Pullis Bros.' Iron v. Parish of Natchitoches

26 So. 402, 51 La. Ann. 1377, 1899 La. LEXIS 578
CourtSupreme Court of Louisiana
DecidedJune 22, 1899
DocketNo. 13,194
StatusPublished
Cited by2 cases

This text of 26 So. 402 (Pullis Bros.' Iron v. Parish of Natchitoches) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pullis Bros.' Iron v. Parish of Natchitoches, 26 So. 402, 51 La. Ann. 1377, 1899 La. LEXIS 578 (La. 1899).

Opinion

The opinion of the court was delivered by

Watkins, J.

The following statement of facts has been extracted from the brief of the intervenor’s counsel, viz;

“In June, 1895, P. J. Gillen contracted with the police jury of “Natchitoches parish to erect a court-house for $20,555.00. On July “2nd, 1895, he made arrangements to get $14,000.00 from Ruston “ State Bank, to pay on said work, and executed a notarial assignment “ or pledge of all his rights as mechanic and contractor on said eourt- [1378]*1378“ house,' which was duly recorded on November 13th, 1895. Ou “ August 19th, 1895, he contracted with plaintiff, Illinois Supply and “ Construction Company, for pressed brick for the building at $12.00 “per M., delivered f. o. b. cars, St. Louis, Mo., amounting to $14,- “ 000.00, which contract was made simply by letters, and was never “ recorded.

“In November, 1895, he ordered from Pullis Bros. Iron Company “some iron work for court-house, without privilege of inspection, “ also by letter, and io be delivered also at St. Louis, Mo.

“On April 23d, 1896, Gillen failed, after having spent $20,000.00 “ on the court-house, and the contract was relet to one C. D. Stewart, “ for $11,600.00.

“On May 27th, 1896, plaintiffs gave president of police Jury an at- “ tested account, and also recorded their claim the same day. Gillen owed the Illinois Supply and Construction Company $563.34, and Pullis Bros. Iron Co., $219.00. In September, 1897, these suits were brought, and the parish was garnisheed for what might be due Gil“len, he being a non-resident. There is no denial of the debt.

'“The Ruston State Bank intervened and set up that plaintiffs had “no lien, as it was a Missouri contract, and under the laws of their •“ own State, they had none. Further, that by virtue of their assign- “ rnent recorded, they were entitled to be paid in preference to plain- “ tiffs anyway, which contention on the part of the bank was sanctioned by the judge a quo, and judgment rendered accordingly, “ which judgment was reversed by the Court of Appeals, and this ap- plication was then made.”

These two cases are presented together for convenience of argument, as both plaintiffs are domiciled in St. Louis, M.o., and the law applicable to one, is equally applicable to the other.

Jt appears that these two cases were decided in the District Court '-intfavor of the intervenor, but on appeal to the court of respondents, •that judgment was reversed, and one rendered in favor of the plaintiffs.

Relator assigns as error on the part of respondents, the following, to-wit:

1st. In holding that the plaintiffs are entitled to a lien and privilege as material men on the court-house of Natchitoches parish, for materials used therein, the contracts for same having been entirely made and executed, and the property delivered in a State different [1379]*1379from Louisiana, and whose laws accord nojien to material men who .furnish material to public buildings, on the ground that same is contrary to public policy.

2nd. In holding that plaintiffs had a privilege or lien on said courthouse, because a privilege is a right which the nature of the debt or ■contract gives the creditor to be paid by preference, and, as in this case, the contract was made and executed in Missouri, it must have .an effect given to it by the law of that State — a privilege being one of the effects of a contract given in special cases by particular laws, and must be strictly construed, and can not be extended to eases not coming within the special protection of the law of Louisiana.

3rd. In holding that plaintiff’s lien had effect on said building, same not having been recorded in the parish where the property is situated, within fifteen days after the debt was contracted, as the law requires.

4th. In holding that notwithstanding a foreign material man who furnishes material in another State and has no lien against the building, has yet a right to serve attested accounts and hold the parish under Revised Civil Code, 2772.

5th. In holding that an assignee of a principal contractor for a valuable consideration made before engagements with material men had been made, and prior to the presentation to the owner of their attested accounts, and prior to the recordation thereof, can not contest with such material men for priority of payment out of the proceeds of the balance due the contractor by the owner.

Relator states that respondents “have made a very full -statement of the facts in this case in the opinion filed herewith, which we adopt;” consequently, we need not go outside of the recitals of fact contained 'in the opinion of the respondent judges, and may safely take the ■statement therein contained as our guide.

We make the following recapitulation from the opinion of the respondents, to be taken in connection with the foregoing statement of facts made by counsel:

(a) On the 4th day of June, 1895, Gillen contracted with the parish of Natchitoches to build a court-house for the price of $20,-555.00,' payable $2500.00 when the foundation was laid, and the remainder as fast as same was produced by a one-mill tax, which had been levied on the property of the parish.

On the 8th d,ay of June following, Gillen gave Bond for the comple[1380]*1380tioii of the building in accordance with the contract and. specifications which had been recorded on the 4th day of June, previous. He proceeded with his contract until the 23rd day of June, 1896, when, by reason of his inability to complete his contract, the same was forfeited, and in pursuance of clause 13 of the contract, the job was re-let to C. D. Stewart, for completion of the building, in conformity with the contract with Gillen, and for the price and sum of $11,600.00.

On October 17th, 1896, Gillen filed suit in the United States Court against the parish for $14,734.00, as a balance due him, and which resulted in a judgment in his favor for $7,700. This judgment was-rendered on February 1, 1898, and was immediately afterward assigned to the intervenor, and notice given to the parish of Natchitoches.

(b) On July 2d, 1895, P. J. Gillen, contractor, by notarial act, assigned to the Ruston State Bank, intervenor herein, all of his contract rights as collateral security, for a loan of $14,000 in cash, to be made to him to enable him to build and construct said court-house, and to secure the same, subrogated said bank to his privilege as contractor on; said building, and authorized it to collect the money due him by the parish, as it became due.

This contract was duly recorded in the parish of Natchitoches on November 13, 1895.

(c) On November —, 1895, Pullis Bros. Iron Oo., in pursuance of a previous contract, furnished Gillen with material, which -was used in the construction of the court-house, the balance due on which account is $219.54.

On the failure" of Gillen to pay balance due for material, said company caused an attested account to be made out in conformity with the-provisions of Article 2772 of the Civil Code, and served it on the parish on February 14, 1896, and caused same to be recorded on May 12, 1896.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barrett Mfg. Co. v. Board of Com'rs
63 So. 505 (Supreme Court of Louisiana, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
26 So. 402, 51 La. Ann. 1377, 1899 La. LEXIS 578, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pullis-bros-iron-v-parish-of-natchitoches-la-1899.