Pusey & Jones Co. v. Combined Locks Paper Co.

255 F. 700, 1918 U.S. Dist. LEXIS 707
CourtDistrict Court, E.D. Wisconsin
DecidedMay 8, 1918
StatusPublished
Cited by6 cases

This text of 255 F. 700 (Pusey & Jones Co. v. Combined Locks Paper Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pusey & Jones Co. v. Combined Locks Paper Co., 255 F. 700, 1918 U.S. Dist. LEXIS 707 (E.D. Wis. 1918).

Opinion

GEIGER, District Judge.

The complaint contains two causes of action, the first based upon a contract dated on or about May 15, 1916, whereby the plaintiff undertook to make for the defendant a paper machine for the agreed price of $120,000,. according to the' terms and specifications prescribed, and that the defendant, the plaintiff having furnished the machine, is indebted to the plaintiff in the sum of $31,215.19, with interest' from March 1, 1917, as an unpaid balance of the agreed purchase price. The statement of the second cause of action recites the written undertaking on the part of the plaintiff, dated on or about July 26, 1916, to rebuild for the defendant a described paper machine in consideration of the payment of $23,750; that the plaintiff performed such contract, but defendant has defaulted upon an unpaid balance of the contract price, $4,890. On both causes of action judgment in the aggregate of $36,105.19 is-asked.

The prima facie character of the plaintiff’s demand was substantially admitted by the defendant upon the trial of the case, whereupon the [701]*701issues for trial were those tendered by the answer which set up counterclaims in substance;

That with respect to the first cause of action the plaintiff—

“failed to fulfill said contract by not delivering the machine therein mentioned on the 15th day of November as the contract provided, until the 3d day of April, 1917, when it was delivered to the carrier in uncompleted shape; that by reason of said delay, and the failure of the plaintiff to deliver the said machine in the time provided in said contract, and the resulting inability of the defendant to make use of said machino during the period of delay caused by the plaintiff in noncompliance with said contract, the defendant suffered great damages, namely, in the amount of thirty-four thousand four hundred ten dollars and seventy cents ($34,410.70), which damages were the direct result and entirely caused by the failure of the plaintiff to fulfill said contract as it, the plaintiff, was obligated to do, and that all of his damages necessarily resulted from default, negligence, and violation of this contract by the plaintiff.”

In respect of the second cause of action the defendant alleged that the machine to be repaired was to be so repaired and delivered to transportation lines at Fitchburg, Mass., on November 1, 1916; but—

“that the plaintiff delayed the delivery of said repaired machine as provided in said contract until the 20th day of February, 1917; that by reason of said delay and the resulting deprivation of the use of said machine by the defendant, the defendant suffered great damages and losses, namely, the sum of eight thousand four hundred dollars ($8,400), all of which damages and losses were directly caused by the direct and necessary result of said plaintiff’s delay in the fulfillment of said contract.”

A further set-off and counterclaim, based upon alleged expenditures made by the defendant on account of supplying missing parts from the machine, traveling expenses, and the like, in the sum of $1,733.85 is offered, and the answer demands judgment for a dismissal of the complaint, and for judgment in the sum of $16,544.55, being, I assume, the excess of the damages set out in the counterclaim beyond the sum which by the answer is admitted to be due to the plaintiff.

Upon the trial of the case the defendant undertook to establish its counterclaim by evidence, most of which was tentatively received, subject to objection, but practically all of which was subsequently stricken out, whereupon a verdict was directed in favor of the plaintiff and against the defendant, and a motion for a new trial, which has been argued, presents for review the various rulings of the court upon the rejection of evidence, which led to granting the motion for a direction of verdict and a dismissal of the counterclaim.

A consideration of the motion must be addressed, first, to the general contentions of the defendant respecting the rule of recovery upon contracts such as are involved in the case, and, secondly, a consideration of the facts tendered in evidence with a view of determining whether, in any aspect, they furnish a basis for an award of damages by the jury upon the theory and the only theory offered and insisted upon by the plaintiff.

It will be observed from the pleadings that the defendant framed the counterclaims, excepting the last, solely upon the hypothesis of seeking recovery under a general rule of damages. There is no inti[702]*702mation in the pleading, except as noted, of any claim of recovery, except the general damages sustained by the defendant through a deprivation of the use of the machine during the delay period; and this brings us at once to a consideration of the bill of particulars demanded by the plaintiff of the defendant prior to the commencement of the trial. It is as follows:

Per ton profit 22%-pound paper made on 176-inch machine, contract No. 1331 .............................................. $9.78
Daily tonnage produce......................................... 30
Delay on shipment, December 1, 1916, to April 3, 1917.......... 110 days
110 days x 30 tons............................................ 3,300 tons
3,300 tons x $9.78....................................$32,274.00
Payments to Valley Iron Works, Appleton, Wis., for material to replace imperfect.or unfinished parts called for in purchase contract........................ 327.30
Cash advanced to Pusey & Jones Company............ 50.00
Total ........ $32,651.30
Contract No. 1340 would have increased production from November 1 to February 20........................................ 281.7 tons
Profit on increased production........................ $8,119.26
Expense L. D. Alsted to Wilmington, Del., January 13, 1917 .........i.................................... 187.48
Service and expense Pittsburg testing laboratory at Wilmington and Pittsburg.............................. 1,292.26
Express charges on delayed material covered by contract 254.11 $9,853.11
Interest on money actually expended on contracts 1331 and 1340 and on plant and equipment from date when delivery should have been made to delivery when same was actually made..... $7,500.00

In explanation of references in this bill, it may be said that the first items, under “Contract No. 1331,” are pertinent to the first cause of action of the complaint and to the counterclaim averring a breach through a delay of furnishing the new machine, and that the second items,'under “Contract No. 1340,” are.pertinent to the second cause of action of the complaint and to the counterclaim for damages for delay in repairing and shipping the old machine; whereas the last item is evidently intended to speak for itself as an interest item on purchase-money expenditures, and “on plant and equipment from date when delivery should have been made to date when delivery actually was made.”

[1]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
255 F. 700, 1918 U.S. Dist. LEXIS 707, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pusey-jones-co-v-combined-locks-paper-co-wied-1918.