Pugh v. Butler Telephone Co., Inc.

512 So. 2d 1317, 1987 Ala. LEXIS 4468
CourtSupreme Court of Alabama
DecidedJuly 31, 1987
Docket85-1017
StatusPublished
Cited by46 cases

This text of 512 So. 2d 1317 (Pugh v. Butler Telephone Co., Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pugh v. Butler Telephone Co., Inc., 512 So. 2d 1317, 1987 Ala. LEXIS 4468 (Ala. 1987).

Opinion

This is an appeal by the plaintiffs, the surviving parents and the estate of Johnnie Carl Pugh, from a summary judgment in favor of the defendants, Butler Telephone Company, Inc., Bay Springs Telephone Company, Inc., Telephone Electronics Corporation, and Joseph D. Fail, Engineering Company, Inc., in a wrongful death action. Pugh, an employee of Sandidge Construction Company ("Sandidge"), was killed while working in the line and scope of his employment when the sides of an excavation in which he was working caved in on top of him. There was at least a scintilla of evidence that the excavation in which Pugh was working at the time of his death was neither shored nor sloped and that it violated certain general safety standards. The excavation had been dug the day of Pugh's death by Sandidge, without knowledge of Butler Telephone Company ("Butler") or Joseph D. Fail Engineering Company, Inc. ("Fail"). Sandidge was under contract with Butler to "lay approximately 18 miles of telephone cable" in a rural area. This was a system that had been approved by the U.S. Department of Agriculture, Rural Electrification Administration (REA). Butler's contract with Sandidge was an REA contract. Fail was the engineer whose responsibility it was to ensure the expeditious and economical construction of the project in accordance with approved plans and specifications. Fail was not to exercise any actual control over Sandidge's employees. The engineering contract between Butler and Fail further provided that Fail's obligations "run to and are for the benefit of only" Butler and the REA administrator.

The plaintiffs' issues for review relate only to the liability of Butler and Fail.

There are three issues presented for review.

The first issue is whether there is a scintilla of evidence to support a finding that Sandidge was an agent of Butler, which finding would enable the plaintiffs to sue Butler for the negligence of Sandidge under the theory enunciated inAlabama Power Co. v. Beam, 472 So.2d 619 (Ala. 1985).

Plaintiffs correctly state that whether a relationship is that of an independent contractor or master-servant depends on whether the entity for whom the work is being performed has reserved the right of control over the means by which the workis done. Sawyer v. Chevron USA, Inc., 421 So.2d 1263 (Ala. 1982). In the absence of a non-delegable duty, the mere retention of the right to supervise or inspect the work of an independent contractor as the work progresses to ensure compliance with the terms of an agreement does not operate to create a master-servant relationship. There must be a retention of control over the manner in which the work is done, before an agency relationship is created. Alabama Power Co. v. Beam,supra, at 625; Brown v. Commercial Dispatch Publishing Co.,504 So.2d 245 (Ala. 1987). In determining the relationship between Butler and Sandidge, we must review the written contract and the actions of the parties pursuant to the contract.

Our standard of review of a summary judgment granted in favor of a defendant requires us to review the record in a light most favorable to the plaintiff and to resolve all reasonable doubts against the defendant. Harrell v. Reynolds Metals Co.,495 So.2d 1381 (Ala. 1986); Burt v. Commercial Union Insurance Co.,489 So.2d 547 (Ala. 1986); Autrey v. Blue Cross Blue Shield ofAlabama, 481 So.2d 345 (Ala. 1985).

The following are all of the provisions of the contract that in any way relate to Butler's retained right of any control:

(1) Butler reserved the right to require the removal from the project of any of Sandidge's employees if in Butler's judgment such removal was necessary to protect Butler's interest. *Page 1319

(2) Butler had the right to require Sandidge to increase the number of employees and to increase and change the amount or kind of tools or equipment if at any time the progress of the work was unsatisfactory to Butler, but Butler's failure to give such directions did not relieve Sandidge of its obligations to complete the work within the time and manner specified in the contract.

(3) Butler and the REA administrator reserved the right to inspect all payrolls, invoices of materials, and other data and records of Sandidge relating to the construction of the project.

