R. P. Farnsworth & Co. v. Continental Marble Co.

276 F. Supp. 349, 1967 U.S. Dist. LEXIS 8524
CourtDistrict Court, D. Puerto Rico
DecidedNovember 1, 1967
DocketNo. Civ. 359-66
StatusPublished

This text of 276 F. Supp. 349 (R. P. Farnsworth & Co. v. Continental Marble Co.) is published on Counsel Stack Legal Research, covering District Court, D. Puerto Rico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R. P. Farnsworth & Co. v. Continental Marble Co., 276 F. Supp. 349, 1967 U.S. Dist. LEXIS 8524 (prd 1967).

Opinion

FINDINGS OF FACTS AND CONCLUSIONS OF LAW

CANCIO, Chief Judge.

This cause came to be tried before this court, sitting without a Jury, the trial starting on July 31, 1967, and ending on [350]*350August 14, 1967. Sidney S. Allen, Esq. of the New York Bar, admitted by courtesy for the purposes of this ease, represented plaintiff; Iván Díaz de Aldrey, Esq., a member of the Bar of this Court, represented defendant The Continental Marble Co., Inc.; and Alvaro R. Calderón, Jr., Esq., also a member of the Bar of this Court, represented defendant Great American Insurance Co.

Various stipulations were entered into by the parties and submitted to the Court, which approved them, covering amendments of pleadings, waiver of causes of action, admission of evidence, etc., the most important of which, for the purposes of these Findings and Conclusions, are the following:

1.- Plaintiff waived and withdrew that part of its claim related to general and special damages for alleged loss to its business reputation and profits.

2- Defendant The Continental Marble Co., Inc. (hereinafter referred to as Continental Marble) waived and withdrew that part of its counter-claim included under paragraph 3 of the same, except interest for failure to make payment on time.

3.- Defendant Continental Marble limited that part of its counter-claim covered under paragraph 1 of the same to the — $25,646.20 admitted by plaintiff, plus the $486.80 of its charge for extra thickness in the exposed aggregate.

4- The active participation by the attorney for Great American Insurance Co. in all the aspects of the trial was without prejudice to the right of said Great American Insurance Co. to contend, as it contends, that the bond issued by it does not cover the work performed under Change Order No. 6 and any claims arising thereunder.

5.- The Court could reserve its rulings on the admissibility of certain documentary evidence until such time as all the witnesses for the proponent finished testifying, memoranda on the question of law of the admissibility of said evidence was submitted, and the Court was ready to hand down Judgment, it being further stipulated that if any ruling on the admissibility of such documentary evidence was contrary to the offering party, such party expressly waived its right to present other evidence in lieu thereof.

Memoranda have been filed and the Court, upon consideration of all the pleadings, the evidence, the said Stipulations and the said Memoranda, being fully appraised in the premises, makes its

FINDINGS OF FACT

1- Plaintiff is a corporation organized under the laws of Delaware with principal place of business in New York.

2- Defendant Continental Marble is a corporation organized under the laws of Puerto Rico and has its principal office in Puerto Rico.

3.- Defendant Great American Insurance Co. is a corporation organized under the laws of New York with principal place of business in New York.

4- The amount in controversy exceeds the sum of $3,000.00.

5. - Plaintiff and defendant Continental Marble entered into a contract, dated August 28, 1962, whereby plaintiff, as main or prime contractor of the Puerto Rico Sheraton Hotel in San Juan, Puerto Rico, sub-contracted with Continental Marble the terrazzo and marble portions of the work covered under the plans and specifications of the main construction contract, all of which were made a part of said sub-contract by reference.

6. - Defendant Great American Insurance Co. executed a Performance and Payment Bond, dated February 27, 1963, (which had been printed by plaintiff as part of said sub-contract) binding the obligees therein, defendants herein, as to the performance of said sub-contract and all duly authorized modifications to the said sub-contract that were thereafter made, notice of which modifications to the surety was waived by the latter, defendant Great American Insurance Co.

7. - Said sub-contract provided, among other things, that the ■ “sub-con[351]*351tractor shall pay contractor the sum of $3,000 as liquidated damages and not as a penalty for each and every day that sub-contractor delays the job.”

8. - Ten Change-Orders, numbered 1 to 10 were issued by plaintiff and accepted by defendant Continental Marble. Nine of these Change Orders (all except No. 6) modified the sub-contract. Change Order No. 6 added to the subcontract, which had covered the marble and terrazzo work at the hotel, the construction of the exposed aggregate areas around the pool, cabañas, and certain other walks and outside areas near the main hotel structure.

9. - The Puerto Rico Sheraton Hotel was inaugurated and opened for business during the first days of October, 1963.

10. - The hotel had not been formally accepted by the owner by that time, however, and certain work of completion and correction still had to be performed by plaintiff, including work not covered by the sub-contract with defendant Continental Marble.

11- By the end of May 1964, all the corrective and completion work had been performed by plaintiff or its sub-contractors, except that a certain problem had arisen with respect to the exposed aggregate, to which reference is made hereinafter in these findings.

12- Excluding the problem of the exposed aggregate, defendant Continental Marble was not involved in any delay which might have occurred in the final acceptance of the project after May 1964. The only other items pending at this date were so minor and inconsequential that Mr. Pablo Lugo, engineer in charge for Passalacqua & Cía., the owner’s project manager, who appeared as a witness for plaintiff, testified that he would have recommended acceptance of the hotel at this time if it had not been for the problem of the exposed aggregate.

13.- Plaintiff became involved in a controversy with the owner (for reasons not pertinent hereto), the hotel was never formally accepted, a suit was filed in this court by plaintiff against the owner and the case (Civil No. 390-64) was finally settled out of court.

14- By reason of the said controversy, and its out-of-court settlement, there is no final acceptance date for this contract.

15. - The stones in some of the exposed aggregate surfaces of the Puerto Rico Sheraton Hotel started to come loose shortly after the hotel was inaugurated early in October of 1963.

16. - The court finds that this deterioration of the exposed aggregate surfaces was the direct and foreseeable result of the manner in which these areas were cleaned with hydrochloric acid by plaintiff to remove cement and other materials which other trades had spilled. Although the court need not, and does not, conclude that cleaning of exposed aggregate with hydróchloric acid is per se improper, it finds, from the testimony of the expert witnesses for both sides (whose testimony is not fundamentally contradictory) and from all the other evidence submitted, that extreme care must be exercised whenever an acid solution of hydrochloric acid is brought into contact with concrete or exposed aggregate surfaces, and that this must be done under carefully controlled conditions if no damage is to be suffered by such surfaces.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Palmer v. Hoffman
318 U.S. 109 (Supreme Court, 1943)
Masterson v. Pennsylvania R. Co
182 F.2d 793 (Third Circuit, 1950)
Pekelis v. Transcontinental & Western Air, Inc.
187 F.2d 122 (Second Circuit, 1951)
Gerard Hartzog v. United States
217 F.2d 706 (Fourth Circuit, 1954)
Standard Oil Company of California v. Moore
251 F.2d 188 (Ninth Circuit, 1958)
Archibald Lyles v. United States
254 F.2d 725 (D.C. Circuit, 1958)
Clyde O. Williams v. National Surety Corporation
257 F.2d 771 (Fifth Circuit, 1958)
United States v. Martin
167 F. Supp. 301 (N.D. Illinois, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
276 F. Supp. 349, 1967 U.S. Dist. LEXIS 8524, Counsel Stack Legal Research, https://law.counselstack.com/opinion/r-p-farnsworth-co-v-continental-marble-co-prd-1967.