Quality Design and Construction, Inc. v. Capital Glass Company, Inc.

994 So. 2d 154, 2008 La.App. 1 Cir. 0838, 2008 La. App. Unpub. LEXIS 554, 2008 WL 4869974
CourtLouisiana Court of Appeal
DecidedOctober 31, 2008
Docket2008 CA 0838
StatusPublished

This text of 994 So. 2d 154 (Quality Design and Construction, Inc. v. Capital Glass Company, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Quality Design and Construction, Inc. v. Capital Glass Company, Inc., 994 So. 2d 154, 2008 La.App. 1 Cir. 0838, 2008 La. App. Unpub. LEXIS 554, 2008 WL 4869974 (La. Ct. App. 2008).

Opinion

QUALITY DESIGN AND CONSTRUCTION, INC.
v.
CAPITAL GLASS COMPANY, INC.

No. 2008 CA 0838.

Court of Appeals of Louisiana, First Circuit.

October 31, 2008.
NOT DESIGNATED FOR PUBLICATION

SCOTT E. FRAZIER, CHRISTOPHER R. RUTZEN, Counsel for Plaintiff/Appellee Quality Design and Construction, Inc.

JOHN A. BRUNINI, STEPHEN J. CARMODY, Counsel for Defendant/Appellant Capital Glass Company, Inc.

Before: CARTER, C.J., WHIPPLE and DOWNING, JJ.

WHIPPLE, J.

This matter is before us on appeal by a subcontractor, defendant Capital Glass Company, Inc. ("Capital"), from a trial court judgment awarding the contractor plaintiff Quality Design and Construction, Inc., ("Quality"), damages resulting from Capital's failure to perform its obligations under two agreements. We affirm.

PROCEDURAL HISTORY AND FACTUAL BACKGROUND

Quality was selected as the general contractor on the United States Army Corps of Engineers (the "Corps") construction project known as the J. Bennett Johnston Waterways Regional Visitors Center project in Shreveport (the "Project"). Capital was one of Quality's subcontractors on two separate jobs for the Project. In connection with the construction project, the Corps provided architectural drawings for use by prospective bidders for the general contractor award and by prospective subcontractors in the pre-bidding process and post-award period. During the pre-bidding period, Capital submitted a proposal to Quality to fabricate and install the Project's curtain wall system for a price of $109,900.00, and a separate proposal to fabricate, but not install, the aluminum composite panel wall system for the exterior wall of the Project for a price of $91,300.00

On March 22, 2004, Quality issued a notice to Capital to proceed with the curtain wall system job for the bid price of $109,900.00. Quality also forwarded its standard subcontractor's agreement for the curtain wall system job. However, the parties never executed a written subcontract agreement for the curtain wall system job.

On March 23, 2004, Quality issued a purchase order to Capital to fabricate the panels for $90,300.00, which was $1,000.00 lower than Capital's bid. Before it would begin work on the panel job, Capital required that Quality sign a document containing eleven terms and agreements. On May 5, 2004, Quality's project manager, David Nail, signed the terms-and-conditions document for the panel purchase agreement.

Before fabrication of the component parts of the two jobs could begin, Capital was required to submit complete shop drawings to Quality based on the pre-bid architectural drawings. In turn, Quality would forward the submissions to the Corps for approval.[1] Initially, the parties exchanged general information concerning the Project. Capital also made a request for additional information on the panel job. Soon after, Nail began making weekly calls to his contact at Capital, Robert Hamm, to inquire about Capital's progress on the shop drawings.

Within a few months of entering into the curtain wall agreement and the panel purchase order, conflicts arose between the parties concerning Capital's lack of progress in producing complete shop drawings, Quality's demands for the submissions, Capital's demand for an additional $1,000.00 on the panel-purchase order to comply with Capital's bid price, Capital's refusal to release shop drawings until a revised purchase order was issued, and Capital's demand for an additional $15,000.00 on the panel jobs.

The conflict escalated to the point where Quality denied Capital's request for the $15,000.00 increase on the panel job, and Capital notified Quality that it had stopped production on the shop drawings and would not resume work unless it received the $15,000.00 increase. Quality informed Capital that if it refused to perform for the price on the panel purchase order, Quality would cancel Capital's contracts, find a substitute subcontractor, and sue Capital for any additional costs it incurred.

