Puget Soundkeeper Alliance v. Seattle Iron & Metals Corp.

District Court, W.D. Washington·Decided March 13, 2026·No. 2:12-cv-01201·Unknown

Opinion

5 UNITED STATES DISTRICT COURT WESTERN DISTRICT OF WASHINGTON 6 AT SEATTLE

7 PUGET SOUNDKEEPER ALLIANCE, 8 Plaintiff, Case No. C12-1201-RSM 9 10 v. ORDER GRANTING IN PART PLAINTIFF’S MOTION TO 11 SEATTLE IRON & METALS CORP., ENFORCE AND MODIFY CONSENT DECREE 12 Defendant. 13 14 I. INTRODUCTION 15 16 This matter comes before the Court on Plaintiff Puget Soundkeeper Alliance 17 (“Soundkeeper”)’s Motion to Enforce and Modify Consent Decree, Dkt. #102. For the following 18 reasons, the Court GRANTS IN PART Soundkeeper’s Motion. 19 II. BACKGROUND 20 21 In this case, Soundkeeper alleged that Defendant Seattle Iron & Metals Corporation 22 (“SIMC”) violated various provisions of Clean Water Act (“CWA”) permits that authorized 23 stormwater and industrial wastewater discharges from SIMC’s facilities in Seattle’s Georgetown 24 neighborhood used for vehicle and scrap metal recycling and storage. Dkt. #38. Relevant here, 25 Soundkeeper alleged that SIMC’s scrap handling activities emit dust and harmful particles into 26 27 the air that contaminate the neighborhood and Duwamish River in violation of the CWA and 28 Resource Conservation and Recovery Act. Id. at 55, 104-08, 134 The parties settled the case via a Consent Decree, which the Court entered on March 3, 1 2 2019. Dkts. #82, #84. Due to needing additional time for necessary “major modification of the 3 design for the auto shredder enclosure to make it more effective[,]” the parties proposed an 4 Amended Consent Decree on September 10, 2020, which this Court entered on October 30, 2020. 5 Dkts. #85 at 2, #88. 6 The Consent Decree contains a force majeure clause allowing delays “outside the 7 8 reasonable control of SIMC,” including those caused by the actions or inactions of third parties. 9 Dkt. #84 at 11-12. “In such event, the time for performance of the task will be extended for a 10 reasonable period of time following the force majeure event.” Id. at 12. Any force majeure event 11 must be disclosed “as soon as reasonably possible but, in any case, no later than fifteen days after 12 13 the occurrence of the event.” Id. at 11. 14 SIMC agreed to build, as mentioned above, an “auto shredder enclosure.” This enclosure 15 was part of a required “deduster” under the Amended Consent Decree, which would work to 16 contain SIMC’s dust emissions. Dkt. #88 at 2. Rather than a particular deadline, SIMC agreed 17 to “exercise its best efforts to obtain all necessary permits” for the deduster. Id. Once permits 18 19 were obtained, SIMC had to install and commence operation of the deduster within 63 weeks or 20 pay $1,000 per day for delays. Id. at 3. 21 Prior to the installation of the deduster, the Amended Consent Decree required dust 22 emission testing conducted in phases. Id. at 5. 23 Phase I, conducted for 10 weeks between May and August of 2019, measured 24 25 “background” dust monitoring at several monitoring sites chosen by Dr. Ranajit Sahu, the parties’ 26 joint consultant. Id. The study was designed to measure “particulate concentrations upwind 27 (South to Southwest)” of SIMC (Dkt. #111, Ex. F. at 1 ) as “to collect samples at locations that 28 were not impacted by SIM[C]’s operations.” Id., Ex. A at 4. 1 2 Phase II, which began June of 2020, required SIMC to continuously monitor dust for one 3 year at two of the same locations as Phase I and at “three additional locations selected by Dr. 4 Sahu on the north, south and east fence lines” of SIMC’s facility. Id. at 6. The purpose of this 5 phase was “intended to document SIMC’s dust emissions prior to installation” of the deduster. 6 Dkt. #88 at 6. 7 8 Lastly, Phase III would not occur until after installation of the deduster. Id. at 6. This 9 would involve two years of continuous monitoring at the same locations as Phase II “to document 10 SIMC’s dust emissions following installation[.]” Id. at 6-7. Under a “corrective action” 11 provision, if Phase III monitoring from “the first dry season” does not show effective dust 12 13 emission reductions to (1) 10 µg/m3, or (2) “the background level determined by Dr. Sahu based 14 on additional data collection,” and show that polychlorinated biphenyl (“PCB”) levels are 15 reduced to the background PCB levels from Phase I, then further enhancements would apply. Id. 16 at 8. This would include more inspections and recommendations by Dr. Sahu. Id. 17 The original Consent Decree also contains a “dispute resolution” clause, which provides: 18 19 In the event of a dispute regarding implementation of, or compliance with, this decree, the parties must first attempt to resolve the dispute by meeting to discuss 20 the dispute and any suggested measures for resolving the dispute. Such a meeting should be held as soon as practical but must be held within thirty (30) days after 21 notice of a request for such a meeting to the other party and its counsel of record. 22 If no resolution is reached at that meeting or within thirty (30) days of the notice, whichever occurs first, either party may file a motion with this court to resolve the 23 dispute.

