TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN
NO. 03-02-00547-CV
Public Utility Commission of Texas and South Texas Electric Cooperative, Inc., Appellants
v.
City Public Service Board of San Antonio, Appellee
FROM THE DISTRICT COURT OF TRAVIS COUNTY, 201ST JUDICIAL DISTRICT NO. 97-11665, HONORABLE PAUL DAVIS, JUDGE PRESIDING
OPINION
In this appeal, we must decide whether the Public Utility Commission exceeded its statutory
authority by conducting a proceeding to determine the transmission cost of service (TCOS) for the City
Public Service Board of San Antonio (San Antonio) as a part of its regulatory oversight of the wholesale
energy market under the Public Utility Regulatory Act of 1995 (PURA 95). A utility=s TCOS includes all
reasonable and necessary expenses, plus a reasonable return on investments, associated with owning and
operating its transmission network. The Commission held individual TCOS proceedings for every utility in
the statewide power-transmission grid. Then, the Commission proceeded to use the utilities= TCOS
numbers to set statewide rates for use of transmission lines in wholesale energy transactions. While the Commission was conducting these proceedings, San Antonio brought a declaratory-judgment action
challenging the Commission=s authority to enact a wholesale rate-setting scheme under PURA 95. San
Antonio eventually prevailed when the supreme court declared the rate-setting rules to be invalid. See
Public Util. Comm=n v. City Pub. Serv. Bd. of San Antonio, 53 S.W.3d 310, 325 (Tex. 2001). Relying
on the supreme-court decision, the district court Areversed and vacated@ the Commission=s order in San
Antonio=s TCOS case. The Commission appeals,1 contending that although it cannot use the TCOS
numbers to set rates, it can use them to carry out its other responsibilities under PURA 95. Because we
think that determining a utility=s TCOS number is tantamount to setting its transmission-service rates, we
affirm the district court=s judgment reversing the Commission=s order.
BACKGROUND
Texas utilities have voluntarily interconnected their regional transmission networks to form a
single grid called the Electric Reliability Council of Texas (ERCOT). When power is sold in a wholesale
transaction, it is transported over this ERCOT grid. Prior to PURA 95, utilities whose transmission
networks were directly connected within the grid could sell power to one another in Abundled@ transactions
which used a single rate to cover generation, transmission, and distribution services. However, not all
1 In addition to the Commission, an intervenor, South Texas Electric Cooperative, Inc., urges us to reverse the trial court=s judgment. Because its arguments are substantially the same as the Commission=s, we will treat them together.
2 wholesale transactions were between utilities with directly connected networks; many such transactions
required power to be transmitted or Awheeled@ over the networks of other utilities. In these cases,
payments to the wheeling utilities were negotiated on a case-by-case basis. PURA 95 eliminates these
distinctions and requires utilities to offer nondiscriminatory access to their transmission facilities and to
charge uniform rates for such access.
PURA 95
In 1995, the legislature amended PURA to promote competition in the wholesale electricity
market. See Act of May 28, 1995, 74th Leg., R.S., ch. 765, ' 2.01(a), 1995 Tex. Gen. Laws 3972,
3988-89 (codified at Tex. Util. Code Ann. ' 31.001(c)). The centerpiece of PURA 95=s wholesale-
deregulation scheme is a requirement that electric utilities provide open access to their transmission facilities.
See id. ' 2.08, 1995 Tex. Gen. Laws at 4000 (Tex. Util. Code Ann. ' 35.004, since amended). In this
open-access regime, each utility must provide transmission service at rates and terms comparable to what it
costs the utility to operate its own system. Id. This requires the utilities to separate or Aunbundle@ the costs
associated with their transmission facilities from the costs associated with their generation and distribution
facilities.
