Quail Ridge Associates v. Chemical Bank

185 A.D.2d 522, 586 N.Y.S.2d 155, 1992 N.Y. App. Div. LEXIS 8976
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJuly 16, 1992
StatusPublished
Cited by2 cases

This text of 185 A.D.2d 522 (Quail Ridge Associates v. Chemical Bank) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Quail Ridge Associates v. Chemical Bank, 185 A.D.2d 522, 586 N.Y.S.2d 155, 1992 N.Y. App. Div. LEXIS 8976 (N.Y. Ct. App. 1992).

Opinion

Crew III, J.

Appeals (transferred to this court by order of the Appellate Division, Second Department) (1) from an order of the Supreme Court (Dickinson, J.), entered June 25, 1991 in Putnam County, which denied defendant’s motion for summary judgment dismissing the complaint and on its counterclaims, and (2) from an order of said court, entered September 6, 1991 in Putnam County, which, inter alia, upon reconsideration, adhered to its prior decision.

On September 18, 1987 plaintiff and defendant entered into an agreement whereby defendant agreed to loan plaintiff $22.3 million to finance plaintiff’s acquisition and development of real property for a condominium complex located in the Town of Kent, Putnam County. In furtherance of the loan, the parties executed a building loan agreement (hereinafter BLA) which prescribed the terms under which money would be advanced to plaintiff. Central to the determination of this appeal is paragraph 10 of the BLA, which provides that defendant is not obligated to make any advance on the loan if, in its sole opinion, the balance of the loan yet to be advanced is, at any time, less than the actual sum which would be required to complete construction. The difference between the amount yet to be advanced and the actual amount needed to complete the project is defined as the "deficiency”, which was to be determined by estimation of the lender and the inspecting engineer. In the event of a deficiency, plaintiff was afforded 10 days to cure the same and if it did not do so, defendant was entitled to declare plaintiff in default of the contract.

[523]*523Pursuant to the BLA, Merit & Harris, Inc. was designated by the parties as the inspecting engineer. Thereafter, between September 1987 and May 1988, defendant advanced more than $3.6 million to plaintiff pursuant to the BLA. By letter dated July 19, 1988 plaintiff was advised that it had 10 days to cure a deficiency or defendant would consider it to be in default. Plaintiff objected to the deficiency determination and the parties thereafter debated the existence and the amount of the deficiency through the fall of 1988. After certain contract revisions and further analysis, Merit & Harris, Inc. issued a revised report in which it estimated that there would be a deficiency of more than $2.3 million. On December 14, 1988 defendant notified plaintiff that if the deficiency was not cured by December 31, 1988, defendant would accelerate the loan. On January 10, 1989 defendant declared plaintiff to be in default, accelerated payment of the loan and demanded payment of the outstanding principal plus interest.

Plaintiff commenced this action against defendant for breach of contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

havePower, LLC v. General Electric Co.
256 F. Supp. 2d 402 (D. Maryland, 2003)
State Bank of Chittenango v. Central National Bank
202 A.D.2d 828 (Appellate Division of the Supreme Court of New York, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
185 A.D.2d 522, 586 N.Y.S.2d 155, 1992 N.Y. App. Div. LEXIS 8976, Counsel Stack Legal Research, https://law.counselstack.com/opinion/quail-ridge-associates-v-chemical-bank-nyappdiv-1992.