Quality Heating Supply Co. v. Buckeye Loan & Building Co.

148 N.E.2d 88, 105 Ohio App. 369, 6 Ohio Op. 2d 149, 1957 Ohio App. LEXIS 803
CourtOhio Court of Appeals
DecidedNovember 18, 1957
Docket8330
StatusPublished
Cited by3 cases

This text of 148 N.E.2d 88 (Quality Heating Supply Co. v. Buckeye Loan & Building Co.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Quality Heating Supply Co. v. Buckeye Loan & Building Co., 148 N.E.2d 88, 105 Ohio App. 369, 6 Ohio Op. 2d 149, 1957 Ohio App. LEXIS 803 (Ohio Ct. App. 1957).

Opinion

Matthews, J.

This is an action by a materialman to foreclose a mechanic’s lien upon real estate owned by the defendant. The case comes to this court upon appeal on questions of law and fact from the Common Pleas Court.

*370 The defendant entered into a contract with Miller & Company, on or about February 24, 1954, whereby Miller & Company, in consideration of $20,300, agreed to install air-conditioning equipment in a building owned by the defendant. Payments were to be made “as deliveries are made and work progresses as approved by architect.”

Miller & Company started to furnish and install the equipment, and the defendant, on several occasions in April and May of 1954, made payments on account of the contract price. These payments totaled $14,989.91, and were made without the approval of an architect, and, apparently, without reference to the progress of the work, unless it can be said that the defendant itself made an estimate of the progress before making payments.

The plaintiff furnished material upon an open account to Miller & Company, and made deliveries thereof on the defendant’s premises, and, by October 1954, this account showed about $4,100 due, and at that time the plaintiff submitted a bill for $4,100 to Miller & Company, and Miller & Company gave the plaintiff two checks totaling $4,100. There is evidence that these checks were to be withheld until Miller received payment from the defendant, but, in this connection, it is sufficient to say that the checks were not paid, and while it is contended that these checks constituted payment and precluded a lien, we think it is clear that they were accepted only on condition that they would be honored and not as payment per se. They were given to be used only if- and when the defendant furnished Miller & Company sufficient funds with which Miller & Company could arrange to have the checks honored, and defendant did not supply the funds.

It was apparent by that time that a dispute was developing • between Miller & Company and the defendant as to the extent and quality of the installation. This was brought into the open at a meeting held on or about November 1, 1954, between representatives of the plaintiff, the defendant and Miller & Company. At that meeting, the plaintiff had the unused checks and claimed tha,t the plaintiff had furnished all the material, in which it dealt, necessary to complete Miller & Company’s contract with defendant, and wanted payment.

*371 However, the plaintiff thereafter made deliveries of certain parts of small value, on six different occasions, the last delivery, according to the plaintiff and its books, being made on November 26,1954. There is a dispute as to all these deliveries.

At the meeting of November 1st, Miller & Company contended that it had fully performed, and the defendant contended that Miller & Company had not fully performed. The defendant refused to make any further payments at that time, and the meeting adjourned. Apparently, the defendant still hoped that Miller & Company would complete the installation according to its demands, and, on November 19th — about 18 days after the meeting — the defendant wrote Miller & Company a letter in which it referred to a telephone conversation of the previous day, and in that letter set forth in great detail the respects in which the installation was deficient and expressed the hope that Miller & Company would “complete your work as agreed in your contract * * * in a good and workmanlike manner.” The defendant’s witness testified to the same effect. At a later date, not made specific by the evidence, Miller & Company was either voluntarily or involuntarily in bankruptcy.

As already noted, the plaintiff’s last delivery was on November 26, 1954, and it waited until the sixtieth day thereafter to file its affidavit claiming a lien. The delivery of November 26th is disputed.

Now, what is the evidence on the subject of the delivery of November 26th?

The president of the plaintiff corporation testified that, on November 26th, he received an order from an employee of Miller & Company, who was in charge of the work, to send the items to him on the premises, and that he visited the premises and saw the articles in the basement. The driver of the truck testified that he delivered the items on the premises and took a receipt from Miller & Company’s employee. That receipt was introduced in evidence. The only other evidence on the subject was the testimony of the defendant’s vice-president in charge of this installation. He testified, on direct examination, that no delivery was made on November 26th, and that no deliveries were made after November 1st. However, on cross-examination, he stated that material could have been delivered to the building without his knowledge.

*372 On this evidence we conclude that .the delivery on November 26th has been proven by the preponderance of the evidence, and that the lien affidavit was filed within the time required by law.

But the defendant contends that the amount which it paid to Miller & Company and the cost of completing the installation in accordance with the contract have exhausted the contract price, and that, therefore, there is no fund on which to fasten the lien. On the other hand, the plaintiff contends that even by giving the defendant credit for the cost of completing the air-conditioning of the building in accordance with the contract, there still remains a fund more than sufficient to satisfy the plaintiff’s lien. This claim is postulated on its contention that none of the payments made by defendant were in accordance with the terms of the contract. This claim requires a consideration of the evidence relating to the circumstances under which these payments were made.

It is admitted that the first payment, amounting to $1,900, was made to Miller & Company, the principal contractor, without either a contractor’s affidavit, as required by Section 1311. 04, Revised Code, or an architect’s certificate, and that all other payments were made upon the affidavit of the principal contractor, that in form complied with said section, averring that the amount requested was due, and that there was nothing owing by Miller & Company to any subsequent contractor or materialman, but without the certificate of an architect as to the progress of the work.

As already noted, the contract provided that “payments are to be made as deliveries are made and work progresses as approved by architect.”

Can these payments which were made, either without the architect’s certificate as to the progress of the work or the affidavit of the principal contractor, be charged against the contract to the detriment of the materialman? It is manifest that the defendant made payments to Miller & Company which were not justified by the progress of the work, and that this depletion of the balance due under the contract might have been avoided had the defendant required an architect’s certificate as to the status of the work. The procedure prescribed by Sections 1311. *373

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Plumbing Connection, Inc. v. Kostelnik
430 N.E.2d 1340 (Lake County Court of Common Pleas, 1980)
Berea Block & Supply Co. v. Bridges
178 N.E.2d 844 (Ohio Court of Appeals, 1961)
Ed. A. McCarthy & Sons, Inc. v. Fleming
170 N.E.2d 269 (Ohio Court of Appeals, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
148 N.E.2d 88, 105 Ohio App. 369, 6 Ohio Op. 2d 149, 1957 Ohio App. LEXIS 803, Counsel Stack Legal Research, https://law.counselstack.com/opinion/quality-heating-supply-co-v-buckeye-loan-building-co-ohioctapp-1957.