PURA 95 gives the Commission several responsibilities related to oversight of the
transmission-service market. The Commission is directed to ensure that each utility provide transmission
service in a nondiscriminatory manner, and recover its reasonable costs in providing such transmission
service so that the utility=s other customers are not required to bear those costs. See id. PURA 95 also
3 provides that A[t]he [C]ommission may require a utility . . . to provide transmission service at wholesale to
another utility . . . and may determine whether the terms and conditions for the transmission service are
reasonable.@ See id. ' 2.07, 1995 Tex. Gen. Laws at 3999 (Tex. Util. Code Ann. ' 35.005, since
amended). Moreover, the Commission is authorized to require parties with wholesale-transmission disputes
to submit to nonbinding alternative dispute resolution. See Tex. Util. Code Ann. ' 35.008 (West 1998). In
order to fulfill these responsibilities, the Commission must Aadopt rules relating to wholesale transmission
service, rates, and terms.@ See id. ' 35.006(a) (emphasis added). Utilities that own transmission facilities
are, in turn, required to Afile a tariff in compliance with [C]ommission rules.@ See id. ' 35.007(a).
The Rules
The Commission adopted rules governing wholesale-transmission in 1996. See 21 Tex.
Reg. 1397 (1996), adopting 16 Tex. Admin. Code ' 23.67 [hereinafter Rule 23.67], and 21 Tex. Reg.
3343 (1996), adopting 16 Tex. Admin. Code 23.70 [hereinafter Rule 23.70]. These rules required each
ERCOT utility to pay every other ERCOT utility a Afacilities charge@ for transmission service. See Rule
23.67(g). Each ERCOT utility was to pay this facilities charge in its capacity as a transmission customer,
and to receive a portion of the facilities charges paid by other utilities in its capacity as a transmission
provider. This facilities charge had two components, an Aimpact fee@ and an Aaccess fee.@ See Rule
23.67(g)(1). The impact fee made up thirty percent of the facilities charge and was calculated based upon
the distance traveled by the electricity in the transmission customer=s wholesale transactions. See id.; Rule
23.70(o); City Pub. Serv. Bd. v. Public Util. Comm=n, 9 S.W.3d 868, 872-73 (Tex. App.CAustin
4 2000), aff=d, 53 S.W.3d 310 (Tex. 2001). The access fee, which made up the remaining seventy percent
of the facilities charge, was not distance sensitive. The yearly access fee paid by each utility in its capacity
as a transmission customer was to be based on its percentage of use of the ERCOT grid. More precisely,
the access fee was to reflect the transmission customer=s percentage of the peak-load quantity of electricity
channeled through the ERCOT grid, applied to the TCOS for the entire grid. See City Pub. Serv. Bd., 53
S.W.3d at 314; City Pub. Serv. Bd., 9 S.W.3d at 872; Rule 23.67(g). To calculate access fees, the
Commission was first to determine each ERCOT utility=s TCOS, which consists of its reasonable and
necessary expenses, plus a reasonable return on its investments, related to owning and operating
transmission lines. The Commission was to aggregate those costs to arrive at the TCOS for the entire grid.
The Commission was then to determine the maximum amount of electricity carried on the grid at any one
time during the relevant period, or its Atotal peak load@ and each utility=s percentage of that total. City Pub.
Serv. Bd., 53 S.W.3d at 314; see City Pub. Serv. Bd., 9 S.W.3d at 872; Rule 23.67(g)(1), (5). Each
transmission customer=s access fee was then calculated by multiplying its percentage of the aggregate peak
load for the ERCOT grid by the TCOS for the entire grid. City Pub. Serv. Bd., 53 S.W.3d at 314; see
Rule 23.67(g)(1). Relatedly, the amount that each ERCOT utility received in its capacity as a transmission
provider was to be determined by its individual TCOS as a percentage of the aggregate TCOS for the
entire grid.
To set transmission rates pursuant to its rules, the Commission initiated a series of individual
proceedings to determine the TCOS for each ERCOT utility. It also initiated a companion generic
proceeding to resolve common issues and set the transmission rates using the costs determined in the
5 individual cases. The generic proceeding and the individual proceedings worked together. The Commission
issued a preliminary order separating the general issues to be determined in the generic proceeding from the
utility-specific issues to be determined in the individual proceedings. Once the TCOS numbers were
determined in the individual proceedings, the Commission used those numbers in the generic proceeding to
set transmission-service ratesCi.e., to determine the exact amount that each ERCOT utility was to pay
every other ERCOT utility according to the formula described above.
