R. E. Dailey & Co. v. Department of State Highways

188 N.W.2d 89, 31 Mich. App. 518, 1971 Mich. App. LEXIS 2115
CourtMichigan Court of Appeals
DecidedMarch 23, 1971
DocketDocket 8406
StatusPublished

This text of 188 N.W.2d 89 (R. E. Dailey & Co. v. Department of State Highways) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R. E. Dailey & Co. v. Department of State Highways, 188 N.W.2d 89, 31 Mich. App. 518, 1971 Mich. App. LEXIS 2115 (Mich. Ct. App. 1971).

Opinion

Bronson, J.

Plaintiff and defendant entered into a contract for the purpose of constructing a highrise bridge, approximately three miles in length, over the Rouge River in Wayne County.

During the construction period certain disputes arose between the parties relating to the methods of attaching and suspending forms in which to pour and hold the concrete while it hardened (Count I); liability for a 2,169.3 cubic yard overrun in concrete (Count II); liability for the replacement of a damaged portion of the bridge (Count III); liability for the payment of sums required by the contract for *521 the protection of railroad operations and crossings (Count IV); and liability for damages caused by delay resulting from an alleged “strike” of certain of defendant’s employees (Count V).

Plaintiff filed a complaint containing the above counts with the Court of Claims. Following receipt of defendant’s answer, plaintiff moved for a summary judgment, alleging that no genuine issue of material fact existed and that plaintiff was entitled to prevail on each count as a matter of law. Defendant filed written objections to plaintiff’s motion on the grounds that while no material issue of fact existed as to Counts I and II, defendant, not plaintiff, was entitled to prevail as a matter of law on Counts I and II. Defendant further contended that genuine issues of fact existed as to Counts III, IV, and V. The Court of Claims granted plaintiff’s motion for summary judgment on all five counts. The amount of the judgment for plaintiff totaled over $581,000. Defendant’s motion to set aside the summary judgment and order a new trial was denied. Defendant appeals as of right.

Count I of the plaintiff’s complaint alleged that plaintiff was entitled to $411,033 in additional compensation because plaintiff was required to perform “extra work” which was not included in the parties’ contract. Defendant does not question the monetary value placed on the work performed by plaintiff. Rather, it is defendant’s contention that the work was required by the contract and thus did not constitute “extra work” which would entitle the plaintiff to extra compensation. Both plaintiff and defendant agreed no material dispute of fact exists with respect to the issue presented under Count I of plaintiff’s complaint.

The issue of extra compensation arose with respect to the method to be employed in building *522 and suspending forms which hold the poured concrete while it hardens. The written document executed between the parties incorporated by reference the Michigan State Highway Department Standard Specifications (MSHD Specs). The MSHD Specs, in its section regarding electric arc welding, incorporated by reference the American Welding Society Specifications (AWS Specs) of 1963. Herein lies the problem.

It is admitted that at the time the written document was executed on May 19, 1965, it was the custom in the bridge construction industry in Michigan to attach the support form to the bridge by means of a certain welding process. It is further admitted that both parties, at the time the contract was executed, intended that existing custom he followed with respect to the welding process. The plaintiff submitted its bid and entered into the contract with the defendant intending that the general industry practice be followed with respect to welding procedures. The defendant, until March 1966, treated the welding process performed by plaintiff as being in compliance with the parties’ contract. The defendant was aware that the practice of the industry was being followed, observed the welding, raised no objections to it, and considered the welding to be satisfactory and acceptable. However, apparently unknown to either party, the AWS Specs, which had been incorporated into the parties’ written document, had been changed to require a new and different process of attaching the forms.

In March 1966, defendant was informed by the Federal government that the welding was not being performed in accordance with the AWS Specs. The defendant then informed plaintiff that the previously accepted method of welding the forms to the *523 permanent structural steel of the bridge had to be changed and that the welding would have to be performed in accordance with the AWS Specs. The new method, which admittedly was not within the intent of either the plaintiff or defendant at the time the parties executed the written document, required plaintiff to perform extra work. Plaintiff performed the work and promptly filed notice of its claim, alleging that defendant was liable for the work in the amount of $411,033. Plaintiff’s claim in Count I did not request damages for rewelding, but merely for the extra work and expense required by the changed welding procedure.

Defendant, in the action below, did not challenge the value amount placed on plaintiff’s services, nor did defendant contend that any factual controversy existed with respect to Count I. Rather, defendant contended that it, rather than plaintiff, should have been granted a summary judgment because the work performed by plaintiff had been required by the written document. That is, the work performed by plaintiff in welding the forms in accordance with the AWS Specs did not constitute extra work, but rather constituted work required by the express terms of the parties’ written contract, which incorporated by reference the AWS Specs.

These uncontroverted facts present a situation in which the parties intended to enter into a contract for the construction of a bridge, but in which the written instrument, in part, varied from the intent of the parties. The variance was material and related to the welding procedure to be followed. As such, that portion of the written instrument requiring welding in accordance with the AWS Specs did not constitute the real contract of the parties because it did not express that on which the minds of the parties had met:

*524 “A writing is not a contract when it fails to express that on which the minds of the parties met, and courts freely exercise the power to correct mistakes when the proof leaves no doubt that the real contract was something else. A mistake of expression occurs where the parties are of the same mind regarding the terms of the agreement, but the writing intended to embrace those terms does not express their true meaning. * * * ” 17 CJS, Contracts, § 142, p 888.

Since the written document did not express the intention of the parties with respect to the welding procedure, and since both parties intended that the welding procedure would be done in accordance with the custom then used in the trade, the trial court could legally reform the instrument to comply with the parties’ intent. The mere fact that neither party sought to have the written instrument reformed does not bar this remedy:

“ * # * [I]n jurisdictions in which the distinctions between law and equity are abolished, or in which both forms of relief are administered by the same court, in an action at law upon an instrument the court may in a proper case construe the contract as it was intended by the parties, or supply matters omitted either by mutual mistake or fraud, and render a proper judgment on the basis thereof, just as if there had been first a reformation of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Beardsley v. R. J. Manning Co.
139 N.W.2d 129 (Michigan Court of Appeals, 1966)
Bielski v. Wolverine Insurance
150 N.W.2d 788 (Michigan Supreme Court, 1967)
W. H. Knapp Co. v. State Highway Department
18 N.W.2d 421 (Michigan Supreme Court, 1945)
Hersey Gravel Co. v. State Highway Department
9 N.W.2d 567 (Michigan Supreme Court, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
188 N.W.2d 89, 31 Mich. App. 518, 1971 Mich. App. LEXIS 2115, Counsel Stack Legal Research, https://law.counselstack.com/opinion/r-e-dailey-co-v-department-of-state-highways-michctapp-1971.