Puget Soundkeeper Alliance v. Seattle Iron & Metals Corp.

District Court, W.D. Washington·Decided March 13, 2026·No. 2:12-cv-01201·Unknown

Opinion

WESTERN DISTRICT OF WASHINGTON

PUGET SOUNDKEEPER ALLIANCE, Plaintiff, Case No. C12-1201-RSM v. ORDER GRANTING IN PART PLAINTIFF’S MOTION TO SEATTLE IRON & METALS CORP., ENFORCE AND MODIFY CONSENT DECREE Defendant. I. INTRODUCTION This matter comes before the Court on Plaintiff Puget Soundkeeper Alliance (“Soundkeeper”)’s Motion to Enforce and Modify Consent Decree, Dkt. #102. For the following reasons, the Court GRANTS IN PART Soundkeeper’s Motion. II. BACKGROUND In this case, Soundkeeper alleged that Defendant Seattle Iron & Metals Corporation (“SIMC”) violated various provisions of Clean Water Act (“CWA”) permits that authorized stormwater and industrial wastewater discharges from SIMC’s facilities in Seattle’s Georgetown neighborhood used for vehicle and scrap metal recycling and storage. Dkt. #38. Relevant here, Soundkeeper alleged that SIMC’s scrap handling activities emit dust and harmful particles into the air that contaminate the neighborhood and Duwamish River in violation of the CWA and Resource Conservation and Recovery Act. Id. at 55, 104-08, 134 The parties settled the case via a Consent Decree, which the Court entered on March 3, 2019. Dkts. #82, #84. Due to needing additional time for necessary “major modification of the design for the auto shredder enclosure to make it more effective[,]” the parties proposed an Amended Consent Decree on September 10, 2020, which this Court entered on October 30, 2020. Dkts. #85 at 2, #88. The Consent Decree contains a force majeure clause allowing delays “outside the reasonable control of SIMC,” including those caused by the actions or inactions of third parties. Dkt. #84 at 11-12. “In such event, the time for performance of the task will be extended for a reasonable period of time following the force majeure event.” Id. at 12. Any force majeure event must be disclosed “as soon as reasonably possible but, in any case, no later than fifteen days after the occurrence of the event.” Id. at 11. SIMC agreed to build, as mentioned above, an “auto shredder enclosure.” This enclosure was part of a required “deduster” under the Amended Consent Decree, which would work to contain SIMC’s dust emissions. Dkt. #88 at 2. Rather than a particular deadline, SIMC agreed to “exercise its best efforts to obtain all necessary permits” for the deduster. Id. Once permits were obtained, SIMC had to install and commence operation of the deduster within 63 weeks or pay $1,000 per day for delays. Id. at 3. Prior to the installation of the deduster, the Amended Consent Decree required dust emission testing conducted in phases. Id. at 5. Phase I, conducted for 10 weeks between May and August of 2019, measured “background” dust monitoring at several monitoring sites chosen by Dr. Ranajit Sahu, the parties’ joint consultant. Id. The study was designed to measure “particulate concentrations upwind (South to Southwest)” of SIMC (Dkt. #111, Ex. F. at 1 ) as “to collect samples at locations that were not impacted by SIM[C]’s operations.” Id., Ex. A at 4. Phase II, which began June of 2020, required SIMC to continuously monitor dust for one year at two of the same locations as Phase I and at “three additional locations selected by Dr. Sahu on the north, south and east fence lines” of SIMC’s facility. Id. at 6. The purpose of this phase was “intended to document SIMC’s dust emissions prior to installation” of the deduster. Dkt. #88 at 6. Lastly, Phase III would not occur until after installation of the deduster. Id. at 6. This would involve two years of continuous monitoring at the same locations as Phase II “to document SIMC’s dust emissions following installation[.]” Id. at 6-7. Under a “corrective action” provision, if Phase III monitoring from “the first dry season” does not show effective dust emission reductions to (1) 10 µg/m3, or (2) “the background level determined by Dr. Sahu based on additional data collection,” and show that polychlorinated biphenyl (“PCB”) levels are reduced to the background PCB levels from Phase I, then further enhancements would apply. Id. at 8. This would include more inspections and recommendations by Dr. Sahu. Id. The original Consent Decree also contains a “dispute resolution” clause, which provides: In the event of a dispute regarding implementation of, or compliance with, this decree, the parties must first attempt to resolve the dispute by meeting to discuss the dispute and any suggested measures for resolving the dispute. Such a meeting should be held as soon as practical but must be held within thirty (30) days after notice of a request for such a meeting to the other party and its counsel of record. If no resolution is reached at that meeting or within thirty (30) days of the notice, whichever occurs first, either party may file a motion with this court to resolve the dispute.

Free access — add to your briefcase to read the full text and ask questions with AI

Puget Soundkeeper Alliance v. Seattle Iron & Metals Corp., (W.D. Wash. 2026).

Puget Soundkeeper Alliance v. Seattle Iron & Metals Corp. (Puget Soundkeeper Alliance v. Seattle Iron & Metals Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related