24 Dkt. #84 at 12. 25 Original deduster design drawing and a City of Seattle permit application were completed 26 27 and approved by Dr. Sahu when the parties proposed the Amended Consent Decree on September 28 10, 2020. After Phase II of the above study, however, SIMC invoked the force majeure clause on March 31, 2023. Dkts. #102 at 6, #108 at 3. In an email to Soundkeeper that day, SIMC 1 2 stated that, while awaiting permits in 2022, the original company contracted to build the deduster, 3 Metso, was acquired by another company. Dkt. #111 at Ex. B. This email notified Soundkeeper 4 that the acquiring company “ha[d] recently indicated to SIMC that it does not intend to honor the 5 September 19, 2019 cont[r]act between Metso and SIMC.” Id. SIMC said they were in 6 “ongoing” negotiations and “evaluating its options[.]” Id. SIMC later retained a different 7 8 company, Wendt, and new designs were underway by the summer of 2023. Dkt. #108 at 3. 9 SIMC provided a “far enough along” design to Soundkeeper in March 2024. Id. at 4. 10 However, while the original deduster estimate was under $1 million, the new design 11 estimate was “at nearly $4M for the equipment alone.” Id. Due to this cost increase, SIMC had 12 13 its environmental consultants “scrutinize” the design “to ensure that it would enable SIMC to 14 achieve the 10 µg/m3 action level prescribed” by the Consent Decree. Id. SIMC alerted 15 Soundkeeper of this on June 21, 2024. Dkt. #102 at 6. 16 On April 2, 2025, SIMC stated that it was continuing work on the deduster design and 17 wanted to discuss “some issues with the Phase II study results” with Dr. Sahu. Id. at 7, #108 at 18 19 7. On April 28, 2025, SIMC requested data from Dr. Sahu, which was provided on August 1 20 directly from the consultant who worked on the study. Id. On August 6, 2025, opining “that 21 SIMC was stalling,” Soundkeeper notified SIMC that it was violating the Amended Consent 22 Decree “for not using its best efforts to obtain the deduster permits” and invoked the Decree’s 23 dispute resolution process. Id. The parties, including SIMC’s environmental consultant and Dr. 24 25 Sahu, had the requested meeting on September 25, 2025, via Zoom. Id. 26 During this September 25 meeting, SIMC’s consultant presented a slideshow with 27 criticisms of the Phase I and Phase II testing. First, SIMC alleged that Dr. Sahu did not exclude 28 data from wildfires during Phase II, which caused SIMC’s data to incorrectly “reflect[] the 1 2 impacts of one of the largest plumes of wildfire smoke to settle over Seattle in recent memory.” 3 Dkt. #108 at 5. As a result, SIMC claimed that its “dry season” average during that time was 4 “well below [the] 10 µg/m3 action level[.]” Id. at 6. Because of this, SIMC asked the consultant 5 to review Phase I. Id. From this, SIMC alleged that Dr.

Free access — add to your briefcase to read the full text and ask questions with AI

Puget Soundkeeper Alliance v. Seattle Iron & Metals Corp., (W.D. Wash. 2026).

Puget Soundkeeper Alliance v. Seattle Iron & Metals Corp. (Puget Soundkeeper Alliance v. Seattle Iron & Metals Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related