R. C. Mahon Co. v. Hedrich Construction Co.

230 N.W.2d 621, 69 Wis. 2d 456, 1975 Wisc. LEXIS 1540
CourtWisconsin Supreme Court
DecidedJune 30, 1975
Docket22
StatusPublished
Cited by3 cases

This text of 230 N.W.2d 621 (R. C. Mahon Co. v. Hedrich Construction Co.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R. C. Mahon Co. v. Hedrich Construction Co., 230 N.W.2d 621, 69 Wis. 2d 456, 1975 Wisc. LEXIS 1540 (Wis. 1975).

Opinion

Wilkie, C. J.

This is an action on a payment bond by a supplier of a subcontractor brought against the prime contractor and the surety. We affirm the trial court’s determination that the plaintiff-appellant is barred from recovery because it failed to give notice of its claims as required by the terms of the bond.

Defendant-respondent Hedrich Construction Company was the prime contractor engaged to construct an office building by the General Telephone Company. To insure payment to “every person” for “all the claims for labor performed, and materials furnished,” and to eliminate statutory lien rights, Hedrich gave a payment bond as allowed under sec. 289.035 (1), Stats. Architectural Wall Systems, Inc., subcontracted to furnish and install metal sidewall panels for the building. In turn, Mahon supplied the panels to Wall. Hedrich paid Wall for the materials and services, but Wall became insolvent and never paid plaintiff. Plaintiff then commenced this action upon the payment bond, against Hedrich and the bond’s issuer, defendant-respondent Fidelity & Deposit Company of Maryland, seeking $23,567.44, the unpaid balance due on its contract with Wall.

The Private Improvement Labor and Material Payment Bond, secured by Hedrich, provided, in pertinent part:

*459 “NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that, if Principal [Hedrich] shall promptly make payment to all persons entitled thereto for all claims for labor performed and materials furnished to the Principal or any of his subcontractors under the Contract, and subsequent amendments thereto, to be used or consumed in making the improvement or performing the work of improvement as provided in the Contract, and subsequent amendments thereto, then this obligation shall be void; otherwise it shall remain in full force and effect, subject, however, to the following conditions:
“3) Any claimant who is in a contractual relationship with a subcontractor of the Principal but not in such relationship with the Principal shall within 90 days from the day he last performed any labor or furnished any material give notice of his claim by registered mail, return receipt requested, addressed to the Owner and to the Principal at their addresses stated herein.
“4) Any party in interest may, not later than one year after the completion of the contract, maintain an action in his own name against the Principal and the Surety upon this bond for the recovery of any damages he has sustained by reason of the breach of the Condition of this bond. If the amount of this bond is insufficient to satisfy all of the claims of the parties in full, it shall be distributed among the parties pro rata.”

Two issues are involved on this appeal:

I. Is the plaintiff-appellant a “party in interest” statutorily entitled by sec. 289.035 (2), Stats., to sue on a payment bond?

II. Is the ninety-day notice provision contained in the bond void, for conflicting with sec. 289.035 (2), Stats., giving any “party in interest” one year after final completion of the contract in which to sue?

Is plaintiff-appellant a “party in interest”?

Under sec. 289.03 (2), Stats., where a prime contractor on a private construction project furnishes a payment bond, construction lien rights except those of the prime *460 contractor himself, are eliminated. 1 The nature of the bond and of the prime contractor’s obligations are specified in sec. 289.035 (1), which provides in part:

“(1) To eliminate lien rights as provided in s. 289.03 (2), the contract between the owner and the prime contractor for the construction of the improvement shall contain a provision for the payment by the prime contractor of all claims for labor performed and materials or plans or specifications furnished, used or consumed, . . . in making such improvement and performing the work of improvement. The contract shall not be effective to eliminate lien rights unless the prime contractor gives a bond issued by a surety company licensed to do business in this state. The bond shall carry a penalty for unpaid claims of not less than the contract price, and shall be conditioned for the payment to every person entitled thereto of all the claims for labor performed, and materials furnished under the contract and subsequent amendments thereto, to be used or consumed in making the improvement or performing the work of improvement as provided in the contract and subsequent amendments thereto. . . .”

Sec. 289.035 (2), which governs who may sue on the payment bond, provides in part as follows:

“(2) Any party in interest may, not later than one year after the completion of the contract, maintain an action in his own name against the prime contractor and the sureties upon the bond for the recovery of any damages he has sustained by reason of the failure of the prime contractor to comply with the contract or with the contract between the prime contractor and subcontractors. . . .”

*461 The question is: Is the plaintiff-appellant here a “party in interest” entitled to sue Hedrich, the prime contractor, and the surety, by virtue of Hedrich’s alleged failure to comply with its contractual obligation to pay “all claims for . . . materials . . . furnished, used or consumed ... in making such improvement and performing the work of improvement” ? We conclude that plaintiff-appellant Mahon is such a party in interest entitled to maintain this action.

As the court indicated in Gilson Bros. Co. v. Worden-Allen Co. 2 the question of whether a person is entitled as a party in interest to sue on a payment bond depends upon whether that person would have a statutory lien in the absence of the bond. Clearly Mahon, as supplier of materials used in the construction of the building, would be entitled to such a lien under sec. 289.01 (3), Stats., which provides in part:

“Extent and character of lien. Every person who performs any work or procures its performance or furnishes any labor or materials or plans or specifications for the improvement of land . . . shall have a lien therefor on all interests in the land belonging to its owners. . . .” 3

*462 Moreover, plaintiff’s claim here falls squarely within Hedrieh’s obligation under sec. 289.035 to pay “all claims for . . . materials . . . furnished, used or consumed.”

Defendant Hedrich contends that plaintiff is not statutorily entitled to sue on the bond for two reasons: (a) Plaintiff has lien rights under sec. 289.036, Stats., which, Hedrich argues, are exclusive; and (b) in the recent decision of Peabody Seating Co. v. Jim Cullen, Inc., 4 this court held a supplier of materials to a subcontractor for use in a public construction project unable, under the relevant statute, to sue on a payment bond.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

H. H. Robertson Co. v. Lumbermen's Mutual Casualty Co.
94 F.R.D. 578 (W.D. Pennsylvania, 1982)
Ladwig v. Ermanco Inc.
504 F. Supp. 1229 (E.D. Wisconsin, 1981)
Western Cas. and Sur. Co. v. Honeywell, Inc.
380 So. 2d 1385 (Mississippi Supreme Court, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
230 N.W.2d 621, 69 Wis. 2d 456, 1975 Wisc. LEXIS 1540, Counsel Stack Legal Research, https://law.counselstack.com/opinion/r-c-mahon-co-v-hedrich-construction-co-wis-1975.