Q.G.S. Development, Inc., etc. v. National Lining Systems, Inc., etc.

CourtDistrict Court of Appeal of Florida
DecidedJanuary 31, 2024
Docket2022-0699
StatusPublished

This text of Q.G.S. Development, Inc., etc. v. National Lining Systems, Inc., etc. (Q.G.S. Development, Inc., etc. v. National Lining Systems, Inc., etc.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Q.G.S. Development, Inc., etc. v. National Lining Systems, Inc., etc., (Fla. Ct. App. 2024).

Opinion

Third District Court of Appeal State of Florida

Opinion filed January 31, 2024. Not final until disposition of timely filed motion for rehearing.

________________

No. 3D22-699 Lower Tribunal No. 17-17110 ________________

Q.G.S. Development, Inc., etc., et al., Appellants,

vs.

National Lining Systems, Inc., etc., Appellee.

An appeal from the Circuit Court for Miami-Dade County, Mark Blumstein, Judge.

Marlowe McNabb Machnik, P.A., Scott W. Machnik, and Jacqueline J. Brown (Tampa), for appellants.

Crabtree & Auslander, Charles M. Auslander, John G. Crabtree, Brian C. Tackenberg, Ferencik Libanoff Brandt Bustamante & Goldstein, P.A., Robert E. Ferencik, and Ira L. Libanoff (Plantation), for appellee.

Before FERNANDEZ, SCALES, and MILLER, JJ.

MILLER, J. This dispute arises out of the renovation of the Riviera Country Club

(the “Club”) golf course. Q.G.S. Development, Inc. ("QGS"), the general

contractor, and Berkley Regional Insurance Company, the surety, appeal

from a final judgment awarding damages to appellee, National Lining

Systems, Inc. (“NLS”), the subcontractor, for unpaid invoices following a

protracted nonjury trial. Appellants assert a myriad of errors on appeal, most

of which implicate factual and evidentiary considerations. We affirm in all

respects and write only to reiterate the familiar principle that although a

reviewing court might have reached a different result in the first instance, it

is not entitled to reweigh or reevaluate conflicting evidence. See State v.

Burke, 531 So. 2d 416, 418 (Fla. 4th DCA 1988).

BACKGROUND

In 2015, the Riviera Country Club hired QGS to construct an irrigation

lake on its property and refurbish the existing eighteen-hole golf course.

QGS, in turn, retained NLS to install a polyvinyl chloride (“PVC”) reservoir

liner on the bottom of the lake. Berkley issued a bond to guarantee

subcontractor payment for the project.

The parties exchanged purchase orders, proposals, and project plans

and specifications, along with two quality control manuals. Under the terms

of the agreement, QGS was to construct the lake and prepare the subgrade,

2 while NLS would install a protective textile layer over the subgrade, followed

by the reservoir liner. The liner would be secured by a sand ballast system.

QGS was solely responsible for dewatering operations.

Despite expressing concerns regarding the site conditions, NLS

installed the liner. QGS filled the lake and implemented the sand ballast

system.

QGS failed to pay the last invoice for the liner installation, and, mere

months later, portions of the liner began to lift. QGS contacted NLS for

remedial assistance, but, before NLS arrived on site, a QGS employee cut

part of the liner.

NLS effectuated repairs, but, soon after, the Club noticed the water

elevation in the lake was rapidly decreasing. A survey procured by QGS

revealed multiple leaks in the liner. QGS drained the lake, removed the sand

ballast, and isolated the leaks. NLS again performed repairs and

propounded invoices, but QGS refused to tender payment.

NLS filed suit against QGS and Berkley in the circuit court seeking

damages for breach of contract and performance under the payment bond,

or, alternatively, quantum meruit or unjust enrichment relief. QGS

counterclaimed for breach of contract and negligence.

3 The case proceeded to a bench trial, at the conclusion of which the

judge issued a lengthy and comprehensive order and entered judgment for

the unpaid invoices in favor of NLS. As relevant to this appeal, the court

attributed the lining failure to QGS’s ineffective dewatering operations and

improper installation of the sand ballast. The court further rejected the

counterclaim outright, finding that, given untenable time constraints and

other extraneous circumstances, NLS performed within industry standards.

A motion for rehearing proved futile, and the instant appeal ensued.

LEGAL ANALYSIS

It is axiomatic that, in a bench trial, the trial judge possesses the

“superior vantage point to see and hear the witnesses and judge their

credibility.” Guzman v. State, 721 So. 2d 1155, 1159 (Fla. 1998), cert.

denied, 526 U.S. 1102 (1999). Consequently, “the factual findings of the

judge are entitled to the weight of a jury verdict.” Petion v. State, 48 So. 3d

726, 730 (Fla. 2010). The appellate court is only authorized to reverse if

such findings are not supported by competent, substantial evidence. See

Citibank, N.A. v. Olsak, 208 So. 3d 227, 229 (Fla. 3d DCA 2016).

