R. B. Brunemann & Sons, Inc. v. Duke University

533 F. Supp. 365, 1982 U.S. Dist. LEXIS 10901
CourtDistrict Court, M.D. North Carolina
DecidedFebruary 23, 1982
DocketNo. C-81-136-D
StatusPublished

This text of 533 F. Supp. 365 (R. B. Brunemann & Sons, Inc. v. Duke University) is published on Counsel Stack Legal Research, covering District Court, M.D. North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R. B. Brunemann & Sons, Inc. v. Duke University, 533 F. Supp. 365, 1982 U.S. Dist. LEXIS 10901 (M.D.N.C. 1982).

Opinion

MEMORANDUM OPINION

ERWIN, District Judge.

This matter came before the court on December 3, 1981, United States Courthouse, Durham, upon the motion of respondent-plaintiff Duke University to remand this action to the state court (Superior Court of Durham County). The court having carefully considered all pleadings, documents, arguments of counsel, briefs, and supplemental briefs holds that it must abstain.

Respondent-plaintiff Duke University and petitioner-defendant Brunemann entered into a contract dated August 6, 1976 under which Brunemann agreed to fabricate and construct the stucco wall panel system and plaster for the Duke Hospital North in Durham, North Carolina for a contract price of $1,150,000. Duke University contracted directly with approximately fifty separate prime contractors who were each responsible for the construction of a portion of the project. Because the project was bid in portions as the design was completed, there was no single general contractor responsible for the entire building. The work of the many separate contractors was supervised and coordinated by a construction manager. Under this system, each contractor was responsible for the construction of its part of the project and contracted directly with all necessary subcontractors and had direct control over all facets of its work.

It is undisputed that at all times pertinent to its contract with Duke, Brunemann was not licensed in compliance with Article I of Chapter 87 of the North Carolina General Statutes. In April 1979, Brunemann filed a claim under its construction contract with Duke University for damages in excess of $1,000,000; this claim was submitted to the project architect and denied. In November 1979, Brunemann filed a claim for $1,500,000 with the American Arbitration Association. At Brunemann’s request, the arbitration was held in abeyance until March 1981.

In March 1981, Duke University filed a complaint and a motion for stay of arbitration in the Superior Court of Durham County, North Carolina. Duke University’s suit in the Durham County Superior Court re[367]*367quested the court to stay arbitration pursuant to N.C.Gen.Stat. § 1-567.3 (Supp.1981) because Brunemann was not licensed under N.C.Gen.Stat. §§ 87-1 to 87-15.2 (1981 & Supp.). In its answer to Duke University’s complaint, Brunemann contended that it was not required to be licensed under N.C. Gen.Stat. § 87-1 (Supp.1981), that Duke was estopped to assert the licensing statute as a defense to Brunemann’s claim, and that enforcement of the licensing statute against Brunemann would violate Brunemann’s due process rights under the Fourteenth Amendment to the Constitution of the United States.

Brunemann removed the action to this United States District Court, and Duke University filed a motion to remand on the ground, among others, that the federal court should abstain since the case involved unresolved and difficult issues of state law relating to state policies of substantial public import. The issue before the court is whether abstention is warranted on the grounds asserted by respondent-plaintiff Duke University.

Chapter 87 of the North Carolina General Statutes is a regulatory statute enacted to regulate the construction industry and to protect the general public from incompetent builders. Bryan Builders Supply v. Midyette, 274 N.C. 264, 162 S.E.2d 507 (1968). The North Carolina courts have held that when an unlicensed person contracts for construction costing more than the minimum sums specified in the statute, he may not recover for the owner’s breach of that contract, nor may he recover on a quasi-contractual theory. Id.; Ar-Con Construction Co. v. Anderson, 5 N.C.App. 12, 168 S.E.2d 18 (1969). The courts have also held that the statute does not require a subcontractor to be licensed, ruling that the public does not need to be protected from a subcontractor because the general contractor stands between the owner and the subcontractor. Vogel v. Reed Supply Co., 277 N.C. 119, 177 S.E.2d 273 (1970).