(4) Sandidge was required at all times to take all reasonable precautions for the safety of its employees on the project and of the public and to comply with all applicable provisions of federal, state, and municipal safety laws and building construction codes, as well as safety rules and regulations of Butler. Interpreting the contract most favorably to the plaintiffs, one would conclude that if Sandidge violated this provision, after written notice was given Sandidge by Fail or Butler, Sandidge would immediately correct the violation and if it failed to do so then Butler "may correct such violation" at Sandidge's expense. If Butler deemed it necessary or advisable, it could correct a violation at Sandidge's expense without prior notice to Sandidge.

This contract is materially different from the contract inAlabama Power Co. v. Beam, supra.

We do not believe that the contract gave Butler any right of control over the manner in which the work was done by Sandidge. As previously noted, retention of the right to supervise or inspect the work as it progresses to ensure compliance with the terms of the construction contract and the retention of the right to stop work done improperly do not create a master-servant relationship between the entity for whom the work is being performed and the entity doing the work. AlabamaPower Co. v. Beam, supra.

There is no evidence in the record that Butler exercised any control or retained any right of control over the manner in which Sandidge performed any of its work on the project. The undisputed evidence in the record shows that Sandidge's employees took their directions in the laying of the pipe or cable exclusively from Sandidge and that Sandidge alone was "running the show and controlling the workplace."

The remaining two issues for review are as follows:

Is there a scintilla of evidence to support plaintiffs' contention that Fail negligently failed to carry out its duties under the terms of the contract between Butler and Fail and thereby proximately caused Pugh's death?

Whether Butler may be held liable for the negligence of Fail if Fail violated its contractual responsibilities by failing to be present on the jobsite and if this failure resulted in Pugh's death?

These issues will be discussed together, since we do not find that Fail did not carry out its duties under its contract with Butler.

Fundamental to the maintenance of a negligence action is the existence of a legal duty of care owed by the defendant to the plaintiff. Plaintiffs place great emphasis upon the contractual undertaking of Fail in its contract with Butler. While a party's negligent performance of a contract may subject that party to liability in tort for physical harm to others, seeMorgan v. South Central Bell Tel. Co., 466 So.2d 107, 114 (Ala. 1985), the scope of that duty, i.e., the persons to whom that duty runs, must be ascertained. Thus, for instance, a workmen's compensation carrier who makes safety inspections of its insured's premises owes a duty of care to the employees of that insured to perform the inspection non-negligently. Beasley

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Benson v. BBH WBMC LLC
N.D. Alabama, 2025
Melissa Ann Bobo v. Tennessee Valley Authority
855 F.3d 1294 (Eleventh Circuit, 2017)
Bain v. Colbert County Northwest Alabama Health Care Authority
233 So. 3d 945 (Supreme Court of Alabama, 2017)
Bobo v. Tennessee Valley Authority
138 F. Supp. 3d 1285 (N.D. Alabama, 2015)
Southland Bank v. a & a Drywall Supply Co.
21 So. 3d 1196 (Supreme Court of Alabama, 2009)
Gowens v. Tys. S. Ex Rel. Davis
948 So. 2d 513 (Supreme Court of Alabama, 2006)
Terry Calloway v. PPG Industries, Inc.
155 F. App'x 450 (Eleventh Circuit, 2005)
Commercial Union Insurance Co. v. Deshazo
845 So. 2d 766 (Supreme Court of Alabama, 2002)
Armstrong Business Services, Inc. v. AmSouth Bank
817 So. 2d 665 (Supreme Court of Alabama, 2001)
McGinnis v. Jim Walter Homes, Inc.
800 So. 2d 140 (Supreme Court of Alabama, 2001)
Cobb v. Union Camp Corp.
786 So. 2d 501 (Court of Civil Appeals of Alabama, 2000)
Smith v. Universal Scheduling Co.
736 So. 2d 562 (Supreme Court of Alabama, 1999)
Carter v. Chrysler Corp.
743 So. 2d 456 (Court of Civil Appeals of Alabama, 1998)
Spriggs v. Compass Bank
742 So. 2d 178 (Court of Civil Appeals of Alabama, 1997)
Defoor v. Evesque
694 So. 2d 1302 (Supreme Court of Alabama, 1997)
Ramirez v. Alabama Power Co.
898 F. Supp. 1537 (M.D. Alabama, 1995)
Parr v. Champion Intern. Corp.
667 So. 2d 36 (Supreme Court of Alabama, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
512 So. 2d 1317, 1987 Ala. LEXIS 4468, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pugh-v-butler-telephone-co-inc-ala-1987.