San Antonio=s Challenge to the Rules
While these proceedings were taking place, San Antonio and Houston Lighting and Power
Company each filed declaratory-judgment actions claiming that the Commission had exceeded its statutory
authority in promulgating its wholesale-transmission rules. The causes were consolidated and the trial court
ruled in favor of the Commission. This court then reversed the trial court, agreeing with the utilities that the
Commission had exceeded its authority in promulgating its rules. See City Pub. Serv. Bd., 9 S.W.3d at
877-78. We reasoned that PURA 95 did not grant the Commission authority to establish any transmission-
access rate, regardless of the methodology. See id. at 873. In reaching this conclusion, we explained that
PURA 95 gave the Commission oversight of wholesale transmission service, but not the authority to set
rates initially:
We believe that the subchapter [dealing with wholesale transmission service], read in context, contemplates that negotiations between parties regarding transmission-access pricing be voluntary and contractual. Should a party be dissatisfied with the outcome of the negotiations, that party may then seek the aid of the [Commission], which can either order
6 the parties to submit to alternative dispute resolution, or may settle the dispute by establishing a reasonable rate after notice and a contested-case hearing.
See id. at 875. The supreme court affirmed, agreeing that PURA 95 does not grant the Commission
authority to set wholesale transmission rates for municipally owned utilities such as San Antonio, which are
not otherwise subject to the Commission=s traditional ratemaking authority.2 It further elaborated on the
Commission=s oversight role in resolving disputes between the requesting and providing utilities in a way that
ensures that the transmission provider is offering nondiscriminatory access to its network at a reasonable
rate and that the transmission provider=s customers are not unfairly bearing the transmission costs inflicted by
the requesting utility. See City Pub. Serv. Bd., 53 S.W.3d at 320. The Commission does not have the
power to set wholesale transmission rates as an initial matter, but once a dispute arises, it can either refer the
parties to alternative dispute resolution, or it can set a reasonable rate to resolve that dispute. Id. The
supreme court added that the Commission has the independent ability to order utilities to appear before it
2 The supreme court did, however, find that the traditional, broad power of the Commission to Aestablish and regulate@ rates for investor-owned utilities, such as Houston Lighting and Power Company, encompassed the power to set wholesale transmission rates for those utilities. The court nonetheless affirmed our invalidation of the rules with respect to investor-owned utilities on the ground that the access fee violates the provisions of PURA 95 prohibiting subsidies among utilities and requiring that rates for wholesale transmission service be comparable to each utility=s use of its own system. See Public Util. Comm=n v. City Pub. Serv. Bd. of San Antonio, 53 S.W.3d 310, 323-24 (Tex. 2001).
7 even without a dispute to ensure that they are providing non-discriminatory access and to protect their
customers from bearing others= transmission costs.
San Antonio=s TCOS Case
While the declaratory-judgment action was on appeal, San Antonio sought judicial review
of its TCOS as determined by the Commission after the contested-case proceeding. See Tex. Gov=t
Code Ann. ' 2001.171 (West 2000). San Antonio alleged that the Commission had ignored or
underestimated certain portions of its transmission costs and had therefore set a TCOS number that was too
low. The district court initially affirmed the Commission=s order. But shortly after we declared the
transmission rules invalid in the declaratory-judgment appeal, the district court granted San Antonio=smotion
for new trial, vacated its earlier judgment, and abated the cause pending the final resolution of the
declaratory-judgment action. Once the supreme court ruled that the transmission rules were invalid, the
district court conducted a new hearing and received additional briefing to review San Antonio=s TCOS.
San Antonio argued that the Commission=s order setting its TCOS should be vacated and declared void and
invalid for lack of agency authority. The Commission argued that the court should affirm the agency order.3
The district court vacated the Commission=s order, declaring it to be Avoid and invalid as exceeding the
authority and jurisdiction of the [Commission].@ On appeal, the Commission asserts that although the
3 The Commission also argued that district court was not authorized to vacate the order but could only reverse and remand to the agency. See Tex. Gov=t Code Ann. ' 2001.174 (West 2000).
