R & B FALCON CORP. v. American Exploration Co.

154 F. Supp. 2d 969, 2001 WL 844864
CourtDistrict Court, S.D. Texas
DecidedJanuary 26, 2001
DocketCiv.A. H-99-0580
StatusPublished
Cited by6 cases

This text of 154 F. Supp. 2d 969 (R & B FALCON CORP. v. American Exploration Co.) is published on Counsel Stack Legal Research, covering District Court, S.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R & B FALCON CORP. v. American Exploration Co., 154 F. Supp. 2d 969, 2001 WL 844864 (S.D. Tex. 2001).

Opinion

AMENDED ORDER

GILMORE, District Judge.

Pending before the Court is Defendants’ Motion for Summary Judgment. (Instrument No. 20). Based on the submissions of the parties and the applicable law, the Court finds that the motion should be GRANTED.

I.

Plaintiff R & B Falcon Drilling Co. Cfrk/a Reading & Bates Drilling Co.) (“R & B”) brings this action against Defendants American Exploration Company (“American Exploration”) and its successor-in-interest, Louis Dreyfus Gas Production Corporation (“Louis Dreyfus”) 1 pursuant to the Outer Continental Shelf Lands Act (“OCSLA”), 43 U.S.C. § 1331 et seq., for breach of contract.

Plaintiff entered into a contract on May 5, 1997 with AGIP Petroleum Company, Inc. (“AGIP”) to provide offshore drilling services. AGIP assigned the drilling contract to Louis Dreyfus in late June 1997 to perform operations offshore Louisiana in the vicinity of East Cameron Block 328, in which Louis Dreyfus owns an interest. The contract contained a force majeure clause that required the payment of day rates for the services of R & B’s drilling *971 unit, regardless of delays or damage that occurred as a result of “act[s] of God” or were “reasonably beyond the control” of the party seeking to be excused from performance. (Contract, Instrument No. 21, Exh A at ¶ 1303).

On July 1, 1997, as the drilling unit was being moved into place, it suffered damage to its hull and legs. The following day, R & B wrote to Louis Dreyfus informing them of the difficulties, characterizing the damage as a “force majeure event.” Despite investigations and studies, no one knows what caused the damage to the drilling unit, though experts have suggested that anomalies in the seabed or a mechanical failure in the jacking system may have been responsible. (Bill Ellis Dep., Instrument No. 21, Exh F at 18; Report of Donald Remson, Instrument No. 21, Exh D; Report of W.J. Wilkinson, Instrument No. 22, Exh A at 14). R & B invoiced Louis Dreyfus for the day rate, but did not receive payment. Plaintiff placed liens on East Cameron Block 328.

R & B filed this action on February 24, 1999, alleging that Defendants had breached the contract by failing to pay according to the terms of the force majeure clause. (First Amended Complaint, Instrument No. 4).

Defendants filed a counterclaim on April 29, 1999, alleging that when R & B moved the drilling unit into position, it improperly deployed one of the legs, causing damage to the unit. (Instrument No. 5 at 6). Louis Dreyfus contends that the damage was caused by R & B and was not, therefore, a force majeure event. (Id). As a result, Louis Dreyfus asserts that it did not breach the contract because it was not required to pay the day rate while the drilling unit was undergoing repairs. Louis Dreyfus seeks removal of the liens Plaintiff placed on East Cameron Block 328 on the grounds that “an actual controversy now exists between the parties.” (Id. at 7).

On March 1, 2000, Defendants filed this motion for summary judgment, arguing that they are entitled to judgment as a matter of law on Plaintiffs claim as well as on their counterclaim. (Instrument No. 20). Defendants argue that Plaintiff cannot demonstrate that the damage to the unit occurred as a result of an “act of God” or was “beyond [its] control” and therefore, cannot recover based on application of the force majeure clause. While Plaintiff and its experts candidly admit that they do not know what caused the leg of the rig to bow, Defendants contend that there is no evidence that whatever the anomaly was, it cannot be proven to fall within the force majeure parameters. Because it was R & B’s responsibility under the contract to take samples of the seabed if necessary, Defendants argue that any anomaly in the seabed was not outside R & B’s control. In short, Defendants maintain that they are entitled to summary judgment because in order to recover, R & B must demonstrate what happened to the rig. Because they cannot, Defendants argue, the force majeure clause cannot possibly apply.

Plaintiff filed a response on March 21, 2000, arguing that the differing interpretations of the contract and the cause of the accident preclude summary judgment. (Instrument No. 22). Plaintiff argues that in addition to the force majeure clause, it alleges that Louis Dreyfus breached ¶ 606 of the contract by failing to notify R & B of any faulty bottom conditions and failing to provide R & B with soil and sea bottom surveys. The Court notes that this is the first time Plaintiff has raised this argument.

Defendants filed a reply on April 4, 2000, arguing that a dispute as to the meaning of a contract is a matter of law *972 for the court to decide. (Instrument No. 25). Defendants also argue that for purposes of summary judgment, they accept Plaintiffs contention that an anomaly in the sea bed caused the damage to the rig. Finally, Defendants argue that their alleged failure to provide information on the site is not a force majeure event and that the new claim for breach would violate ¶ 909 of the contract which bars recovery for “special, indirect or consequential damages.”

II.

Summary judgment is appropriate if no genuine issue of material fact exists and the moving party is entitled to judgment as a matter of law. Fed.R.CivP. 56. A fact is “material” if its resolution in favor of one party might affect the outcome of the suit under governing law. See Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 106 S.Ct. 2505, 2510, 91 L.Ed.2d 202 (1986); see also United States v. Arron, 954 F.2d 249, 251 (5th Cir.1992). An issue is “genuine” if the evidence is sufficient for a reasonable jury to return a verdict for the nonmoving party. See Anderson, 106 S.Ct. at 2510. If the evidence rebutting the motion for summary judgment is only colorable or not significantly probative, summary judgment should be granted. Id., at 2511; see also Thomas v. Baiion Lodge, Ltd., 174 F.3d 636, 644 (5th Cir.1999). The summary judgment procedure, therefore, enables a party “who believes there is no genuine issue as to a specific fact essential to the other side’s case to demand at least one sworn averment of that [specific] fact before the lengthy process continues.” See Lujan v. National Wildlife Federation, 497 U.S. 871, 110 S.Ct. 3177, 3189-89, 111 L.Ed.2d 695 (1990).

Under Fed.R.Civ.P. 56

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
154 F. Supp. 2d 969, 2001 WL 844864, Counsel Stack Legal Research, https://law.counselstack.com/opinion/r-b-falcon-corp-v-american-exploration-co-txsd-2001.