Quirk v. Data Terminal Systems, Inc.

475 N.E.2d 1208, 394 Mass. 334, 1985 Mass. LEXIS 1391
CourtMassachusetts Supreme Judicial Court
DecidedMarch 25, 1985
StatusPublished
Cited by8 cases

This text of 475 N.E.2d 1208 (Quirk v. Data Terminal Systems, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Quirk v. Data Terminal Systems, Inc., 475 N.E.2d 1208, 394 Mass. 334, 1985 Mass. LEXIS 1391 (Mass. 1985).

Opinion

Lynch, J.

A judge of the Superior Court granted the defendant’s motion to correct an alleged clerical error in an arbitration award, and confirmed the award as corrected. The plaintiffs appealed to the Appeals Court, which reversed and dismissed the motion to correct the award because it was made more than thirty days after the award was filed. Quirk v. Data Terminal Syss., 18 Mass. App. Ct. 1104(1984). SeeG. L. c. 251, § 13. We granted further appellate review to consider the sole issue raised on appeal: whether the judge erred under G. L. c. 251, § 13, in correcting the arbitration award where the motion was made more than thirty days after the award was filed. The defendant contends that no error was made because the judge has the power under G. L. c. 251 and under [335]*335Mass. R. Civ. P. 60 (a), 365 Mass. 828 (1974), to correct a clerical error in the award, even if the motion is made more than thirty days after the award is filed. We reverse the order of the Superior Court.

This dispute over interpretation of the arbitration award has arisen out of an ongoing controversy between the parties concerning their respective duties under a contract entered into in October, 1976, and amended in April, 1977. The contract provided that Robert D. Quirk, and Bruce T. Quirk, trustee of the Robert Quirk Realty Trust (hereinafter collectively referred to as the trust), would convey certain land to Data Terminal Systems, Inc. (Data); that the trust would construct a building on the land; and that, if it completed construction by a specified date, the trust would have the option to repurchase the property at a price to be determined by a formula in the contract. Data would then lease the property back from the trust at a rent to be calculated according to another formula in the contract. The contract also contained an arbitration provision which stated, “All claims, disputes and other matters in question arising out of, or relating to, this Contract or the breach thereof. . . shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise.”

The trust failed to complete construction by the date provided for in the contract, so Data dismissed the trust as building contractor and assumed the responsibility for completion of the building. Data began to occupy the building on May 1, 1979. In the meantime, the trust commenced arbitration proceedings and later brought suit in the Superior Court claiming fraud in the inducement of the contract. In Quirk v. Data Terminal Syss., 379 Mass. 762, 768 (1980), we ordered that the parties’ claims be submitted to arbitration. The contract provided, “The award rendered by the arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof.”

On September 14, 1982, the arbitrators delivered their award, which states that it is “full settlement of all claims and [336]*336counterclaims submitted to this arbitration.” The arbitrators retained jurisdiction, however, “to administer the award through the Closing of the repurchase of the site, if the same takes place.” New disputes have since arisen between the parties concerning their respective obligations under the arbitrators’ award. On January 7, 1983, the trust filed a motion to file a substitute complaint for a jury trial following submission of the arbitration award, which was granted on March 29, 1983. On January 26, 1983, Data filed a motion to correct a clerical error in the arbitration award. The following day, the trust filed a motion for confirmation of the award. On March 23, 1983, Data filed a motion for an order compelling arbitration of the new disputes between the parties. On March 29, the judge denied Data’s motion for an order compelling arbitration, and allowed Data’s motion to correct the award. On March 30, he confirmed the award as corrected. Pursuant to G. L. c. 251, § 18, the trust appealed the judge’s rulings on the motion to correct the award to the Appeals Court. On May 9,1984, the Appeals Court issued an order reversing the judge’s ruling confirming the award as corrected. The Appeals Court directed (1) that the defendant’s motion to correct the award be dismissed on the ground that it was not timely filed, and (2) that the judge confirm the arbitration award without any correction.

