Quinn v. Delfour, Inc.

3 Mass. Supp. 409
CourtMassachusetts Superior Court
DecidedMarch 26, 1982
DocketNo. 13056
StatusPublished

This text of 3 Mass. Supp. 409 (Quinn v. Delfour, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Quinn v. Delfour, Inc., 3 Mass. Supp. 409 (Mass. Ct. App. 1982).

Opinion

MEMORANDUM OF DECISION (Including Findings of Fact and Conclusions of Law, Pursuant to Mass. R. Civ. P. 52[a]) I. PROCEDURAL BACKGROUND and HISTORY

This civil action was commenced on March 11, 1976, by the filing of a Complaint. The plaintiff at that time was Roger E. Bombardier, Sr., of Raynham, Massachusetts, doing business under the firm name and style of Middleboro Drywall. Named as defendants were (1) Delfour, Inc. (Delfour), a Massachusetts corporation having an usual place of business in Boston; (2) City of Brockton (City); and (3) Insurance Company of North America (INA).

[410]*410Delfour counterclaimed (p. #5) on May 12, 1976, seeking to join2 an additional party, New Hampshire Insurance Company (New Hampshire), as an object of the counterclaim, as surety for Bombardier. The counterclaim sought damages against both Bombardier and New Hampshire.

Discovery, mainly by interrogatories, ensued.

On July 30, 1980, Bombardier suggested (p. #21) that he had filed in bankruptcy, and that Thomas H. Quinn, Jr., had been appointed as his trustee in bankruptcy. On December 30, 1980, the court (Young, J.) allowed Quinn’s motion (p. #25) to be substituted as plaintiff.

Further discovery, by interrogatories and production of documents, continued.

Finally, on November 5, 1981, the case was reached for trial, without jury, before the undersigned justice. Numerous witnesses, and a large number of exhibits, were heard and received, respectively.

After the trial was concluded, the parties were given -a reasonable time to file requests for findings of fact and conclusions of law, and did so by November 30, 1981.

II.

FINDINGS OF FACT and CONCLUSIONS OF LAW

, Based upon all of the credible evidence, including testimony of witnesses, the exhibits, and stipulations of counsel,3 and the reasonable inferences to be drawn therefrom, giving due effect to «the credibility of the witnesses as determined by the court during trial observation, the court makes the following findings of fact, and rules as a matter of law where indicated:

A. FACTUAL BACKGROUND; EVENTS LEADING TO THE “STOP WORK”ORDER

1. Bombardier is an individual doing business as Middleboro Drywall4 with an usual place of business in Raynham.

2. Quinn is the trustee in bankruptcy for Bombardier under a proceeding in the U.S. District Court for the District of Rhode Island.

3. Delfour is a Massachusetts corporation with a principal place of business in Boston (Dorchester District).

4. New Hampshire is a foreign corporation with an usual place of business in Cambridge.

5. The City is a duly organized municipal corporation.

6. INA is a foreign corporation with an usual place of business in Boston.

7. On March 12, 1975, the City entered into a contract (general contract) with Delfour for the construction and renovation of a project known as the Three Early Learning Centers at the Goddard, Lincoln and Howard Schools in Brockton (the project). Delfour was to act as the general contractor.

8. On March 24, 1975, Delfour entered into three separate subcontracts with Bombardier d/b/a Middleboro Drywall, a filed subbidder on the project. Middleboro was to provide labor, materials and equipment to perform work necessary in accordance with certain sections of the general contract, as follows:

(a) Section 9A of the specifications to the general contract entitled “plastering” in the amount of $6,610.

j (b) Section 9D of the specifications entitled “Acoustical Work” in the amount of $48,357.

(c) Section 9F of the specifications entitled “Drywall” in the amount of $68,890.

[411]*4119. The total cost of the three subcontracts comprehending Sections 9A, 9D, _ and 9F of the general contract was $123,887. The subcontracts incorporated by reference the general contract, which, in turn, included the specifications, various plans, and AIA Form A 201.

10. Under the terms of the three subcontracts Middleboro agreed, inter alia, to be bound to the general contractor, Delfour, by the terms of the plans, specifications, and general conditions, and to assume to the general contractor all the obligations and responsibilities that the general contractor by those documents assumes to the City, except to the extent that provisions contained in them are by their terms or by law applicable only to the general contractor; and to begin, prosecute and complete the work described in the subcontract in an orderly manner and with due consideration to the date or time specified by the awarding authority, the City, for the completion of the entire work, which was October 31, 1975.

11. Delfour required Middleboro to furnish performance and payment bonds for the acoustical and drywall work but not for the plastering work (which was subsequently deleted from the contract). These bonds were furnished and executed by New Hampshire as Middleboro’s surety pursuant to G.L.c. 149, § 44H. The general contract specified that Delfour would pay the premium for the subcontract bonds; however, Delfour failed to pay that premium.

12. With respect to the subcontract covering the plastering, Section 9A of the general contract, Middleboro and Delfour agreed that Delfour would provide the labor and material itself and then backcharge Middleboro for those services. Delfour did provide labor and material under that subcontract and billed Middleboro accordingly, commencing May 30, 1975. Since that section was subsequently deleted from their contractual arrangement with the assent of both Delfour and Middleboro, no claim for damages has been made by. Delfour in connection with that item.

13. Under the general conditions of the general contract, AIA Form A 201, Delfour as general contractor was required to supervise and direct the work as follows:

4.3 Supervision and Construction Procedure
, 4.3.1 The contractor shall supervise and direct the work using his best skill and attention. He shall be solely responsible for all construction means, methods, techniques, sequences and procedures and for coordinating all portions of the work under the contract.

14. The specifications stated in part that the general contractor shall provide weather protection and heat during the months of November through March. Weather protection included protection from moisture and necessitated heating to maintain a minimum temperature for methods of construction, and for the curing of materials.

15.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 39F
Massachusetts § 39F
§ 44H
Massachusetts § 44H

Cite This Page — Counsel Stack

Bluebook (online)
3 Mass. Supp. 409, Counsel Stack Legal Research, https://law.counselstack.com/opinion/quinn-v-delfour-inc-masssuperct-1982.