Although the statute has been extensively litigated, the courts of North Carolina have not addressed the precise issue involved in this case, i.e., whether a parallel prime contractor who contracts directly with a property owner to build a substantial portion of a new building is required to be licensed as a general contractor,1 nor have the state courts yet dealt with the estoppel defense asserted by Brunemann; prior cases do not clearly indicate how the North Carolina courts would decide either of these issues. Therefore, the interpretation given to the state regulatory statute in this case will have far-reaching consequences which transcend the instant results.

Under the abstention doctrine, a United States District Court has the discretion to refuse to exercise its jurisdiction even when subject matter jurisdiction is proper. Burford v. Sun Oil Co., 319 U.S. 315, 63 S.Ct. 1098, 87 L.Ed. 1424 (1943). The leading case on abstention is Railroad Commission of Texas v. Pullman, 312 U.S. 496, 61 S.Ct. 643, 85 L.Ed. 971 (1941). In Pullman, the United States District Court enjoined enforcement of a Texas Railroad Commission order after it was challenged as unauthorized under Texas law and in violation of the equal protection, due process, and commerce clauses of the United States [368]*368Constitution. On appeal, the United States Supreme Court reversed and ordered the district court to stay its injunction pending state court proceedings to determine the validity of the Railroad Commission’s order. In support of its decision to abstain, the Court noted that abstention by the district court would “avoid the waste of a tentative decision as well as the friction of a premature constitutional adjudication.” Id. at 500. In Colorado River Water Conservation District v. United States, 424 U.S. 800, 96 S.Ct. 1236, 47 L.Ed.2d 483 (1975), the Court reaffirmed the necessity for the United States District Courts’ abstention in at least two circumstances: (1) where a federal constitutional issue might be mooted or presented in a different posture by a state court determination of pertinent state law; and (2) where a case presents difficult questions of state law bearing on policy problems of substantial public import. Id. at 814, 96 S.Ct. at 1244.

In Louisiana Power and Light Co. v. Thibodaux, 360 U.S. 25, 79 S.Ct. 1070, 3 L.Ed.2d 1058 (1959), Justice Frankfurter wrote as follows:

We have increasingly recognized the wisdom of staying actions in the federal courts pending determination by a state court of decisive issues of state law. . . . On the other hand, we have held that the mere difficulty of state law does not justify a federal court’s relinquishment of jurisdiction in favor of state court action. Meredith v. Winter Haven, 320 U.S. 228, 236 [64 S.Ct. 7, 88 L.Ed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Railroad Comm'n of Tex. v. Pullman Co.
312 U.S. 496 (Supreme Court, 1941)
Chicago v. Fieldcrest Dairies, Inc.
316 U.S. 168 (Supreme Court, 1942)
Burford v. Sun Oil Co.
319 U.S. 315 (Supreme Court, 1943)
Meredith v. Winter Haven
320 U.S. 228 (Supreme Court, 1943)
Leiter Minerals, Inc. v. United States
352 U.S. 220 (Supreme Court, 1957)
Louisiana Power & Light Co. v. City of Thibodaux
360 U.S. 25 (Supreme Court, 1959)
Kaiser Steel Corp. v. W. S. Ranch Co.
391 U.S. 593 (Supreme Court, 1968)
Harris County Commissioners Court v. Moore
420 U.S. 77 (Supreme Court, 1975)
AR-CON CONSTRUCTION COMPANY v. Anderson
168 S.E.2d 18 (Court of Appeals of North Carolina, 1969)
Bryan Builders Supply v. Midyette
162 S.E.2d 507 (Supreme Court of North Carolina, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
533 F. Supp. 365, 1982 U.S. Dist. LEXIS 10901, Counsel Stack Legal Research, https://law.counselstack.com/opinion/r-b-brunemann-sons-inc-v-duke-university-ncmd-1982.