The trust argues on appeal that the judge erred under G. L. c. 251, §§ 11 and 13, in modifying the arbitration award to correct a clerical error. General Laws c. 251, § 11, inserted by St. 1960, c. 374, § 1, provides, “Upon application of a party, the court shall confirm an award, unless within the time limits hereinafter imposed grounds are urged for vacating or modifying or correcting the award, in which case the court shall proceed as provided in sections twelve and thirteen” (emphasis added). Section 13 provides grounds for modifying an award and states, in relevant part, “(o) Upon application made within thirty days after delivery of a copy of the award to the applicant, the court shall modify or correct the award if: (1) there was ... an evident mistake in the description of any person, thing or property referred to in the award; ...(b) If the [337]*337application is granted, the court shall modify and correct the award so as to effect its intent and shall confirm the award as so modified and corrected; otherwise, the court shall confirm the award as made” (emphasis added). G. L. c. 251, § 13, as amended by St. 1972, c. 200, § 2.

Data filed its motion on January 26, 1983, to correct a clerical error in the arbitration award. Data made the motion more than 120 days after the arbitrators delivered their award on September 14, 1982. On January 27, 1983, the trust filed a motion for confirmation of the award. Whether the judge erred in allowing Data’s motion to correct the award and in confirming the award as corrected depends upon interpretation of the time limitation in G. L. c. 251, § 13, and its relationship to Mass. R. Civ. P. 60 (a).

Data argues that the judge properly allowed its motion because there is an “evident mistake” in paragraph 3(e) of the arbitrators’ award, which describes the formula according to which the monthly rental is to be calculated in the event that the trust repurchases the property and leases it back to Data. Paragraph 3(e) provides a two-part formula for calculating the monthly rental: “[it] shall be the sum of (i) the regular principal and interest payments on the mortgage indebtedness on the Site assumed by the Purchaser, and (ii) an amount equal to l/12th of 11% of the difference between the option purchase price computed as set forth in Paragraph 48 of the Findings [of Fact and Conclusions of Law] and the principal amount of the mortgage indebtedness assumed by the Purchaser at the Closing . . . (emphasis added).” Data contends that the option purchase price is in fact computed in paragraphs 48 and 50 of the findings, not just in paragraph 48. Data argues that under paragraph 50, $291,133 is deducted from the option purchase price set forth in paragraph 48. According to Data’s calculations, it would pay an additional annual rental of 11% of $291,133, which would achieve a result inconsistent with the parties’ original agreement and with the arbitrators’ ruling in paragraph 49 of their findings. Paragraph 49 also describes the monthly rental formula, but makes no reference to the para[338]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nationwide Mutual Ins. v. Liberty Mutual Ins.
57 F. Supp. 3d 112 (D. Massachusetts, 2014)
Heritage Construction & Development, Inc. v. O'Connor
25 Mass. L. Rptr. 1 (Massachusetts Superior Court, 2008)
Reynolds v. Whitman
663 N.E.2d 867 (Massachusetts Appeals Court, 1996)
Loche v. Dean Witter Reynolds, Inc.
526 N.E.2d 1296 (Massachusetts Appeals Court, 1988)
Ciampa v. Chubb Group of Insurance Companies
525 N.E.2d 1344 (Massachusetts Appeals Court, 1988)
Karbowski v. Resnic, Beauregard, Waite & Driscoll
1987 Mass. App. Div. 19 (Mass. Dist. Ct., App. Div., 1987)
Westwood Group, Inc. v. City of Revere
502 N.E.2d 1387 (Massachusetts Supreme Judicial Court, 1987)
Marino v. Tagaris
480 N.E.2d 286 (Massachusetts Supreme Judicial Court, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
475 N.E.2d 1208, 394 Mass. 334, 1985 Mass. LEXIS 1391, Counsel Stack Legal Research, https://law.counselstack.com/opinion/quirk-v-data-terminal-systems-inc-mass-1985.