Quinn v. Wilkerson

195 S.W.2d 399, 1946 Tex. App. LEXIS 916
CourtCourt of Appeals of Texas
DecidedMay 31, 1946
DocketNo. 14765.
StatusPublished
Cited by14 cases

This text of 195 S.W.2d 399 (Quinn v. Wilkerson) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Quinn v. Wilkerson, 195 S.W.2d 399, 1946 Tex. App. LEXIS 916 (Tex. Ct. App. 1946).

Opinions

Appellant Quinn was the general contractor on a federal housing project in McAlester, Oklahoma. By a written contract Quinn sublet a part of the work to appellees Wilkerson and Pettijohn. This suit is based in part on a count for an alleged balance due the subcontractors under their written contract, and in part on a quantum meruit count for an additional amount alleged to be due for other work done in addition to that performed under the written subcontract. Quinn set up certain claims by way of offset. The issues on appeal are narrowed to three items, the nature of which will appear from this opinion.

In the quantum meruit count appellees claimed that appellant requested them to move certain rock which had been excavated on the project, that the amount of rock so moved was 1166 yards, and that the reasonable value of moving the rock was $3 per yard. The jury verdict is favorable to appellees on this claim.

Under the first point of error appellant contends that the trial court erred in overruling appellant's special exception and motion to strike directed at the paragraph of appellees' petition setting out the quantum meruit count for recovery for moving the 1166 yards of rock above referred to. Two contentions are presented under the point of error.

The substance of the first contention is that the allegations of the quantum meruit count did not give appellant notice of the relief sought or the proof necessary to meet the allegations, in that they did not state the date or dates on which the alleged services were performed, but merely stated that the rock was moved at the request of appellant, on or about February 15, 1944, and that they did not show the dates when the rock was moved, or by whom, or in what quantities, and were too uncertain and indefinite to give appellant such notice as would enable him to prepare his defense.

Appellant first attacked the sufficiency of the allegations in question in his first amended original answer. In a supplemental petition appellees alleged that they moved the rock, beginning about February 15, 1944, and at various times thereafter until August of that year, that they moved it from the site described in the contract between appellant and appellees, and that they bulk of the rock came from the trenches dug for the foundations for the houses on the site, and a small amount from the plumber's excavations under the houses, and from holes dug by the electricians. Under our present rules of pleading, we believe that the allegations in question were sufficient to give appellant fair notice of the claim. Texas Rules of Civil Procedure, rules 45, 47. And even if the petition might have been more in detail, we can find from the record as a whole no indication that the paucity of appellees' pleadings was such as was reasonably calculated to cause or did cause any harm to appellant. Rule 434.

The other contention made under this point of error relates to an allegation in appellees' pleadings that appellant was paid the sum of $9.50 per yard by the Federal Government for the rock removed by appellees. It is claimed that the allegation was immaterial to any issue in the case, that it was highly inflammatory, and that it was prejudicial to appellant's defense. It seems to us that the allegation was material, in that it had some bearing on the question of whether or not the parties contemplated that appellant should pay appellees for removing the rock that was not covered by the written subcontract. In determining whether such was the case, it was proper to take into consideration the fact that appellant as the general contractor was paid by the Federal Government for the *Page 402 removal of such rock. The allegation tended to show that appellant received benefit from the work done at his special instance and request by appellees, and that, in good conscience, he should pay appellees for the reasonable value of their work. Tramonte v. A. J. Rasmussen Sons, Inc., Tex. Civ. App. 167 S.W.2d 566.

