Purnell Furniture Services, Inc. v. Warehouse Rack Company

CourtCourt of Appeals of Texas
DecidedAugust 1, 2006
Docket14-04-00270-CV
StatusPublished

This text of Purnell Furniture Services, Inc. v. Warehouse Rack Company (Purnell Furniture Services, Inc. v. Warehouse Rack Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Purnell Furniture Services, Inc. v. Warehouse Rack Company, (Tex. Ct. App. 2006).

Opinion

Affirmed and Memorandum Opinion filed August 1, 2006

Affirmed and Memorandum Opinion filed August 1, 2006.

In The

Fourteenth Court of Appeals

____________

NO. 14-04-00270-CV

PURNELL FURNITURE SERVICES, INC., Appellant

V.

WAREHOUSE RACK COMPANY, Appellee

On Appeal from the 295th District Court

Harris County, Texas

Trial Court Cause No. 2002-30460

M E M O R A N D U M   O P I N I O N


Appellee, Warehouse Rack Company (AWRC@), sued appellant, Purnell Furniture Services, Inc. (APurnell@) for breach of contract.  Purnell counterclaimed alleging violations of the Deceptive Trade Practices Act (ADTPA@).  A jury awarded WRC damages, but awarded Purnell no damages on its counterclaim.  Appellant raises four issues on appeal: (1) the evidence was legally and factually insufficient to support the judgment in favor of WRC because Purnell performed the contract or, alternatively, was excused from performance; (2) the trial court reversibly erred by refusing to give a limiting instruction to the jury regarding a witness=s compliance under the Texas Engineering Practices Act (ATEPA@); (3) the trial court erred when it entered the jury=s award for extra-contractual damages; and (4) the evidence was legally and factually insufficient to support the award of attorney=s fees.  We affirm.

Factual and Procedural Background

WRC specializes in buying and selling warehouse equipment.  Purnell specializes in warehousing and shipping furniture for various national retailers, and, in order to better serve its customers, Purnell constructed a new warehouse in Suwannee, Georgia.  Purnell contracted with WRC to purchase used furniture cantilever rack from a warehouse in Athens, Texas.  WRC was to purchase the rack, ship it to Suwannee, modify the rack to suit Purnell=s needs, and then install it in January, 2002. 

Purnell provided the dimensions of the warehouse and specifications for the rack.  Utilizing those dimensions, WRC hired Rick Denmark in September, 2001 to provide drawings of proposed rack layouts.  The original dimensions provided by Purnell did not include certain aspects of the warehouse, as Denmark discovered in November or December, 2001 when he received an AutoCAD drawing of the warehouse.  The AutoCAD drawing showed that a wall was not positioned as originally understood, and there was a work area within the warehouse.  Denmark and Neil Camberg, WRC=s president, discussed the variances with Purnell.  All agreed that the best solution would be to move the work areaCa solution Purnell said would be no problem, as the warehouse was a work in progress. 

On January 4, 2002Cthree days before installation was supposed to beginCPurnell informed WRC that a permit was necessary.  WRC immediately began the process of obtaining a permit, including hiring Grayson Willard, a Georgia registered professional engineer.  Despite beginning the permitting process in January, the permit was not approved until March, 2002.  As a result, the installation was delayed until March 8. 


WRC hired Don Russell to modify and install the rack.  Russell agreed to travel to Georgia in January for ten or twelve days.  He was to meet the trucks carrying the rack in Georgia, unload the trucks, and begin working.  However, two issues prevented the plan from being carried out.  First, the building contractor was preparing to pour the parking lot and would not allow the trucks on the surface.[1]  Second, the necessary permit had not been obtained and, as a result, the building contractor would not allow the installation to begin.[2]  Although installation could not begin, Russell and Camberg testified that it was necessary for Russell and his crew to make the trip to Georgia to meet the trucksCwhich had already left Texas when the permitting issue was first raised.  Russell unloaded the trucks at an off-site location, and then returned to Texas with his crew.

The lack of permit caused further problems.[3]  Specifically, after the first trip to Georgia, Camberg instructed Russell to communicate directly with Purnell and return to Georgia when Purnell asked him to return.  Believing the permit was imminent on three other occasions, Elmer Purnell instructed Russell to return to Georgia three other times, though Russell was not able to install the rack because the permit had not issued.  Russell complained to Camberg of the added expense of the trips.  Camberg agreed that Russell should recover the additional $13,697 in expenses for the four additional trips and orally guaranteed he would pay those expenses. 


In March, when the permit was finally approved, WRC and Purnell again discussed the terms of their agreement.  Camberg was concerned that Purnell would not pay the remaining contract installment.  There was one remaining truckload of materials to deliver to Georgia and WRC refused to ship those materials until Purnell signed a letter reaffirming all original termsCexcept for the datesCof the original agreement.  The letter made no mention of the additional trip expenses for Russell.  However, in a telephone conversation, Camberg told Richard Purnell that he would not invoice those extra expenses if Purnell would sign the letter and pay according to its terms.  Richard Purnell signed and returned the letter.

Russell returned to Georgia with his crew in MarchChis fifth tripC

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Golden Eagle Archery, Inc. v. Jackson
116 S.W.3d 757 (Texas Supreme Court, 2003)
Interstate Contracting Corp. v. City of Dallas
135 S.W.3d 605 (Texas Supreme Court, 2004)
Arrellano v. State Farm Fire & Casualty Com.
191 S.W.3d 852 (Court of Appeals of Texas, 2006)
Horizon/CMS Healthcare Corporation v. Auld
34 S.W.3d 887 (Texas Supreme Court, 2000)
Dow Chemical Co. v. Francis
46 S.W.3d 237 (Texas Supreme Court, 2001)
Stewart Title Guaranty Co. v. Sterling
822 S.W.2d 1 (Texas Supreme Court, 1992)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Arthur Andersen & Co. v. Perry Equipment Corp.
945 S.W.2d 812 (Texas Supreme Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
Purnell Furniture Services, Inc. v. Warehouse Rack Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/purnell-furniture-services-inc-v-warehouse-rack-co-texapp-2006.