After the parties exchanged a series of strongly worded letters, Capital relented and agreed to perform for the price listed on the panel purchase agreement. However, Capital required that Quality execute the curtain wall system contract with the contract amendments and exclusions Capital had previously submitted. Quality refused to modify its standard subcontractor agreement. Capital responded that the refusal was problematic and that Capital required the modifications. Quality then cancelled both contracts and entered into its standard subcontractor's agreement with a substitute subcontractor, Ace Glass, Inc. ("Ace"), to perform the curtain wall system and panel jobs.

Thereafter, Quality filed suit against Capital to recover the increased cost incurred by Quality on the two jobs due to Capital's failure to perform its obligations. In response, Capital filed a reconventional demand, seeking to recover lost profits and damages arising out of Quality's wrongful termination of the agreements. After a bench trial, where the trial court issued factual findings, the trial court granted judgment in favor of Quality in the amount of $54,870.00. Capital then filed the instant suspensive appeal.

STANDARDS OF REVIEW

Capital raises six assignments of error through which it asserts that the evidence does not support the trial court's factual findings that Quality was justified in terminating both contracts and that Quality was entitled to damages in the amount of $54,870.00. Alternatively, Capital contends that the trial court's factual findings were interdicted by its legal error in failing to apply an adverse presumption with regard to Quality's alleged disposal of certain evidence.

With regard to the trial court's factual findings, an appellate court cannot reverse factual findings unless it finds both that no reasonable factual basis exists for the finding and that it is manifestly erroneous or clearly wrong. Stobart v. State, through Department of Transportation and Development, 617 So. 2d 880, 882 (La. 1993). Moreover, in applying this standard, a trial court's credibility determinations are entitled to great deference. See State ex rel. Thibodeaux v. State, 2001-2510 (La. 3/8/02), 811 So. 2d 875 (per curiam). If the trial court's findings are reasonable in light of the record reviewed in its entirety, the court of appeal may not reverse. Consequently, where there are two permissible views of the evidence, the factfinder's choice between them cannot be manifestly erroneous or clearly wrong. Marie v. John Deere Insurance Company, 96-1288 (La. App. 1st Cir. 3/27/97), 691 So. 2d 1327, 1333.

With regard to Capital's contention that the trial court committed legal error, we note that if a party is entitled to a legal presumption and the trial court fails to apply the presumption, legal error results. Johnson v. State through Department of Public Safety and Corrections, 95-0003 (La. App. 1st Cir. 10/6/95), 671 So. 2d 454, 457, writ denied, 95-2666 (La. 1/5/96), 667 So. 2d 522. When the legal error interdicts the fact-finding process, the manifest error standard is no longer applicable, and, if the record is otherwise complete, the appellate court must conduct a de novo review of the entire record and determine a preponderance of the evidence. Rhodes v. State through Department of Transportation and Development, 94-1758 (La. App. 1st Cir.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

RIVER CITIES CONSTRUCTION CO, INC. v. Barnard & Burk, Inc.
444 So. 2d 1260 (Louisiana Court of Appeal, 1983)
Stobart v. State Through DOTD
617 So. 2d 880 (Supreme Court of Louisiana, 1993)
Degravelles v. Hampton
652 So. 2d 647 (Louisiana Court of Appeal, 1995)
Johnson v. State
671 So. 2d 454 (Louisiana Court of Appeal, 1995)
Owens v. Robinson
329 So. 2d 766 (Louisiana Court of Appeal, 1976)
Tunnard v. Simply Southern Homes, LLC
985 So. 2d 166 (Louisiana Court of Appeal, 2008)
Marie v. John Deere Ins. Co.
691 So. 2d 1327 (Louisiana Court of Appeal, 1997)
Rhodes v. State Through DOTD
684 So. 2d 1134 (Louisiana Court of Appeal, 1996)
State Ex Rel. Thibodeaux v. State
811 So. 2d 875 (Supreme Court of Louisiana, 2002)
Robison v. Jarreau
452 So. 2d 1271 (Louisiana Court of Appeal, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
994 So. 2d 154, 2008 La.App. 1 Cir. 0838, 2008 La. App. Unpub. LEXIS 554, 2008 WL 4869974, Counsel Stack Legal Research, https://law.counselstack.com/opinion/quality-design-and-construction-inc-v-capital-glas-lactapp-2008.