Puerto Rico Telephone Company v. National Labor Relations Board

359 F.2d 983, 62 L.R.R.M. (BNA) 2069, 1966 U.S. App. LEXIS 6363
CourtCourt of Appeals for the First Circuit
DecidedApril 27, 1966
Docket6460
StatusPublished
Cited by29 cases

This text of 359 F.2d 983 (Puerto Rico Telephone Company v. National Labor Relations Board) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Puerto Rico Telephone Company v. National Labor Relations Board, 359 F.2d 983, 62 L.R.R.M. (BNA) 2069, 1966 U.S. App. LEXIS 6363 (1st Cir. 1966).

Opinion

McENTEE, Circuit Judge.

This National Labor Relations Act case comes to us on the petition of the Puerto Rico Telephone Company to set aside and on the cross-petition of the National Labor Relations Board to enforce an unfair *985 labor practice order 1 issued by the Board against the company. The order is based upon the Board’s findings 2 that the company «violated Section 8(a)(5) and (1) of the Act 3 by unilaterally subcontracting work performed by its employees in the bargaining unit without first giving the union 4 *notice and an opportunity to bargain with respect thereof; and also by refusing to furnish the union with relevant information as to the cause of layoffs of unit employees.

During the period involved in this case the company was engaged in a large scale modernization and expansion program mandated by the Puerto Rico Public Service Commission. This program, which began in 1958 and was enlarged in 1961, included, among other things, the removal and replacing of old telephones with dial sets, filling a large number of back orders for new phones, modernizing and expanding central exchanges and long distance circuits, and the installation and addition of' cables. The entire project involved an expenditure of 130 million dollars with completion required by 1964. 5

It was evident from the start that the company could not possibly carry out this program with its regular work force. Accordingly, the company decided to subcontract 6 and did subcontract a substantial amount of the work. It is undisputed that the company’s decision to subcontract was motivated by business considerations. No antiunion animus was involved in this decision, but at no time did the company give the union prior notice or an opportunity to bargain with reference to any of these subcontracts. Most of these subcontracts involved removal and installation of telephones and the distribution and splicing of cable. There is evidence that the company could not have used its own employees exclusively on the program since it needed them to continue providing service at the same time the expansion program was in operation. Furthermore, this program frequently required the services of highly skilled technicians which it would have taken a considerable time to train.

In May of 1959 the company and the union entered into their first collective bargaining agreement which was effective through May 6, 1962. There was no clause in this agreement covering subcontracting. Negotiations for a new agreement began in October of 1961. At that time a number of subcontracts had been let and the company’s subcontracting policy was causing the union serious concern. The union informed the company that it regarded the subcontracting as “a threat to employment.” During this period of negotiations, which resulted in the signing of a new agreement on November 8, 1962, the union made repeated demands for the inclusion of a *986 clause limiting subcontracting. 7 The company resisted these demands on the grounds that subcontracting was its exclusive prerogative and that the use of subcontractors was necessary for the completion of its program. Also, there is evidence that during these negotiations the company assured the union that no unit employees would be laid off because of the company’s subcontracting activities. Despite the negotiations, the parties could not agree on this issue and the upshot of the matter was that no subcontracting clause of any kind was included in the November 8 agreement.

We now reach the crucial period in this case. On November 9, the day after the execution of the new agreement, the company started laying off employees. This continued through March 31, 1963, during which period some 227 unit employees, 41 management employees and 37 temporary employees, were laid off. The employees were told that the layoffs were due to a reorganization of the company. In the course of the next few months the parites had numerous meetings with reference to the layoffs. The union attributed them to the subcontracting. The company denied this and claimed that these layoffs were entirely the result of the “economic reorganization” of the company. It pointed out that the expansion program had reached its peak in mid 1962 and was tapering off; that a recent survey showed the company was greatly overstaffed and that a decision had been made earlier in 1962 to reduce its personnel over a period of time. Also, there was evidence that this “economic reorganization” was motivated, at least in part, by the refusal of the Public Service Commission in June of 1962 to grant a temporary rate increase to the company.

In March of 1963, the parties agreed that the dispute concerning the layoffs would be submitted to the grievance committee established under the November 8 agreement. At the March 14 meeting of this committee the union asked the company to submit data 8 that would prove to the committee that the layoffs were due to “economic reorganization” as claimed. The company rejected this request. The union took the position that since it had been denied the requested information, there was no point in continuing the discussions. It then proposed that the matter be submitted to arbitration but the company would not agree.

This brings us to the issue of whether there is substantial evidence to support the Board’s finding that the company violated the Act by refusing to furnish this information. To be sure, an employer is not required to furnish all the information the union thinks might be helpful in processing grievances. However, an employer violates Section 8(a)(5) and (1) of the Act by refusing during the term of a collective bargaining agreement, to furnish information requested by the union if such information is relevant to a grievance or to the administration or policing of the agreement. Curtiss-Wright Corp., Wright Aero. Div. v. N. L. R. B., 347 F.2d 61, 65 (3d Cir. 1965). As stated in that case at p. 69; “Once relevance is determined, an employer’s refusal to honor a request is a per se violation of the Act.” The company contends that the requested information was irrelevant. We do not agree with this contention. The information requested by the union was relevant in evaluating the pending grievances. The company claimed the layoffs were for economic reasons. The union merely wanted the company to prove that such *987 economic reasons existed. Clearly the data concerning volume of business, earnings, wage savings due to layoffs, etc., became relevant once the company raised the economic issue as the reason for the layoffs. Whether or not the company must furnish the information requested here cannot be separated from the overriding issue of whether or not unilateral subcontracting of the Fibreboard type was taking place as will hereinafter be discussed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sociedad Espanola v. NLRB
414 F.3d 158 (First Circuit, 2005)
Local 2405 Coun. 4 v. State Bd. of Labor, No. Cv91-396523 (Apr. 24, 1992)
1992 Conn. Super. Ct. 3829 (Connecticut Superior Court, 1992)
Amcar Division v. National Labor Relations Board
596 F.2d 1344 (Eighth Circuit, 1979)
Amcar Division v. Natinal Labor Relations Board
596 F.2d 1344 (Eighth Circuit, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
359 F.2d 983, 62 L.R.R.M. (BNA) 2069, 1966 U.S. App. LEXIS 6363, Counsel Stack Legal Research, https://law.counselstack.com/opinion/puerto-rico-telephone-company-v-national-labor-relations-board-ca1-1966.