Public Utility District No. 1 of Snohomish County v. Bonneville Power Administration

506 F.3d 1145, 2007 WL 2948909
CourtCourt of Appeals for the Ninth Circuit
DecidedOctober 11, 2007
Docket04-74240, 04-74245, 04-74252
StatusPublished
Cited by15 cases

This text of 506 F.3d 1145 (Public Utility District No. 1 of Snohomish County v. Bonneville Power Administration) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Public Utility District No. 1 of Snohomish County v. Bonneville Power Administration, 506 F.3d 1145, 2007 WL 2948909 (9th Cir. 2007).

Opinion

BYBEE, Circuit Judge:

Petitioners, publicly owned utilities (“PUDs”) operating in the Pacific Northwest 1 challenge contract amendments entered into in May 2004 (collectively “2004 Amendments”) between the Bonneville Power Administration (“BPA”) and several investor-owned utilities (“IOUs”) arguing that they violate provisions of the Northwest Power Act (“NWPA”). The amendments at issue modify various provisions of several “REP Settlement Agreements” BPA entered into with IOUs in October 2000 and additionally implement a $100M “Reduction of Risk” or “litigation penalty” implemented in agreements between BPA and two IOUs, PacifiCorp and Puget *1148 Sound Energy, in May and June of 2001. In a previously issued opinion, we held that BPA was bound by the power exchange requirements of the Northwest Power Act and exercised its settlement authority contrary to those requirements when it entered into the REP Settlement Agreements. Portland Gen. Elec. Co. v. BPA, 501 F.3d 1009 (9th Cir.2007). Because BPA has not had an opportunity to determine the continued validity of the 2004 Amendments, we remand to the agency to determine in the first instance how to treat the amendments in light of our prior decision and this opinion.

I. BACKGROUND

Our prior opinion in PGE provides a thorough explanation of the underlying regulatory framework, BPA’s operations, and background on the 2000 REP Settlement Agreements which form the basis of the 2004 Amendments at issue here. See 501 F.3d at 1013-14. Additionally, several other of our opinions chronicle the history of BPA and describe its complicated regulatory framework. See, e.g., Golden Nw. Aluminum, Inc. v. BPA, 501 F.3d 1037 (9th Cir.2007); Pub. Power Council, Inc. v. BPA 442 F.3d 1204 (9th Cir.2006); M-S-R Pub. Power Agency v. BPA 297 F.3d 833 (9th Cir.2002) (as amended); Ass’n of Pub. Agency Customers, Inc. v. BPA 126 F.3d 1158 (9th Cir.1997). We only repeat facts necessary for the disposition of this case and refer the reader to our prior opinions for a more comprehensive explanation.

A. The 2001 Load Reduction Agreements

In 2001, while the PGE litigation was pending, the Pacific Northwest experienced a severe drought. Lower precipitation throughout the region coupled with prior BPA decisions and contracts (including the 2000 REP Settlement Agreements which were at issue in PGE, 501 F.3d 1009) put the agency in a position where it could not generate enough power to meet its contractual obligations. BPA’s Administrator warned in a public speech that rate increases of “250 percent or more” were possible since “BPA’s obligations added up to approximately 11,000 megawatts — about 3,000 megawatts more than [its] current generating resources [could] provide on a firm basis.” The Administrator advised that the only way to avoid massive rate increases was for BPA to reduce its 3,000 megawatt short position. In response, BPA developed a three-pronged Load Reduction Program involving conservation by consumers, reduction in power demand by utilities, and load curtailments by its direct service industrial customers. After negotiating several load reduction agreements with various customers, BPA was able to announce that the effort was “absolutely a stunning success” and that it only had to impose a rate increase of 46%, instead of a much higher anticipated increase.

As part of its load reduction plan, BPA entered into Load Reduction Agreements with PacifiCorp and Puget Sound Energy (“PSE”) on May 23, 2001, and June 7, 2001, respectively (collectively “LRAs”). The LRAs eliminated BPAs obligation to deliver virtually all power to PacifiCorp and PSE for the FY 2002-2006 time period in exchange for cash payments. 2 One of *1149 the provisions in the LRAs provided that BPA would reduce the payments to Pacifi-Corp and PSE from $45.49 per MWh of foregone power to $38 per MWh if by December 1, 2001, PacifiCorp and PSE were able to negotiate and enter into litigation settlement agreements with the PUDs and other of BPA’s preference customers. If the PUDs did not enter into agreements by the specified date, the clause would expire and BPA would make cash payments to PacifiCorp and PSE based on the $45.49 rate for the FY 2003-2006 period. This clause — referred to as the “litigation penalty” by the PUDs and a “Reduction of Risk Discount” by BPA 3 — operated as a strong incentive for the PUDs to settle their ongoing litigation (including litigation over the 2000 REP Settlement Agreements) with BPA. If the PUDs settled, the cash payments BPA was obligated to make to PacifiCorp and PSE would be reduced by approximately $200M. If the PUDs refused to settle, they would in effect have to pay an additional $200M to acquire BPA power, as BPA announced it would recover the $200M through its wholesale power rates which would affect all of its customers, including the PUDs.

B. The Defeiral Agreements and the Failed 2003 Global Settlement

When none of the PUDs or other of BPA’s preference customers entered into settlement agreements by the December 1, 2001 deadline, BPA deferred payment of the “litigation penalty” and entered into renewed settlement talks. In anticipation of a broad settlement, PacifiCorp and PSE executed Conditional Deferral Agreements (“CDAs”) in June 2002 with BPA. Under the CDAs, PacifiCorp and PSE agreed to defer payment of the $200M beginning October 1, 2002, while settlement discussions progressed. The payments would be automatically deferred for continuing six month periods unless PacifiCorp or PSE elected to terminate the deferral period. BPA agreed to pay the companies 4.46 percent interest on the $200M during the deferral period. In 2003, BPA proposed a global litigation settlement which called for the preference customers to agree to a new formula for IOU benefits for FY 2007-2011; dismiss all their pending Ninth Circuit litigation, including challenges to the 2000 REP Settlement Agreements; and enter “covenants not to sue” regarding future claims. In exchange, the IOUs would waive payment of the $200M litigation penalty. In a Record of Decision published October 21, 2003 (“2003 ROD”), BPA made it clear that if the settlement failed, it would raise rates in order to pay the litigation penalty to PacifiCorp and PSE. 4

BPA failed to garner the required unanimous support for its settlement proposal by the January 21, 2004, deadline. A day later, BPA issued a press release announcing that the agreement had failed and giving notice that it was implementing the $200M litigation penalty: “[h]ad the proposal succeeded, BPA’s wholesale power rates would have dropped by nearly 7 percent, retroactive to Oct. 1, 2003....

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
506 F.3d 1145, 2007 WL 2948909, Counsel Stack Legal Research, https://law.counselstack.com/opinion/public-utility-district-no-1-of-snohomish-county-v-bonneville-power-ca9-2007.