R & D Contracting, L.L.C. v. Jenkins Construction, Inc. (In re R & D Contracting, L.L.C.)

383 B.R. 890, 2008 Bankr. LEXIS 969
CourtUnited States Bankruptcy Court, E.D. Michigan
DecidedApril 7, 2008
DocketBankruptcy No. 02-43540; Adversary Pro. No. 02-5127
StatusPublished
Cited by1 cases

This text of 383 B.R. 890 (R & D Contracting, L.L.C. v. Jenkins Construction, Inc. (In re R & D Contracting, L.L.C.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R & D Contracting, L.L.C. v. Jenkins Construction, Inc. (In re R & D Contracting, L.L.C.), 383 B.R. 890, 2008 Bankr. LEXIS 969 (Mich. 2008).

Opinion

AMENDED TRIAL OPINION

THOMAS J. TUCKER, Bankruptcy Judge.

In this adversary proceeding, Plaintiff R & D Contracting, L.L.C. (“R & D”) seeks to recover from Defendant Jenkins Construction, Inc. (“Jenkins”) a total of $157,408.87 for work, materials, and the rental of certain equipment by R & D relating to two construction projects. R & D is the debtor in the related chapter 11 bankruptcy case (No. 02-43540). It brings this adversary proceeding under authority granted to it by the confirmed plan of liquidation in the Chapter 11 case.1 The Court conducted a five and one-half day bench trial. This opinion states the Court’s findings of fact and conclusions of law.

For the reasons stated in this Opinion, the Court finds for R & D in part, and [893]*893against R & D in part, on its claims, and will enter judgment for R & D in the total amount of $92,264.37 plus interest.

1. Jurisdiction and venue

The Court has subject matter jurisdiction under 28 U.S.C. § 1334(b) and 28 U.S.C. § 157(a), and the United States District Court’s Local Rule 83.50(a) (E.D.M.). The parties correctly agree that, at a minimum, this proceeding is “related to” the R & D Chapter 11 bankruptcy case within the meaning of 28 U.S.C. § 1334(b) and 28 U.S.C. § 157(a). It is unnecessary to determine whether this is a core proceeding under 28 U.S.C. §§ 157(b) and 157(c). To the extent this is not a core proceeding, the parties have consented to the bankruptcy judge entering final judgment under 28 U.S.C. § 157(c)(2).2

Venue is proper under 28 U.S.C. § 1409(a), and is not disputed.

II. Discussion

R & D’s claims relate to two construction projects, which this opinion will refer to as the “MDOT” project and the “Greater Grace” project.3

A. R & D’s claims relating to the MDOT project

The MDOT project involved the construction of two buildings for the Michigan Department of Transportation (“MDOT”) on Interstate 94 in Port Huron Township, Michigan. Defendant Jenkins was the general contractor hired by MDOT for the project, which included construction of a salt storage building and another building to house an office and a garage/maintenance facility, as well as installation of on/off ramps, a parking lot, and related landscaping.4 Jenkins hired a number of subcontractors to work on the project, including R & D.

The subcontract between Jenkins and R & D was a written contract entitled “Subcontract Agreement” dated September 19, 2000.5 The Subcontract stated that R & D was to “perform certain labor and furnish certain material for the erection and completion of Sitework [i]n accordance with specifications prepared by: D.L.Z. [of South Bend, Indiana, the “Architect”].” The Subcontract further described the “Sitework” to be done as:

1. Complete all earthwork, grading and balancing in strict accordance to Drawings and Specifications.
2. Work is to include all cut and fill necessary to meet subgrade elevations noted and required at all areas.
3. Complete all erosion control as required.
4. Provide all equipment and labor necessary to complete work.
5. Clean up and remove all debris caused by your work.6

The Subcontract incorporated certain “Contract Documents” and further defined the scope of R & D’s work by reference to [894]*894specific drawings and specifications, including:

M.D.O.T. Drawings Sheets 1-5 dated May 5, 2000
D.L.Z. Drawings dated June 13, 2000 Specifications dated for Bid August 4, 20007

Jenkins agreed to pay R & D the sum of $85,000.00 for its work under the Subcontract.8

The parties stipulated that during the course of the MDOT project, “Jenkins requested R & D perform additional work which included providing and installing all stone required for a temporary road on the project, including grading. A change order was issued for this work in the amount of $26,541.42.”9 The change order brought the total Subcontract price to $111,541.42. The parties stipulated that of this amount, Jenkins paid R & D a total of $98,839.85,10 leaving an unpaid amount of $12,701.57.11

R & D makes four different claims for sums owing by Jenkins relating to the MDOT project. These are (1) the unpaid $12,701.57 contract balance just described; (2) $29,760.00 to compensate R & D for certain “equipment stand down time” that R & D suffered during the project; (3) $17,463.50 for extra work R & D claims it did, outside the scope of the Subcontract, on an agreed time-and-material basis, for moving topsoil, and doing certain grading and installation of certain “swales” on the job site; and (4) $40,500.00 for removal by R & D of excess topsoil.

This opinion will discuss each of these claims separately.

1. R & D’s claim for the $12,701.57 unpaid balance under the Subcontract

As noted above, and as the parties stipulated, Jenkins issued a written change order amending the Subcontract, for R & D to perform additional work, including providing and installing stone required for a temporary road and related grading. The change order increased the total Subcontract price from $85,000.00 to $111,541.42.

This change order was dated June 18, 2001,12 and was the only written change order Jenkins issued for R & D under the Subcontract. The change order states that the work added was “as required and directed by Bryan Ritter.” Ritter was the project superintendent for R & D on the MDOT project until December 2000, when he left the project.13 The extra work added by this change order was actually done by R & D several months before the change order was issued.

Because the parties also stipulated that Jenkins paid R & D a total of $98,839.85 for the MDOT project, it is undisputed that there is an unpaid balance of $12,701.57 under the Subcontract. The only defense that Jenkins asserts to this claim is that R & D did not properly complete all of its work under the Subcontract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JAY CASHMAN, INC. v. Portland Pipe Line Corp.
559 F. Supp. 2d 85 (D. Maine, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
383 B.R. 890, 2008 Bankr. LEXIS 969, Counsel Stack Legal Research, https://law.counselstack.com/opinion/r-d-contracting-llc-v-jenkins-construction-inc-in-re-r-d-mieb-2008.