According to appellees, they were requested to move the rock by Mr. Paschal, appellant's superintendent. Appellant contends that there is no proof of the superintendent's authority to request appellees to move the rock. Without discussing the evidence in detail, we overrule the contention, because it is plain from the evidence in the record that Paschal was the general superintendent on the job, that appellant was required by his contract with the Government to keep a general superintendent on the job, and that Paschal had at least implied authority to request appellees to haul this rock. Viewed in the light favorable to the verdict, the testimony showed that the rock in question needed to be moved in order that appellees could proceed with the work required of them under their subcontract, that they asked the superintendent to move the rock out of their way, that he told them that he did not have the equipment required to move the rock, and that he requested appellees to move it. Quinn was away from the project some of the time, and the evidence is amply sufficient to show that Paschal had at least enough general authority as superintendent to order the removal of the rock so that the work of the project could go forward.

Appellant next charges error in admitting oral evidence that the removal of the rock referred to in the quantum meruit count was work done outside of the written contract. The substance of the complaint seems to be that oral evidence was thus admitted to construe the written contract. We do not so consider the evidence in question. To our minds it is clear that the removal of this rock was not something required by the written contract. The real battle in the trial court was over the question of whether appellees did or did not move this particular rock. It is evident from the record that both parties understood that such was the issue between them. Appellees testified that they were requested by the superintendent to move the rock and that they did so. The superintendent denied that he made any such request of appellees, and denied that appellees moved this particular rock, maintaining throughout that the rock was moved by Quinn, the general contractor. The oral evidence of removal of rock outside of the contract was admissible by way of identifying the rock in question from other rock which appellees were required to remove under the terms of their written subcontract.

Under the fourth point appellant urges that error was committed in permitting appellees to testify that they would not have moved the rock if they had not believed that they would be paid therefor. Bearing in mind that appellees were seeking to recover on a theory of quantum meruit, it seems to us that it was material to inquire whether they did the work with the expectation of being paid, else it might be thought that they did the work gratuitously.

Under the fifth point appellant complains of the testimony of appellees that moving the rock was worth $3 per yard. The complaint is based on the contention that appellees admitted that they did not know how much was moved, or what distance any particular amount was moved, or how much was moved by any particular means. We overrule the contention. When the testimony is examined as a whole, it appears that the estimate of value of the services was based on the average of the whole amount moved. Appellees were both experienced contractors, and any objection to the testimony would go to its weight rather than to its admissibility. Furthermore, this matter was not assigned as error in the motion for new trial, and cannot now be relied on as error.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nora Swafford v. Dick Avakian
581 F.2d 1224 (Fifth Circuit, 1978)
Stanfield v. Butler
475 S.W.2d 838 (Court of Appeals of Texas, 1971)
Electric Wire & Cable Co. v. Ray
456 S.W.2d 260 (Court of Appeals of Texas, 1970)
Gulf Coast Operators, Inc. v. Fleming Oil Company
393 S.W.2d 954 (Court of Appeals of Texas, 1965)
Royal v. Cameron
382 S.W.2d 335 (Court of Appeals of Texas, 1964)
Puente v. Mata
346 S.W.2d 643 (Court of Appeals of Texas, 1961)
Texas Delta Upsilon Foundation v. Fehr
307 S.W.2d 124 (Court of Appeals of Texas, 1957)
Miller v. Miller
274 S.W.2d 762 (Court of Appeals of Texas, 1955)
Buchanan v. Sinclair Oil & Gas Co.
126 F. Supp. 950 (S.D. Texas, 1953)
Miller v. Watson
257 S.W.2d 839 (Court of Appeals of Texas, 1953)
Liberty Mut. Ins. Co. v. Connell
250 S.W.2d 400 (Court of Appeals of Texas, 1952)
Insurance Co. of North America v. Cangelosi
217 S.W.2d 888 (Court of Appeals of Texas, 1949)
Miller v. Long-Bell Lumber Co.
217 S.W.2d 867 (Court of Appeals of Texas, 1949)
Smock v. Fischel
207 S.W.2d 888 (Court of Appeals of Texas, 1947)

Cite This Page — Counsel Stack

Bluebook (online)
195 S.W.2d 399, 1946 Tex. App. LEXIS 916, Counsel Stack Legal Research, https://law.counselstack.com/opinion/quinn-v-wilkerson-texapp-1946.