R. A. Brown & Co. v. Board of Supervisors
This text of 129 Iowa 533 (R. A. Brown & Co. v. Board of Supervisors) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
It appears that certain proceedings ■ were had for the location and construction of a public ditch in Harrison and Pottawattamie counties, under the provisions of Code, section 1939 et seq., and that plaintiff’s bid for a portion of the work was accepted. But, before any actual work had been done by plaintiff in performance of its con[535]*535tract, doubts arose as to the validity of the proceeding, and no further steps were taken by plaintiff to carry out the undertaking, until in August, 1905. In the meantime new proceedings had been instituted in the respective counties, under Acts 30th General Assembly, chapter 68, in pursuance of which bids were received and contracts made for the construction of a ditch intended to drain substantially the same territory, but not entirely corresponding with the former proposed ditch, being larger' in size and to be constructed through portions of its course on other lines than those specified in the first proceeding. Before the contracts for the new ditch were let, plaintiff protested willingness to proceed under the contract for the first ditch, and asked directions as to the construction of the proposed new ditch, and demanded that it be allowed to construct a portion of that ditch under the terms of its contract. This protest not being regarded by the respective boards, plaintiff made a bid in competition with others for constructing the new ditch, and, upon the awarding of this contract to another, plaintiff instituted this action to enjoin the defendants from proceeding with the construction of the ditch under the new contract and to, compel them to carry out the original contract with plaintiff.
It is contended, however, for the plaintiff, that, by mutual understanding between him and the respective boards of supervisors, the performance of1 the work was to be postponed until the validity of the first proceeding and the constitutionality of the law should be determined. It appears from the testimony that there was doubt on both sides as to the validity of the proceedings, and that representatives of the plaintiff had conversations and correspondence' with the county auditors and members of the boards of supervisors as to whether plaintiff should proceed. But there was no objection on the part of defendants to the carrying out of the contract by plaintiff, and the sole question was whether plaintiff was likely as a matter of law to be able to get the money which he was to have for his work. The defendants interposed no obstacle to the performance of the work, and we think that plaintiff must be held to have acted at its peril in postponing the performance until after the time for performance had expired. Indeed plaintiff seems to have abandoned, for more than a year prior to the institution of the new proceeding, any idea of performing the contract, and, only after the decision in Ross v. Board of Supervisors of Wright County, 128 Iowa, 427, was handed down by this court, in which it was held that proceedings already commenced under the provisions of the Code might be continued under the provisions of Acts 30th General Assembly, page 59, chapter 67, by complying with the requirements of the new statute^ did plaintiff entertain any idea that he had a contract which might be specifically enforced. Plaintiff was not a party to any action with regard to the validity of the proceedings first instituted for the construction of a ditch, nor was he enjoined by any action from carrying out his contract. The county officers, and members of the boards of supervisors with whom plaintiff conferred and corresponded had no authority to set [537]*537aside plaintiff’s contract or release kirn from tlie performance thereof. It is provided in the contract that:
The contractor shall not be entitled to any claim for hindrance or delay from any cause whatever in the progress of the work or any portion thereof, but such hindrance may entitle the contractor to an extension of time for the completion of this contract sufficient to compensate for the detention; the same to be determined by the boards of supervisors of the several counties, provided that immediate notice of said cause of detention be served on the said boards of supervisors.
No notice of any cause of detention was given by plaintiff to the boards of supervisors or either of them, and no extension of time was granted. It is to be borne in mind that plaintiff’s failure to carry out his contract was not attributable to any fault or omission of the defendants. Nothing which defendants were to do under the contract prior to its performance by plaintiff was omitted to be done. The simple fact is that plaintiff thought the proceeding to be illegal and his contract unenforcible, and for that reason failed to perform. It cannot now ask equitable relief on the theory that, if it had performed, the contract would have been enforceable as against defendants.
[538]*538
We reach the conclusion that plaintiff was not entitled to any relief, and the decree of the lower court is- affirmed.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
129 Iowa 533, Counsel Stack Legal Research, https://law.counselstack.com/opinion/r-a-brown-co-v-board-of-supervisors-iowa-1906.