R. S. Noonan, Inc. v. Morrison-Knudsen Co.

522 F. Supp. 1186, 1981 U.S. Dist. LEXIS 14916
CourtDistrict Court, E.D. Louisiana
DecidedOctober 2, 1981
DocketCiv. A. 80-2280, 80-2281
StatusPublished
Cited by1 cases

This text of 522 F. Supp. 1186 (R. S. Noonan, Inc. v. Morrison-Knudsen Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R. S. Noonan, Inc. v. Morrison-Knudsen Co., 522 F. Supp. 1186, 1981 U.S. Dist. LEXIS 14916 (E.D. La. 1981).

Opinion

FINDINGS OF FACT, CONCLUSIONS OF LAW AND DAMAGES

BEER, District Judge.

To the extent any of the following findings of fact constitute conclusions of law, they are adopted as such. To the extent any conclusions of law constitute findings of fact, they are so adopted.

Findings of Fact

1. Plaintiff, R. S. Noonan, Inc. (hereinafter, “Noonan”), is a Pennsylvania corporation having its principal place of business in that state.

2. Defendant, General Motors Corporation (hereinafter, “GM”), is a Delaware corporation having its principal place of business in Michigan.

3. Defendant, Morrison-Knudsen Company, Inc. (hereinafter, “M-K”), is a Delaware corporation having its principal place of business in Idaho.

4. Defendant, Potashnick Construction, Inc. (hereinafter, “Potashnick”), is a Missouri corporation having its principal place of business in that state.

*1188 5. GM is a party to this action in two capacities. On the one hand, GM’s Assembly Division (GMAD) was the “owner” for whom a major assembly facility, which forms the basis of this action, was constructed in Shreveport, Louisiana. At the same time, GM’s Engineering and Construction (PE&C) division served as architect/engineer for the project. GMAD, as owner, had direct control of all project expenditures and entertained, approved and disapproved all contract awards and change order expenditures executed by its agent, M-K. PE&C, as project arehitect/engineer, designed the entire assembly facility, drafted the project specifications and developed the bid packages which were ultimately put out for bidding by its agent, M-K. Both entities maintained a full on-site staff which participated in the daily operations on the project, including administrative decisions concerning scheduling, site preparation, access, laydown, parking and various expenditures as well as design-related problems, changes and ongoing work.

6. GM, through GMAD, contracted with M-K in August, 1977, for the latter to act as construction manager for the assembly facility. Pursuant to this contract, M-K was to coordinate with and advise PE&C with respect to various aspects of the design phase. In addition to reviewing the design of PE&C, M-K was to draft proposed bidder lists for GM, solicit bidders for GM, prepare bid packages, conduct preaward investigations and orientations and, thereafter, award contracts as agent for GM. Additionally, M-K obligated itself to devise a work schedule to be included in each of GM’s bid packages and contracts. Finally, throughout performance, M-K acted as an intermediary between GM and the many contractors involved in the project to ensure communication between them.

7. Between June and September, 1978, Noonan entered into four agreements to perform certain portions of the work necessary to construct GM’s assembly plant. In the first agreement, Noonan contracted with M-K to perform the Phase-I Structural Concrete bid package (Contract No. 2843-09). Pursuant to this contract, Noonan was to form and pour floor slabs and footers, interior and exterior walls and grade beams, piers, walls, pits and trenches and trainwells as specified. The bulk of the Phase-I Structural Concrete work was performed in the “plenum” area. Additionally, Noonan was required to perform fine grading and backfill operations attendant to the performance of the structural concrete work.

8. In Noonan’s second agreement to perform work at the GM facility, Noonan contracted with M-K to perform the Phase-II Structural Concrete bid package (Contract No. 2843-20). This work basically consisted of structural concrete work in the upper level of the plenum including the upper slab of the paint plenum and the exhaust and sludge building portions of the plant.

9. Noonan’s third agreement stems from a significant contract which was awarded to Potashnick for site concrete work at the GM plant. Potashnick, in turn, subcontracted with Noonan to provide labor and materials for certain portions of the work required by Potashnick’s site concrete contract. Pursuant to its subcontract, Noonan was to form and pour site concrete roadways, curbs, gutters, headwalls, light standards and concrete for the construction of the retention pond. Noonan was also to form and pour drainage and interceptor basin structures as well as junction chambers where the storm drains were to tie together.

10. Noonan’s fourth agreement was entered into with M-K to perform the Powerhouse Foundation Work bid package (Contract No. 2843-43). Noonan’s work, pursuant to this contract, encompassed the performance of foundation work under the piping bridge connecting the powerhouse to the main building as well as foundations for circular tanks and utility trenches with attendant underground mechanical and electrical work for the Powerhouse Waste Treatment Building and tank area. Additionally, Noonan was required to pour the slab on grade at the Powerhouse.

*1189 11. As an important part of each of the above described contracts, defendants M-K and GM included a “milestone” schedule setting forth dates on which various segments of each contract were to be undertaken and, thereafter, completed. When Noonan bid and contracted for these three contracts and one subcontract, it was informed that work areas would be made available on dates set forth in the contract milestone schedules in such manner as to permit Noonan to meet the milestone dates using the labor force and equipment and construction methods mutually contemplated.

12. The first Noonan project, Phase I, was scheduled to begin in the beginning of June, 1978, but actually was begun by Noonan in the end of June, 1978. Thereafter, problems were encountered that prevented Noonan from completing its work according to schedule.

13. Commencing in November, 1978, and lasting until May, 1979, the project site was subjected to unprecedented rainfall. In the aggregate for the months involved, the rainfall was approximately 45% over the norm. There were eighty “rain days” instead of the normal sixty-two; fifty-three inches of rain fell instead of the expected thirty inches.

14. The abnormal weather during this seven-month period inevitably impeded the performance of Noonan’s outdoor, sub-ground and ground level work which involved moving workers and materials over the site, excavating, pouring concrete, building' and connecting drainage systems and completing the myriad of other tasks essential to its part of the construction of a major industrial plant. However, the severe weather was only one of several factors which combined to impede Noonan’s progress on each of its four projects.

15. A second contributing factor was that the 400-acre site upon which the GM assembly plant was situated was, in its natural configuration, relatively flat land with almost no natural slope. As a result of cut and fill operations undertaken by Potash-nick, the site was, according to plan, rendered even more completely flat and, for all practical purposes, had no natural drainage.

16. Defendants did not provide a satisfactory temporary drainage system to remove surface water from the site.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Opinion Number
Louisiana Attorney General Reports, 2008

Cite This Page — Counsel Stack

Bluebook (online)
522 F. Supp. 1186, 1981 U.S. Dist. LEXIS 14916, Counsel Stack Legal Research, https://law.counselstack.com/opinion/r-s-noonan-inc-v-morrison-knudsen-co-laed-1981.