Quadtek, Inc. v. Foister, Unpublished Decision (8-15-2005)

2005 Ohio 4191
CourtOhio Court of Appeals
DecidedAugust 15, 2005
DocketNo. CA2004-09-112.
StatusUnpublished
Cited by3 cases

This text of 2005 Ohio 4191 (Quadtek, Inc. v. Foister, Unpublished Decision (8-15-2005)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Quadtek, Inc. v. Foister, Unpublished Decision (8-15-2005), 2005 Ohio 4191 (Ohio Ct. App. 2005).

Opinion

OPINION
{¶ 1} Defendant-appellant, Jimmie Foister, appeals a judgment of the Warren County Court, ordering him to pay $12,175, along with interest and court costs, to plaintiff-appellee, Quadtek, Inc., with respect to appellee's breach of contract and unjust enrichment claims.

{¶ 2} In 1994, the parties entered into a written contract, wherein appellee agreed "to remove and dispose of three underground storage tanks" on appellant's property in exchange for appellant's agreeing to pay him $7,100 plus additional, unspecified costs if contaminants were present. Appellee agreed to perform the work in accordance with the Bureau of Underground Storage Tank Regulations ("BUSTR") and Ohio Environmental Protection Agency regulations. Specifically, appellee was obligated to "file permit, perform environmental workup, do soil tests on tank cavity, stockpiles [sic] soil, and along any burried [sic] lines[,] * * * purge tank of liquids, remove sludge, ventilate, and run L.E.L. S [sic] for the state fir [sic] marshal, prepare the B.U.S.T.R. site featuring scoring system and checklist and prepare and file the closure with the state." The contract provided that if "contamination is present[,]" there would be additional charges, including a $65 per ton fee for "contaminated soil disposal." The contract also contained a provision stating that "backfill" was "not included." Appellant was required under the terms of the contract to make a $2,000 down payment on the $7,100 contract price and to pay the "balance upon completion." The contract also contained a provision that stated:

{¶ 3} "Any alteration or deviation from above specifications involving extra costs, will be executed only upon written orders, and will become an extra charge over and above the estimate."

{¶ 4} Appellee proceeded to remove the underground storage tanks and test the surrounding soil; after doing so, it discovered that the soil was contaminated. Appellee proposed to appellant that rather than have the contaminated soil hauled away to a landfill site at $65 per ton as called for under the terms of their contract, they "landfarm" the soil, instead. This procedure involved spreading out the contaminated soil on a sheet of plastic over a certain area of appellant's land, and then planting thistle or grass in the contaminated soil to speed the degradation of its contaminants. Appellant responded to appellee's landfarming proposal by telling him, "that's fine we can do that." Appellant even assisted appellee in landfarming the contaminated soil. Appellee subsequently conducted numerous inspections and soil tests to monitor the degradation of the soil's contaminants. Appellee also hauled in about 350 tons of crushed concrete to fill in the excavated site, at $3 per ton. At one point, appellant asked appellee to test a well on his property for contamination, which appellant did.

{¶ 5} Under the terms of the parties' contract, appellee was obligated to file a "closure report" with the state regarding the steps taken to ameliorate the contaminants created by the underground storage tanks. When the time came to file this report, however, a dispute arose between the parties over the costs associated with the additional work of cleaning up the contamination. As a result of this dispute, appellee refused to file the closure report with the state because appellant "said he wasn't going to pay me[.]" With the statutory deadline for filing the closure report approaching, appellant hired Mike Luessn of ATC Associates to draft the closure report, which Luessn submitted to BUSTR in February 1999. In May 2000, BUSTR issued to appellant a NFA (no further action) letter, thereby indicating that appellant's property was sufficiently in compliance with all applicable regulations. Upon its attorney's advice, appellee eventually submitted a closure report of its own.

{¶ 6} In August 1999, appellee filed a complaint against appellant, arguing that appellant breached their contract, or alternatively, was unjustly enriched to appellee's detriment. Appellee acknowledged that appellant had paid it $6,000 on the contract, but it argued that appellant still owed it an additional $8,150 for the work that it performed as a result of the contaminants it found in appellee's soil. In October 1999, appellant filed an answer and counterclaim, denying appellee's allegations that he had breached the terms of their contract or was unjustly enriched at appellee's expense, and arguing that appellee had breached the terms of their agreement by, among other things, failing to file a complete and timely closure report. Appellant also claimed that appellee failed to perform the agreed upon services in "a reasonable and workmanlike manner." The matter was referred to a magistrate.

{¶ 7} A hearing was held on appellee's claims and appellant's counterclaims on June 13, 2001. On August 22, 2001, the magistrate issued a decision in the matter that stated in relevant part as follows:

{¶ 8} "The court views this matter as one governed by the express terms of the parties' written contract, recognizing that some additional work was contemplated by the parties if certain contingencies were met, although no price term was agreed to with respect to backfill. The court also notes as a threshold matter that [appellee] agreed to perform the contract in exchange for [appellant's] payment of $2,000 on the contract and his promise to pay the balance upon completion of [appellee's] work. It appears that at some point the [appellant] withdrew his promise to pay the balance, or refused a present demand to pay the balance, and that [appellee] therefore refused to complete [its] work. Without reference to which party was the first to breach the contract, the court is disinclined to treat the unpaid work [appellee] did complete as forfeit. Material to deciding this case is whether the surcharges for well analysis, bank financing analysis, contaminated soil disposal, contaminated soil treatment, and backfill are alterations or deviations from specifications contained or contemplated in the contract, and if so, whether they involve extra costs.

{¶ 9} "The surcharges for testing and backfill total $1,525, which the court finds reasonable. The original contract called for hauling away contaminated soil at $65 per ton. As a deviation from that specification, the parties agreed to landfarm the soil at $28 per ton. The court notes that this is a deviation, but not one involving extra costs to those contemplated in the contract. Consequently, the lack of a written change order will not defeat [appellee's] prayer for compensation for disposal. The cost of the excavation and testing operation was $5,050, which the court finds reasonable. The water well testing and financing report were not contemplated in the original contract, and the court finds that they are changes or `extras' without written change orders. The court awards no further compensation for those items.

{¶ 10} "The court finds that [appellee] did not complete some work agreed to, which was subsequently completed by a third party at the cost to [appellant] of $1,500. This third party, Mike Luesson [sic, Luessn] of J.T. Express [sic, ATC Associates],1 testified that the site and the closure are clean, as is also established by BUSTR's `no further action' letter, and that the landfarmed soil is continuing to degrade as expected.

{¶ 11}

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JAG Imperial, L.L.C. v. Literski
2012 Ohio 2863 (Ohio Court of Appeals, 2012)
Torbeck v. Iannelli, Ca2006-10-085 (9-4-2007)
2007 Ohio 4539 (Ohio Court of Appeals, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
2005 Ohio 4191, Counsel Stack Legal Research, https://law.counselstack.com/opinion/quadtek-inc-v-foister-unpublished-decision-8-15-2005-ohioctapp-2005.