Pyramid Condominium Ass'n v. Morgan

664 F. Supp. 216, 1986 U.S. Dist. LEXIS 29777
CourtDistrict Court, D. Maryland
DecidedJanuary 31, 1986
DocketCiv. No. JFM-84-1719
StatusPublished
Cited by1 cases

This text of 664 F. Supp. 216 (Pyramid Condominium Ass'n v. Morgan) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pyramid Condominium Ass'n v. Morgan, 664 F. Supp. 216, 1986 U.S. Dist. LEXIS 29777 (D. Md. 1986).

Opinion

MEMORANDUM

MOTZ, District Judge.

This is an action brought by the Pyramid Condominium Association against William Morgan and A.T.E.C. Associates, Inc., the architect and the material and geophysical engineers involved in the design and construction of the condominium. The defendants have implead as third party defendants a number of other companies which [217]*217performed various facets of the construction or engineering work.

Pending are motions for summary judgment filed by Morgan and A.T.E.C., joined by several of the third party defendants, based upon the ground that plaintiff’s claims are barred by limitations. The parties agree that Maryland’s three year statute of limitations applies. The parties also agree that the statute of limitations began to run when plaintiff knew or reasonably should have known of the alleged wrongs upon which its cause of action is based. The critical question is when that event occurred.

Defendants point to numerous facts demonstrating that plaintiff had knowledge of defects at the Pyramid substantially more than three years before this suit was filed on April 27, 1984. Minutes of meetings of plaintiff’s board of directors as early as July 80,1977 refer to problems with the air conditioning system, and on May 22, 1978 the board discussed “several water problems which the building is suffering on the exterior end with leaks.” The board commissioned an inspection by Jimmie Critchfield, a professional engineer, who submitted a letter report dated June 28, 1978, detailing various construction problems. Critchfield indicated that in his view the building was in need of considerable remedial work, and he suggested that a further investigation (including materials testing) be made of the structural and mechanical systems in the building. The board obtained another report from the C.C. Murphy Company on October 2, 1978, which reflected cracking problems in the concrete. While on an almost continuous basis thereafter the board discussed and considered construction problems and took various steps to try to repair manifold items of damage, including ones resulting from water leakage, it did not follow up on Critchfield’s suggestion that a more complete investigation be conducted. In April 1981, as the problems continued, the board toured the building and inspected numerous cracks, faults and deterioration in several units. After the tour the board authorized the hiring of Abel Schwartz, another engineer, to make a study of the Pyramid and to make recommendations for long term maintenance. Schwartz’s report, dated April 27, 1981, was received by the board on April 80, 1981.1

The problems at the condominium continued. In 1982 plaintiff hired the structural engineering firm of George, Miles & Buhr, to conduct another inspection. This action was instituted approximately two years later. In 1985 plaintiff hired Donald W. Vannoy, a professor of civil engineering at the University of Maryland, as an expert wit ness. Dr. Vannoy reached the conclusion that the water problems at the Pyramid were caused primarily because salt had been used as an admixture in the concrete of the building and that flashing to control water run off had not been incorporated into the building’s design or construction.

Against this background defendants contend that plaintiff’s cause of action accrued substantially more than three years before this suit was filed, specifically in June 1978 when Critchfield submitted his report suggesting that a more extensive engineering study be conducted. In reply, plaintiff makes the rather remarkable contention that it did not know, and reasonably should not have known, of the wrongs upon which this action is based until after the action was instituted. Plaintiff argues that limitations did not begin to run until 1985, when Vannoy submitted his litigation report setting forth what he perceived to be the causes of plaintiff's problems.

Summary judgment may, of course, be granted only where there is no genuine dispute as to any material fact. Furthermore, the burden is upon the moving party to establish that it is entitled to summary judgment, and all reasonable inferences from established facts must be drawn in favor of the non-moving party. See, e.g., Charbonnages de France v. Smith, 597 F.2d 406, 414 (4th Cir.1979); Donovan v. [218]*218Porter, 584 F.Supp. 202, 209 (D.Md.1984). While these rules are appropriately strict, it is clear that defendants are entitled to summary judgement here.

Maryland law indisputably governs the limitations question. See, e.g., Brown v. American Broadcasting Co., 704 F.2d 1296, 1299 (4th Cir.1983); Sasso v. Koehler, 445 F.Supp. 762, 765 (D.Md.1978). The “discovery rule” has long been applied under Maryland law to claims involving alleged professional malpractice in connection with construction projects. See Steelworkers Holding Co. v. Menefee, 255 Md. 440, 443-44, 258 A.2d 177 (1969); Sisters of Mercy v. Gaudreau, Inc., 47 Md.App. 372, 377-78, 423 A.2d 585 (1980). The Maryland Court of Appeals has now ruled that the “discovery rule” is generally applicable to all limitations questions. See Poffenberger v. Risser, 290 Md. 631, 636, 431 A.2d 677 (1981).

In Poffenberger the court indicated that the “knew or reasonably should have known” standard would be met if the plaintiff had “knowledge of circumstances which ought to have put a person of ordinary prudence on inquiry ... with notice of all facts which such an investigation would in all probability have disclosed if it had been properly pursued.” 290 Md. at 637, 431 A.2d 677 quoting Feritta v. Bay Shore Development Corp., 252 Md. 393, 402, 250 A.2d 69 (1969). As plaintiff properly conceded, at the oral argument held on December 11, 1985, Poffenberger makes clear that a plaintiff is charged with expert knowledge not at the time that he receives a report from an expert but at the time he is aware of enough facts to know he needs to consult an expert. It is within three years of that date that suit must filed.

Defendants here are correct in contending limitations began to run in June 1978 when plaintiff received the Critchfield report. Prior to that time plaintiff had no reason to know that there were fundamental, structural defects at the condominium. However, in the report Critchfield expressly advised plaintiffs directors that they should have a further and more extensive engineering study conducted. This was confirmed by the C.C. Murphy report. Moreover, for several years thereafter, the problems became exacerbated, and in April 1981 plaintiff hired Schwartz to conduct another study of the water leakage problem. Yet another report was obtained from George, Miles & Buhr in mid 1982 and the suit was still not filed until almost two years later.

Sisters of Mercy v. Gaudreau, Inc. is analogous to this case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reaves v. Westinghouse Electric Corp.
683 F. Supp. 521 (D. Maryland, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
664 F. Supp. 216, 1986 U.S. Dist. LEXIS 29777, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pyramid-condominium-assn-v-morgan-mdd-1986.