8 TCOS proceedings were initially conducted as part of a rate-setting scheme, it has other responsibilities that
empower it to determine the TCOS of individual utilities.
DISCUSSION
This is a suit for judicial review of a Commission decision made after a contested
case. See Tex. Util. Code Ann. ' 15.001 (West 1998); Tex. Gov=t Code Ann. ' 2001.171 (West
2000). The trial court was therefore authorized to reverse the case if the agency=s findings,
inferences, conclusions, or decisions were in excess of the agency=s statutory authority. See Tex.
Gov=t Code Ann. ' 2001.174(2)(B). This ground for reversal presents a question of law that we
review de novo. See Texas Dep=t of Transp. v. Jones Bros. Dirt & Paving Contractors, 24 S.W.3d
893, 898 (Tex. App.CAustin 2000), rev=d on other grounds, 92 S.W.3d 477 (Tex. 2002). The
Commission has only those powers conferred upon it by the legislature in clear and unmistakable
language. City Pub. Serv. Bd., 53 S.W.3d at 315-16; Public Util. Comm=n v. GTE-Southwest,
Inc., 901 S.W.2d 401, 407 (Tex. 1995). When the legislature expressly confers a power on an
agency, it also impliedly intends that the agency have whatever powers are reasonably necessary
to fulfill its express functions or duties. See GTE-Southwest, Inc., 901 S.W.2d at 407. An agency
may not, however, exercise what is effectively a new power on the theory that such exercise is
expedient for the agency=s purposes. See id.
The Commission concedes that at the time it conducted San Antonio=s contested-
case proceeding, it intended to use the TCOS number to set rates in the generic rate
9 proceedingCa use beyond its statutory authority. However, the Commission asserts that the
reviewing court is not bound by the reasons given in an agency order and may affirm if there is
any valid legal basis for the agency action. See Central Power & Light Co. v. Public Util.
Comm=n, 36 S.W.3d 547, 559 (Tex. App.CAustin 2000, pet. denied). The Commission argues that
the oversight responsibilities contemplated by PURA 95 invest it with the authority to initiate a
proceeding to determine San Antonio=s TCOS, even though it may not impose rates. San Antonio
rejoins that determining a utility=s TCOS is tantamount to setting its transmission rates. We
agree that the TCOS case was an integral part of the invalid rate-setting scheme.4
Under traditional electric-utility regulation, large, vertically integrated utilities
operated as monopolies in the areas they served. These utilities would generate, transmit, and
retail electricity to end-use customers. The Commission was authorized to set rates for each
investor-owned utility at a level that would allow it to recoup its prudently incurred costs and to
earn a reasonable return on its investments. See id. at 553; 16 Tex. Admin. Code '' 25.231,
.235(a) (2002). The TCOS determination applies these same rate-setting principles to the
wholesale transmission market. That is, the final TCOS number represents the utility=s
4 In 1999, the legislature amended PURA and authorized the Commission to set wholesale transmission rates using a method similar to that invalidated by the supreme court. See Tex. Util. Code Ann. ' 35.004(d) (West Supp. 2003). In this opinion, however, we are concerned only with the authority of the Commission to determine a utility=s TCOS when it issued its final order in 1997.
10 reasonable and necessary expenses, together with a reasonable return on its prudently invested
capital, involved in operating its transmission facilities. As San Antonio points out, this number is
the first and most essential part of establishing a final rateCit sets the amount to be recovered.
The only thing left to do is apply some methodology that determines how the amount is to be
recovered. Before its rules were invalidated, the Commission used the formula described above
as its rate-setting methodology.
Because the Commission admits that it initiated the TCOS proceeding for a purpose that
was undoubtedly beyond the scope of its authorityCto set rates as an initial matterCits final order must be
reversed unless it had some independent basis of authority to initiate such a case. The Commission asks us
to find such authority in its oversight responsibilities. It claims that it cannot determine whether San Antonio
is providing reasonable rates or being forced to subsidize other utilities without first knowing the costs
associated with its provision of transmission service. The Commission also argues that its authority to
oversee San Antonio=s separation of functions encompasses the authority to determine its TCOS.5 We
reject the Commission=s arguments.
