No. 1035.2 governs the disposition

of summary judgment motions and that the court is to view the record in the

light most favorable to the non-moving party, resolving any doubts as to the

existence of genuine issues of material fact against the moving party. Id.

(citation omitted). The court then determined that Land Endeavor’s

termination under the plain terms of the June 2015 contract was proper.

Although that contract afforded Radon 48 hours to cure a default, Radon was

actually provided thirteen days to cure the problem with the beams.

Nevertheless, Radon was “incapable of curing the issue because [Radon] not

only improperly installed the beams, it misunderstood [Land Endeavor’s] issue

with the installation[.]” Id. at 3. The court concluded:

[Radon] argue[s] that the June subcontract is null and void because it was signed under duress. This court disagrees. “[I]n the absence of threats of actual bodily harm there can be no duress where the contracting party is free to consult with counsel.” Carrier v. William Penn Broad. Co., 233 A.2d 519, 521 (Pa. 1967). Here, Mr. Radon had an opportunity to consult with counsel and there was no threat of actual bodily harm. In his deposition, Mr. Radon stated he did not feel physically threatened, but rather felt “emotionally threatened.” Furthermore, Mr. Radon stated he had the opportunity to speak about the contract with

-3- J-S35016-19

“everyone” which he defined as his wife, father, friends, and best friend []—who consequently all advised him not to sign the contract. Mr. Radon can hardly argue he did not have the opportunity to consult with an attorney prior to signing the contract.

Id. Consequently, the trial court granted partial summary judgment in favor

of Appellees on all counts of Radon’s complaint—including the duress claims

in Count IV—with the exception of Count II, which alleged breach of the June

2015 contract. The court explained that while Land Endeavor’s termination

under the June contract was proper, Radon had not been paid its termination

payment under the terms of Paragraph 14 of the agreement. Because the

court was unable to determine the amount of damages, it transferred Count

II to the Philadelphia County arbitration program, confident the amount at

issue was clearly within that program’s $50,000 jurisdictional limits. Id. at 3-

4 (unnumbered).

Radon filed an appeal to this Court from the May 26, 2017 order. We

quashed the appeal because the May 26, 2017 order was not a final order.

Order, 9/26/17, at 1. The remaining claims asserted in Count II of the

complaint were subsequently submitted to an arbitration panel, which

awarded Radon the sum of $13,537.92. Arbitration Award, 2/6/18. Radon

appealed from the arbitration award. On October 30, 2018, the trial court

awarded damages to Land Endeavor in the net amount of $16,198.68.

Disposition, 10/30/18.

-4- J-S35016-19

Radon filed an appeal from the October 30, 2018 adjudication. The trial

court issued an opinion on December 18, 2018, suggesting the appeal should

be dismissed in light of Radon’s failure to file post-trial motions as required by

Pa.R.C.P. No. 227.1. We issued a rule directing Radon to show cause why the

appeal should not be dismissed for failure to preserve any issues for appellate

review. We further instructed, in part:

[I]f the appellants are merely seeking review of the May 26, 2017 order, review of this matter indicates that no judgment has been entered on the trial court docket as required by Pa.R.A.P. 301.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2019 Pa. Super. 314, 221 A.3d 654, Counsel Stack Legal Research, https://law.counselstack.com/opinion/radon-construction-llc-v-land-endeavor-0-2-inc-pasuperct-2019.