R. T. Clark & Co. v. Miller

122 So. 475, 154 Miss. 233
CourtMississippi Supreme Court
DecidedMay 20, 1929
DocketNo. 27590
StatusPublished
Cited by1 cases

This text of 122 So. 475 (R. T. Clark & Co. v. Miller) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R. T. Clark & Co. v. Miller, 122 So. 475, 154 Miss. 233 (Mich. 1929).

Opinion

ANDersoN, J.,

delivered the opinion of the court.

(After stating" the case as above.) It is true, as contended by the revenue agent, that the positive refusal to perform a contract is a breach of it, although the time for performance has not arrived, The Law of Public Contracts (Donnelly), section 304, p. 435; but the mere assertion of a party to a contract that he ivill be unable, or will refuse, to perform his contract is not sufficient to constitute a breach. There must be a distinct, unequivocal, and absolute refusal to perform, treated and acted upon as such by the other party to the contract. A mere assertion of inability to go on with the contract is not a repudiation of the contract. The intention to abandon the contract at some future date is not a breach of it unless such intention is declared in positive terms and unconditionally. When it is so declared, the other [259]*259party lias an opportunity to accept the declaration if he chooses to do so. Benjamin on Sales, section 568; United States v. Smoot, 15 Wall. 36, 21 L. Ed. 107; Dingley v. Oler, 117 U. S. 490, 6 S. Ct. 850, 29 L. R. A. 984; Kilgore v. Baptist Educational Association, 90 Tex. 139, 37 S. W. 598; The Law of Public Contracts (Donnelly), p. 438; 6 R. C. L., section 387, p. 1028; Elliott on Contracts, section 2032. Applying these principles to the facts as conclusively shown by the evidence, we think it clear that there was no breach of the contract by R... T. Clark & Co. The orders and resolutions of the levee board spread on their minutes, give the history of what occurred with reference to the alleged breach of the contract; and there is no other evidence in the case which contradicts such orders and resolutions in any material particular.

The negotiations between the contractors and the levee board, bearing on the question, cover a period of something like two or three months of the first part of the year 1918, and, while they wore going on, the contractors were proceeding with the work under their contract — never stopping, nor expressing any intention of abandoning the work, unless, and until, they were overtaken by bankruptcy. On the contrary, they gave the levee board to understand that they would continue the work as long as their creditors would permit them, although it was thoroughly understood by both parties that, if the prevailing prices of labor and materials going into the work, brought about by the World War, continued, bankruptcy would ensue. There is no other reasonable interpretation that can be put upon the orders and resolutions of the levee board, taken in connection with the other evidence in the case, than that the increase of fifty per cent, in the contract price was granted by the levee board in order to insure against the contractors ’ abandoning their contract at some future time. The increase, therefore, was not in recognition or acceptance of a breach of the con[260]*260tract that bad already taken place. The fight made by both parties, from the beginning* to the end of the negotiations, was to bring about conditions that would prevent a breach of the contract. There is nothing whatever in the resolutions and orders of the levee board to bear out the theory that R. T. Clark & Co. had breached their contract. The correspondence between the levee board and the attorney-general and the levee board, and its attorneys shows conclusively, we think, that there ivas no thought in the minds of any of the parties concerned that R. T. Clark & Co. had abandoned and breached the contract.

The record shows that the unfinished levee work was emergency work — necessary to be completed without delay in order to prevent disastrous floods from the Mississippi river. It is true that R. T. Clark & Co. were perfectly willing to abandon the contract if agreeable to the levee board, but the levee board was not willing for them to do so. Conditions were such that if the contract had been breached and the Guaranty Company had paid the levee board the full penalty of its bond, one hundred sixty thousand dollars, the levee board had no assurance that the contract for the work could be relet at the original price plus one hundred sixty thousand dollars, the proceeds of the bond. On the contrary, judging from the evidence in this record, the indications were that a re-letting of the contract would have resulted in an increase of more than fifty per cent, of the original contract price. In other words, viewing the situation as it existed, at the time, it appeared to the levee board that the best interest of the district required that R. T. Clark & Co. carry out their contract instead of breaching it, and to that end they seem not to have left anything* undone.

The facts and circumstances relied on by the revenue agent as constituting a reletting of the contract, do not show a reletting, but instead a method adopted which the [261]*261levee board conceived would legalize ail increase in the contract price. We think no other reasonable interpretation can be placed on what occurred. It is true that bidders were. present, bnt no bids were made. R. T. Clark & Co. were represented bnt put in no bid, it being’ understood that they were to go on with the work and receive a fifty per cent, raise in the contract price, provided the alleged reletting developed that such increase was reasonable, which it abundantly did. No new contract was made with R. T.. Clark & Co.; they merely agreed to carry out the old contract of November 1,1916', at the increased price. There is nothing in the minutes of the levee board to show that there was a reletting of the work and a new contract. The contractors gave an additional bond of eighty thousand dollars to carry out the old contract — not a new contract. The guaranty bond then in force provided as a condition precedent to liability thereon, in the event of a breach of the contract, that the levee board give the Guaranty Company notice of such breach and afford it an opportunity itself to complete the contract. We are not deciding, under the particular facts of this ease, that a failure to give such notice would defeat a recovery against the Guaranty Company, but we do think that the failure of the levee board to put anything on its minutes declaring that a breach of the contract had taken place and requiring notice thereof to be given to the Guaranty Company, in accordance with that stipulation in the bond, is most significant. The stipulation in the bond for notice was an important provision of the bond, to say the least.

There seems no escape from the conclusion that everything that was done by R. T. Clark & Co. and the levee board, relied on by the revenue agent as constituting a breach of the contract, and the reletting of the contract, was done by agreement between the parties. There is no such thing known to the law as the breach of a contract by agreement of the parties.

[262]*262The revenue agent lays especial emphasis on parts of the testimony of the witnesses Clark, Harris, and Man-gum, as showing.a breach of the contract. Viewing the parts of their testimony relied on in the most favorable light to the revenue agent, it amounted to this: When the contract price for the work was increased by the levee board, E. T. Clark & Co. were practically bankrupt; they had only about ten thousand dollars in money left with which to prosecute the work. One of the witnesses testified that R. T. Clark & Co.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnston v. Stinson
434 So. 2d 715 (Mississippi Supreme Court, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
122 So. 475, 154 Miss. 233, Counsel Stack Legal Research, https://law.counselstack.com/opinion/r-t-clark-co-v-miller-miss-1929.