R. T. Atkison Building Corp. v. Archer Western Construction L.L.C.

90 Va. Cir. 240, 2015 Va. Cir. LEXIS 153
CourtNorfolk County Circuit Court
DecidedMay 5, 2015
DocketCase No. CL 15-488
StatusPublished

This text of 90 Va. Cir. 240 (R. T. Atkison Building Corp. v. Archer Western Construction L.L.C.) is published on Counsel Stack Legal Research, covering Norfolk County Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R. T. Atkison Building Corp. v. Archer Western Construction L.L.C., 90 Va. Cir. 240, 2015 Va. Cir. LEXIS 153 (Va. Super. Ct. 2015).

Opinion

By Judge Junius P. Fulton, III

This matter concerns a claim filed by R. T. Atkison Building Corp. (RTA), a sub-contractor involved in the construction of the Samuel Slover Library against the principal of that contract, Archer Western Construction, L.L.C. (Archer Western) for payment under a payment bond pursuant to Virginia Public Procurement Act § 2.2-4341 (“Little Miller Act”). Defendant Traveler’s Casualty Surety Company (Traveler’s) issued surety on the payment bond. Defendant Archer Western and Traveler’s assert that the Little Miller Act notice provision bars RTA’s claim and, consequently, move for summary judgment.

The critical issue in this case is the determination of what does it mean to “give notice” pursuant to the Little Miller Act. However, before reaching this issue, the Court must address two peripheral issues raised by the parties. First, the Court will not consider the subcontract attached as Exhibit B to Defendants’ Motion for Summary Judgment because the first page of that exhibit states “it is applicable to all work performed in 2013.” RTA performed all of the work at issue in this case in 2014. Due to this limitation, Defendants’ argument that the subcontract provision regarding notice being defined as the date of receipt will not be considered.

Second, the Court will not consider RTA’s claim for retainage. In Exhibit 2 of the Plaintiff’s Complaint, RTA provided a “Payment Application.” On that document, Plaintiff assessed the total retainage as $0.00. Accordingly, no issue of fact remains concerning the amount of retainage.

[241]*241With those issues eliminated, the Court considers the heart of this case:

(i) whether notice is “given” when it is mailed or when it is received; and
(ii) whether the Court may consider a USPS tracking history report attached as “Exhibit A” to Defendants’ Motion for Summary Judgment.

Determination of the issue of when notice is given concerns an issue of statutory construction. The General Assembly allows “[a]ny claimant who has a direct contractual relationship with any subcontractor but who has no contractual relationship, express or implied with the contractor” to bring an action on the contractor’s payment bond. Va. Code § 2.2-4341(B). A claimant may only bring their claim “if he has given written notice to the contractor within 90 days... .” Va. Code § 2.2-4341(B). The Code provides that “[njotice to the contractor shall be served by registered or certified mail... .” Va. Code § 2.2-4341.

The focus of this case is the meaning of “given written notice.” “[C] ourts apply the plain language of a statute unless the terms are ambiguous, or applying the plain language would lead to an absurd result.” Boyton v. Kilgore, 271 Va. 220, 227 (2006) (citations omitted). Moreover, when “the statute’s terms are undefined, those words are given their ‘ordinary meaning,’ in light of ‘the context in which [they are] used’.” Virginia Marine Res. Comm’n v. Chincoteague Inn, 287 Va. 371, 384 (2014) (citation omitted).

“Ambiguity exists if the text can be ‘understood in more than one way or refers to two or more things simultaneously [or] when the language is difficult to comprehend, is of doubtful import, or lacks clearness or definiteness’.” Boyton v. Kilgore, 271 Va. 220, 227, 623 S.E.2d 922, 926 (2006) (quoting Brown v. Lukhard, 229 Va. 316, 321, 330 S.E.2d 84, 87 (1985) (citation omitted)). “The phrase 'absurd result’ is used ‘to describe situations in which the law would be internally inconsistent or otherwise incapable of operation’.” Id. at 227, 623 S.E.2d at 926 (quoting Cook v. Commonwealth, 268 Va. 111, 116, 597 S.E.2d 84, 87 (2004)).