In the instant case, appellants assail the conclusion that improper

dewatering operations precipitated the breach of the liner, along with the

corollary finding that QGS unilaterally cut the liner as soon as the first

4 infirmity materialized, leaving NLS with no choice other than to use

concededly “unorthodox” techniques to effectuate the repairs. In doing so,

appellants argue they presented a more cogent and logical theory of

recovery.

Although he equivocated at times during his testimony, QGS’s principal

confirmed that a QGS employee cut into the liner while NLS was in transit to

the project site, and NLS adduced evidence that the unilateral cut doomed

the liner to failure.

Further, the record is replete with evidence concerning the impact of

dewatering issues on the project. To identify but a few: (1) NLS was reluctant

to perform its contractual tasks in wet conditions; (2) the Club deemed

dewatering necessary to ensure proper bonding; (3) a consultant hired by

the Club concluded the liner had been damaged by an upswell of

groundwater; and (4) QGS admitted that dewatering issues plagued the

renovation.

Other evidence of record, of course, arguably supported the

proposition that NLS contributed to the failures by way of its repair

methodology. That may well be true, but the scope of our review does not

entail examining evidence that potentially supports a different result.

Instead, we must only determine whether the findings of the trial court are

5 supported by competent, substantial evidence. See Whitby v. Infinity Radio,

Inc., 961 So. 2d 349, 354 (Fla. 4th DCA 2007) (“An appellate court will not

disturb a trial court’s factual findings when supported by competent

substantial evidence.”). In this vein, “the appellate court should interpret the

record and all reasonable inferences and deductions capable of being drawn

therefrom in the light most favorable to sustain [the trial court’s] conclusions.”

DeLalio v. Food Palace, Inc., 330 So. 2d 835, 837 (Fla. 3d DCA 1976); see

also Shaw v. Shaw, 334 So. 2d 13, 16 (Fla. 1976) (“It is not the function of

the appellate court to substitute its judgment for that of the trial court through

re-evaluation of the testimony and evidence from the record on appeal before

it.”); Markham v. Fogg, 458 So.

Related

Marrone v. Miami National Bank
507 So. 2d 652 (District Court of Appeal of Florida, 1987)
Whitby v. Infinity Radio, Inc.
961 So. 2d 349 (District Court of Appeal of Florida, 2007)
Perlow v. Berg-Perlow
875 So. 2d 383 (Supreme Court of Florida, 2004)
Zerquera v. CENTENNIAL HOMEOWNERS'ASS'N
721 So. 2d 751 (District Court of Appeal of Florida, 1998)
Guzman v. State
721 So. 2d 1155 (Supreme Court of Florida, 1998)
Wiederhold v. Wiederhold
696 So. 2d 923 (District Court of Appeal of Florida, 1997)
Everett Painting Co., Inc. v. Padula & Wadsworth Constr., Inc.
856 So. 2d 1059 (District Court of Appeal of Florida, 2003)
Shaw v. Shaw
334 So. 2d 13 (Supreme Court of Florida, 1976)
Lahodik v. Lahodik
969 So. 2d 533 (District Court of Appeal of Florida, 2007)
Markham v. Fogg
458 So. 2d 1122 (Supreme Court of Florida, 1984)
Dreyfuss v. Dreyfuss
701 So. 2d 437 (District Court of Appeal of Florida, 1997)
Bryan v. Bryan
930 So. 2d 693 (District Court of Appeal of Florida, 2006)
DeLalio v. Food Palace, Inc.
330 So. 2d 835 (District Court of Appeal of Florida, 1976)
Griffin Industries, LLC v. Dixie Southland Corporation
162 So. 3d 1062 (District Court of Appeal of Florida, 2015)
Citibank, N.A. v. Olsak
208 So. 3d 227 (District Court of Appeal of Florida, 2016)
Petion v. State
48 So. 3d 726 (Supreme Court of Florida, 2010)
State v. Burke
531 So. 2d 416 (District Court of Appeal of Florida, 1988)
Alvarez v. All Star Boxing, Inc.
258 So. 3d 508 (District Court of Appeal of Florida, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Q.G.S. Development, Inc., etc. v. National Lining Systems, Inc., etc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/qgs-development-inc-etc-v-national-lining-systems-inc-etc-fladistctapp-2024.