5 To support this claim, it cites to a rule requiring utilities to make filings with the Commission separating out their costs and rates, based on the costs associated with their generation, transmission, and distribution operations. In the declaratory-judgment case, the supreme court referred to this rule as an example of Commission authority to Aadopt rules relating to wholesale transmission service, rates, and
11 access@Cwhich the Commission was entitled to do under PURA 95. See City Pub. Serv. Bd., 53 S.W.2d at 319. The Commission apparently argues that the separation of a utility=s Acosts and rates@ associated with it transmission operations from the Acosts and rates@ associated with its generation and distribution operations requires a determination of a utility=s TCOS.
12 The supreme court clearly held that the Commission was not authorized to set rates for
municipally-owned utilities outside of a dispute-resolution context. See City Pub. Serv. Bd., 53 S.W.3d at
320. In so holding, it explicitly referenced the Commission=s oversight responsibilities in a context that
contrasted them with rate-setting. See id 320-21. It would elevate form over substance for us to hold that
although the Commission cannot set San Antonio=s rates, it can nonetheless determine, to the penny, the
precise amount of San Antonio=s reasonable and necessary expenses together with a reasonable
return on its prudently invested capitalCi.e., the precise amount it would be allowed to recover if the
Commission were to set rates. To allow the Commission to develop this number apart from its role of
resolving a dispute, and to Ause@ it to check reasonableness or conduct its other oversight functions bears
too close a nexus to actual rate-setting to withstand scrutiny.
The Commission asks us to draw a hypertechnical distinction between determining San
Antonio=s TCOS and determining how San Antonio=s TCOS is to be recovered. We recognize that, in
carrying out its oversight responsibilities, the Commission must take some measure of the costs associated
with San Antonio=s transmission facilities; however, such authority simply cannot encompass an initial
determination of a municipal utility=s TCOS, which is tantamount to an initial determination of its wholesale
13 transmission rates.6 We hold that the Commission was without authority to conduct TCOS proceedings for
municipally owned utilities such as San Antonio, and overrule the Commission=s single issue.7
Upon finding that the Commission had exceeded its statutory authority in conducting its
TCOS proceeding, the district court Areversed and vacated@ the Commission=s order, which it found to be
Avoid and invalid@ as exceeding the Commission=s authority. This is a suit for judicial review governed by
section 2001.174 of the government code. That section authorizes the trial court to reverse and remand
if the agency=s findings, inferences, conclusions, or decisions exceeded its statutory authority.
See Tex. Gov=t Code Ann. ' 2001.174(2)(B); Texas State Bd. of Pharmacy v. Seely, 764 S.W.2d
806, 815 (Tex. App.CAustin 1988, writ denied) (holding that remand is proper judgment following
6 We note that even if a determination of a utility=s TCOS number were conceptually distinct, in some meaningful way, from setting its rates initially, there surely would be little or no practical distinction in situations where a utility attempts to charge a rate that would allow it to recover more than its predetermined TCOS. Such a rate would immediately be Adisputed@ by its transmission customers and the Commission could then step in to resolve this manufactured dispute by setting a rate. 7 The Commission also attempts to argue that this very TCOS proceeding, where San Antonio=s costs were disputed by several intervening utilities, represents a dispute that it can resolve by setting reasonable rates. This circular argument has no merit, as such disputes only arose in the context of this invalid rate-setting procedure.
14 reversal of agency order). The court was not, in these circumstances, authorized to vacate the
agency=s order. See BFI Waste Sys., Inc. v. Martinez Envtl. Group, 93 S.W.3d 570, 581 (Tex.
App.CAustin 2002, pet. filed).
CONCLUSION
The Commission was without authority to determine San Antonio=s TCOS apart from a
dispute which would entitle it to set rates. Because the appropriate remedy in this case was reversal and
remand to the Commission, we modify the judgment of the trial court to reverse the agency order and
remand the case to the agency. As modified, we affirm the trial-court judgment.
Bea Ann Smith, Justice
Before Chief Justice Law, Justices B. A. Smith and Yeakel
Modified and, as Modified, Affirmed
Filed: April 24, 2003