As Defendants point out, one federal court has already interpreted identical language in a nearly identical federal statute. See Pepper Burns Insulation, Inc., 970 F.2d at 1343. In that case the Fourth Circuit found that the language “giving written notice” required receipt of the notice by the contractor. Id. at 1343. The court reasoned that “given” means “put in the possession of the contractor.” Id. at 1343. In that case, the court noted that Congress could have chosen different language, i.e., “upon written notice” or “upon mailing written notice,” to allow mailing to satisfy the notice requirement. Id. at 1343.

Similarly, the General Assembly mandated that notice, for claims under the Little Miller Act, must be “given” within ninety days. In an attempt to distance itself from Pepper Burns, RTA finds it significant that the Little Miller Act only provides one method of service. Specifically, “[n]otice ... shall be served by registered or certified mail... .” Va. Code § 2.2-4341(B). RTA believes that, because the Little Miller Act only provides for service [242]*242of notice by mailing, “given” must mean that notice is satisfied when it is mailed.

Interestingly, the Fourth Circuit addressed this argument in Pepper Burns. There, the court found that the inclusion of mailing as a permissible method of service fails to indicate that mere mailing satisfies the statutory prerequisite. Pepper Burns Insulation, Inc., 970 F.2d at 1343. Like Pepper Burns, I conclude that the mere mention of mailing as a method of service fails to establish that mailing satisfies the statutory prerequisite to “give” notice. To find otherwise would not provide for the level of certainty that the legislation was intended to give to prime contractors and is a reasonable construction which allows the Little Miller Act to effect its remedial purpose. Accordingly, this Court finds that notice is “given” when the contractor receives notice from the claimant.

Having determined that the Little Miller Act requires notice to be delivered, the inquiry shifts to when delivery occurred in this case. Defendants contend that Archer Western received notice on October 24, 2014, two days after the ninety day period. To date, the only evidence offered to establish the date of delivery, consists of a United States Postal Service “Product Tracking Information” report attached as Exhibit A to Defendants’ Motion for Summary Judgment.

RTA contends that the issue of when delivery occurred remains in dispute because it has not pleaded or admitted that delivery occurred on October 24, 2014. Additionally, RTA argues that the Court cannot grant summary judgment based on Exhibit A because it is not a stipulated document, not admitted to, not made a part of the pleadings, and is otherwise not in evidence.

In Virginia, “[a]ny party may make a motion for summary judgment at any time after the parties are at issue.” Va. Sup. Ct. R. 3:20. The Court may only grant summary judgment if the moving party is entitled to judgment and there are no material facts genuinely in dispute. When making this determination, it must be apparent from “the pleadings, the orders, if any, made at a pretrial conference, [or] the admissions, if any, in the proceedings.” Va. Sup. Ct. R. 3:20.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Boynton v. Kilgore
623 S.E.2d 922 (Supreme Court of Virginia, 2006)
Cook v. Com.
597 S.E.2d 84 (Supreme Court of Virginia, 2004)
Leeman v. Troutman Builds, Inc.
530 S.E.2d 909 (Supreme Court of Virginia, 2000)
Murphy v. Holiday Inns, Inc.
219 S.E.2d 874 (Supreme Court of Virginia, 1975)
George Robberecht Seafood, Inc. v. Maitland Bros.
255 S.E.2d 682 (Supreme Court of Virginia, 1979)
Brown v. Lukhard
330 S.E.2d 84 (Supreme Court of Virginia, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
90 Va. Cir. 240, 2015 Va. Cir. LEXIS 153, Counsel Stack Legal Research, https://law.counselstack.com/opinion/r-t-atkison-building-corp-v-archer-western-construction-llc-vaccnorfolk-2015.